9 MILESTONE SCHEDULES
Project milestone schedules contain such information as :
Project start date
Project end date
Other major milestone
Project start and end date, if known, must be included. Other major milestones such as
review meeting, prototype available, procurement, testing, and so
TABLE 11-2. SPESIFICATION FOR STATEMENT OF WORK
Description Specification No.
Civil 100 (Index)
Concrete 101
Field equipment 102
Piling 121
Roofing and siding 122
Soil testing 123
Structural design 124
Electrical 200 (Index)
Electrical testing 201
Heat tracing 201
Motors 209
Power systems 225
Switchgear 226
Synchronous generators 227
HVAC 300 (Index)
Hazardous environment 301
Insulation 302
Refrigeration piping 318
Sheet metal ductwork 319
Installation 400 (Index)
Conveyors and chutes 401
Fired heaters and boilers 402
Heat exchangers 403
Reactors 414
Towers 415
Vessels 416
Instruments 500 (Index)
Alarm system 501
Control valves 502
Flow instruments 503
Level gages 536
Pressure instruments 537
Temperature instruments 538
Mechanical equipment 600 (Index)
Centrifugal pumps 601
Compressor 602
High-speed gears 603
Material handling equipment 640
Mechanical agitators 641
Steam turbines 642
Piping 700 (Index)
Expansion joints 701
Field pressure testing 702
Installation of piping 703
Pipe fabrication specs 749
Pipe supports 750
Steam tracing 751
Project administration 800 (Index)
Design drawings 801
Drafting standards 802
General requirements 803
Project coordination 841
Reporting procedure 842
Vendor data 843
Vessels 900 (Index)
Fireproofing 901
Painting 902
Reinforced tanks 948
Shell and tube heat exchangers 949
Steam boilers 950
Vessel linings 951
on, should also be identified. The last topic, data items, is often overlooked. There are two
good reasons for preparing a separate schedule for data item. First, the separate schedule
will indicate to line managers that personnel with writing skills may have to be assigned. Second,
data items require direct-labor man-hours for waiting, typing, editing, proofing, retyping, graphic
art, and reproduction. Many companies identify on the data items schedules the approximate
number of pages per data items, and each data items is priced out a cost per page, say $250/page.
Pricing out data items separately often induces customers to require fewer reports.