Table of Contents
REPORT OVERVIEW 3
STRUCTURE 6
ROOFING 7
EXTERIOR 11
ELECTRICAL 14
HEATING 16
INSULATION / VENTILATION 22
PLUMBING 23
INTERIOR 25
MOLD INSPECTION 28
FIRE PROTECTION 29
SITE MAP 32
                                                                                                   Report Overview
THE BUILDING IN PERSPECTIVE
   This project summary is not to be used alone. The attached report is intended to be read in its entirety. Definitions of the
   terms used in the Report Overview to describe average or overall conditions include the following: Excellent – In “like new”
   condition and/or high quality materials used. Good –no remedial work is recommended; Fair – system is aging and/or minor
   remedial work is recommended; and Poor – replacement or major remedial work is recommended. Where it seemed more
   appropriate, Structure & Site assigned combination assessments such as “fair to good” in evaluating various construction
   components. The table displays estimated repair and/or replacement costs. The estimated costs are preliminary and are
   based upon Structure &Site’s experience in conducting similar projects. The actual cost will be affected by factors such as
   duration of time to correction, site access, market conditions, and other contingencies applied by the owner. Immediate costs
   are highlighted in Green and short term costs (1 – 3 Years) is highlighted in Yellow.
                                                                                                     Immediate      Capital
                         Item                    Excellent   Good      Fair     Poor     Action*      Needs**      Reserves**
       SITE IMPROVEMENTS
       Storm Drain System                                     X                            NM
       Parking Pavement, Curbs & Gutters                                X                  RR                            $8,000
       Sidewalks                                              X                            NM
       Utilities                                              X                            NM
       Landscaping                                            X                            NM
       Site Lighting                                          X                            NM
       Site & Building Signage                                                             NA
       STRUCTURAL SYSTEMS AND BUILDING ENVELOPE
       Foundations                                            X                            NM
       Structural System Including Floors                     X                            NM
       Exterior Walls, Patch & Paint                                    X                   RR                           $4,000
       Windows & Frames                                                 X                  NM
       Exterior Doors & Frames                                          X                  NM
       Stairs (Interior & Exterior)                                               X         IR             $500
       Balconies & Upper Floor Walkways                                 X                  NM
       Roof Coverings                                                             X       IR/RR          $2,000         $70,000
       Roof Drainage                                                    X                  NM
       MECHANICAL, ELECTRICAL & PLUMBING SYSTEMS
       HVAC                                                                       X       IR/RR          $1,000         $15,000
       Electrical                                             X                            NM
       Emergency Generator                                                                  NA
       Hot & Cold Water Distribution System                   X                             NA
       Water Heaters                                                    X                  RR                              $600
       Gas Distribution System                                X                            NM
       VERTICAL TRANSPORTATION CONVEYING SYSTEMS
       Elevators/ Escalators                                                                NA
       FIRE/ LIFE SAFETY
       Fire Suppression Systems                                         X                   IR             $500
       Security Alarm Systems                                                               NA
       INTERIOR ELEMENTS
       Common Area Finishes                                             X                  NM
       Warehouse Area Finishes (Walls, Floors,
       Ceilings, Etc.)                                                  X                  NM
       Interior Doors & Frames                                          X                  NM
       “BARRIER FREE” ACCESSIBILITY (ADA)
        Parking, Signage & Ramps                                          X              IR            $750
        Common Area Accessibility Including
        Restrooms                                                         X              IR          $2,000
   *Action: NM = Normal Maintenance, IR = Immediate Repair/Replacement, RR = Replacement Reserves, NA = Not Applicable, NA=Not
   Applicable, **All costs are estimated and reported as Un-inflated Values
   Scope
   Structure & Site’s scope of services for this assessment included a visit to the property with observations of the property and
   its improvements, reviews of available construction and maintenance documents, and interviews with various persons. The
   purpose of these observations was to assess the general physical condition and maintenance status of the property and to
   recommend repair and operation and/or to be restored to a good condition consistent with comparable properties of similar
   age. The assessment was performed in general accordance with ASTM E 2018-99, Standard Guide for Property Condition
   Assessments: Baseline Property Condition Assessment Process.
   Opinions of cost for recommended repairs have been prepared and divided into two categories: Immediate repair needs and
   Short term needs. Immediate Repair Needs are those repairs that are beyond the scope of regular maintenance that should be
   performed within one year of the date of the report. Short-term needs are those items needing repair or replacement to remedy
   physical deficiencies, such as deferred maintenance, that are beyond the scope of regular maintenance that should be
   undertaken on a priority basis within one to two years.
   Structure & Site has prepared one comprehensive Property Condition Report that includes pertinent information from
   building (s) present on the subject property. Structure & Site has provided the standard Property Summary Table normally
   utilized in Structure & Site Property Condition Reports. Structure & Site has provided suggestions for repairs and upgrades
   of selected maintenance items that are not considered “deferred maintenance.” These suggestions have been provided to
   assist the user in identifying certain maintenance issues that may prolong the life of the respective systems. Suggestions for
   repairs and upgrades have been provided for selected conditions and should not be considered all-inclusive. Structure & Site
   has provided general information pertaining to out of scope issues including ADA Compliance and potential microbial
   growth or potential growth issues. No comment is offered on environmental conditions or asbestos containing materials.
Structure & Site representative Martin Pasquinelli conducted the subject property inspection on July 16, 2010 from 9:00 a.m.
until 11:00 a.m. No owner representative was on-site.
Utilities Provided
   Electrical service – DTE Energy
   Natural gas service – Consumers Energy
   City water and sewer service – Municipal supply from Detroit Water
Please refer to the pre-inspection contract for a full explanation of the scope of the inspection.
                                                                                                                     Structure
DESCRIPTION OF STRUCTURE
    Foundation:                                   •Poured Concrete •Masonry Block •Slab on Grade
    Columns:                                      •Steel
    Floor Structure:                              •Concrete
    Wall Structure:                               •Masonry
    Roof Structure:                               •Open-Web Roof Joists •Metal Decking
STRUCTURE OBSERVATIONS
    General Comments
    The construction of the building is good quality. The materials and workmanship, where visible, are good. The inspection
    did not discover evidence of substantial structural movement.
    RECOMMENDATIONS / OBSERVATIONS
    Foundation
    • Monitor: Common minor settlement cracks were observed in the foundation walls. This implies that some structural
       movement of the building has occurred. Cracks of this type should be watched for any sign of additional movement. In
       the absence of any sign of ongoing movement, repair should not be necessary.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Structural components concealed behind finished surfaces could not be inspected.
    • Only a representative sampling of visible structural components were inspected.
    • Furniture and/or storage restricted access to some structural components.
    • Engineering or architectural services such as calculation of structural capacities, adequacy, or integrity are not part of a
         building inspection.
    Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                    This confidential report is prepared exclusively for sample review
                                                                                                                   © 2010 Structure & Site
                                                                                                                   Pages 7 of 32
                                                                                                                  Roofing
DESCRIPTION OF ROOFING
   Roof Covering:                               •Asphalt •Estimated Age 20+ Years
   Roof Flashings:                              •Metal
   Chimneys:                                    •Metal
   Roof Drainage System:                        •Metal •Downspouts discharge above grade
   Method of Inspection:                        •Viewed by walking on roof
ROOFING OBSERVATIONS
   General Comments
   This quality of roof material has a typical lifespan of 20 years. Many factors influence the longevity of roofs including;
   weather, quality of shingle and installation method, proximity of tree limbs, degree of slope and amount of rooftop
   ventilation. Roofs with multiple layers of cover typically have a shorter life span and require additional costs for removal
   when re-roofing becomes necessary. Properly sloped roofs usually last longer than flat roofs.
   RECOMMENDATIONS / OBSERVATIONS
   Flat Roofing
   • Monitor: The roofing is in fair condition. We did not see evidence of active leaks nor need for immediate major repair.
   • Repair: Repairs to the roofing are needed. Damaged or missing roofing material should be repaired. All roof
       penetrations should be examined and sealed as necessary.
   • Monitor: Prior repairs to the roofing are evident. This would suggest that problems have been experienced in the past.
       This area should be monitored.
   Flashings
   • Repair: The flashing is loose and should be re-secured to avoid leaks.
   Chimneys
   • Repair: The metal chimney is rusting. It should be painted with an appropriate paint or replaced.
   Gutters & Downspouts
   • Repair: The downspout(s) should discharge water at least five (5) feet from the building. Storm water should be
      encouraged to flow away from the building at the point of discharge.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Not all of the underside of the roof sheathing is inspected for evidence of leaks.
    • Evidence of prior leaks may be disguised by interior finishes.
    • Estimates of remaining roof life are approximations only and do not preclude the possibility of leakage. Leakage can
         develop at any time and may depend on rain intensity, wind direction, ice build up, and other factors.
    • Antennae, chimney/flue interiors which are not readily accessible are not inspected and could require repair.
    • Roof inspection may be limited by access, condition, weather, or other safety concerns.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                                   Exterior
DESCRIPTION OF EXTERIOR
   Wall Covering:                               •Brick •Metal
   Eaves, Soffits, and Fascias:                 •Metal
   Exterior Doors:                              •Metal
   Window/Door Frames and Trim:                 •Metal-Covered
   Entry Driveways:                             •Asphalt •Concrete
   Entry Walkways:                              •Concrete
   Overhead Garage Doors:                       •Steel
   Surface Drainage:                            •Level Grade
   Retaining Walls:                             •Concrete
EXTERIOR OBSERVATIONS
   General Comments
   The exterior of the building is generally in good condition.
   RECOMMENDATIONS / OBSERVATIONS
   Exterior Walls
   • Repair: Localized pointing of deteriorated mortar between the bricks of the exterior walls is advisable to prevent further
      deterioration.
   • Repair: The block should be painted to preserve the material.
   Windows
   • Repair: The windows require caulking.
   Driveway
   • Repair: The driveway surface is in a semi-deteriorated condition. Resurfacing is necessary to correct this condition.
   Retaining Wall
   • Monitor: The retaining wall shows evidence of movement. This condition should be monitored. It is impossible to
      determine the rate of movement during a one time visit to the building.
View of truck well. Vegetation and debris needs to be cleared from truck well drain.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • A representative sample of exterior components was inspected rather than every occurrence of components.
    • The inspection does not include an assessment of geological, geotechnical, or hydrological conditions, or environmental
         hazards.
    • Screening, shutters, awnings, or similar seasonal accessories, fences, recreational facilities, outbuildings, seawalls, break-
         walls, docks, erosion control and earth stabilization measures are not inspected unless specifically agreed-upon and
         documented in this report.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                                  Electrical
DESCRIPTION OF ELECTRICAL
   Size of Electrical Service:                   •120/240 Volt Main Service - Service Size: 400 Amps
   Service Drop:                                 •Overhead
   Service Entrance Conductors:                  •Not Observed
   Service Equipment &
   Main Disconnects:                             •Main Service Rating 400 Amps •Breakers
   Service Grounding:                            •Ground Rod Connection •Water Pipe Connection
   Ground Fault Circuit Interrupters:            •Present (insufficient)
ELECTRICAL OBSERVATIONS
   General Comments
   Generally speaking, the electrical system is in good order. Dedicated 220 volt circuits have been provided for all 220 volt
   appliances within the building. The size of the electrical service appears to be sufficient for the current usage of building. If
   usage of building changes from its current application, it is recommended that a professional electrician evaluate the service
   to determine capacity for changing usage of the building’s infrastructure. It is possible that significant costs can occur in
   order to upgrade or otherwise modify the buildings electrical capacity. This is an issue to be further investigated if
   modifications to the building or additional process equipment are installed.
   RECOMMENDATIONS / OBSERVATIONS
   • Important Safety Notice: All electrical repairs listed in this report should be considered as important safety items as
      they present risk of fire or shock. These items should receive high priority for action.
   Outlets
   • Repair: The installation of ground fault circuit interrupters (GFCI) is recommended at all outlets that are within four
      feet of a water source. GFCI offers increased protection from shock or electrocution.
   • Repair: Missing outlet cover plates should be replaced to avoid a shock hazard.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Electrical components concealed behind finished surfaces are not inspected.
    • Only a representative sampling of outlets and light fixtures were tested.
    • Furniture and/or storage restricted access to some electrical components which may not be inspected.
    • The inspection does not include remote control devices, alarm systems and components, low voltage wiring, systems,
         and components, ancillary wiring, systems, and other components which are not part of the primary electrical power
         distribution system.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                                 Heating
DESCRIPTION OF HEATING
   Energy Source:                               •Gas
   Heating System Type:                         •Forced Air Furnace •Unitary (Individual Area Units)
   Vents, Flues, Chimneys:                      •Metal-Single Wall
   Heat Distribution Methods:                   •Ductwork •Radiant
HEATING OBSERVATIONS
   General Comments
   It appears that the heating system has not been well maintained.
   RECOMMENDATIONS / OBSERVATIONS
    Improve: The heating systems require immediate service. Not all systems functional at time of inspection. Furnace
      systems have a typical life span of 20 years if properly maintained. Units over 5 years old risk cracked heat exchangers
      and should be routinely checked by a professional heating technician. A heat exchanger is mostly concealed, requires
      partial disassembly of furnace components for full viewing and is beyond the scope of a building inspection. Annual
      maintenance is recommended to assure safe, reliable heat.
   • Monitor: Deferred Cost: Given the age of the furnace, it may be near the end of its useful life. You should reserve
      funds to be ready to purchase a new furnace.
Representative view of warehouse units. Note the corrosion on the vent stack – probable flashing leak at roof.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • The adequacy of heat supply or distribution balance is not inspected.
    • The interior of flues or chimneys which are not readily accessible are not inspected.
    • The furnace heat exchanger, humidifier, or dehumidifier, and electronic air filters are not inspected.
    • Solar space heating equipment/systems are not inspected.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
   General Comments
   It appears that the system has not been well maintained. Air conditioning systems have a typical life span of 15 - 20 years if
   properly maintained. As the systems are old, they will require repairs or replacement soon.
   RECOMMENDATIONS / OBSERVATIONS
   Central Air Conditioning
   • Repair: Three of the air conditioning systems are relatively old. Not all systems functional at time of inspection. They
      will require a higher level of maintenance, and may be more prone to major component breakdown. Predicting the
      frequency or time frame for repairs on any mechanical device is virtually impossible. If the compressor fails, or if
      breakdowns become chronic, replacing the entire system may be more cost-effective than continuing to undertake
      repairs.
      HVAC INENTORY
              HVAC            Year        Cooling         Heating    Operational    Manufacturer   Area Serviced            Comments
               Unit           Built      Capacity         Capacity
                                         # of Tons         BTUs
                                                          [output]
    East Side – 2 Units      1987     4 Ton            82,000        Yes           Luxaire         1st & 2nd floor   Two forced air furnace and
                                                                                                   office space      A/C systems. Old
                                                                                                                     equipment.
    West Side – 2 Units      1987 & 4 Ton              76,000        Yes           Carrier &       1st & 2nd floor   Two forced air furnace and
                             2003                                                  Luxaire         office spaces     A/C systems. One of the
                                                                                                                     systems is old equipment.
    Overhead Radiant         15 - 20 Not applicable    Assume        Yes           Reznor            Warehouse       4 overhead units exist
    Heaters – 4 Units        years                     125,000+                                        areas         throughout the two
                             old                                                                                     warehouse bays. All units
                                                                                                                     were observed operational.
    Overhead Radiant – 1 Unit Less   Not applicable    150,000       Yes           Space-Ray            South        Newer unit – in good
                              than10                                                                 warehouse       working order.
                              years                                                                  area – east
                                                                                                         side
Two condenser units serving east side. These units are 20+ years old.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Window mounted air conditioning units are not inspected.
    • The cooling supply adequacy or distribution balances are not inspected.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                         Insulation / Ventilation
DESCRIPTION OF INSULATION / VENTILATION
    Roof Insulation:                              •Assume Fiberboard
    Roof Ventilation:                             •Roof Stack Vents
    General Comments
    Insulation levels are typical for a building of this age and construction. Caulking and weather-stripping around doors,
    windows and other exterior wall openings will help to maintain weather tightness and reduce energy costs.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Insulation/ventilation type and levels in concealed areas are not inspected. Insulation and vapor barriers are not disturbed
         and no destructive tests (such as cutting openings in walls to look for insulation) are performed.
    • Potentially hazardous materials such as Asbestos and Urea Formaldehyde Foam Insulation (UFFI) cannot be positively
         identified without a detailed inspection and laboratory analysis. This is beyond the scope of the inspection.
    • An analysis of indoor air quality is not part of our inspection unless explicitly contracted-for and discussed in this or a
         separate report.
    • Any estimates of insulation R values or depths are rough average values.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                             Plumbing
DESCRIPTION OF PLUMBING
   Water Supply Source:                        •Public Water Supply
   Service Pipe to Building:                   •Copper
   Main Water Valve Location:                  •Basement
   Interior Supply Piping:                     •Copper
   Waste System:                               •Public Sewer System
   Water Heater:                               •Gas •Electric •Estimated Age 12 & 14 Years
PLUMBING OBSERVATIONS
   General Comments
   The water pressure supplied to the fixtures is average. Only a slight drop in flow was experienced when two fixtures were
   operated simultaneously.
   RECOMMENDATIONS / OBSERVATIONS
   Water Heater
   • Monitor: The water heater tanks are older units that may be approaching the end of its useful lives. It would be wise to
      budget for new units. One cannot predict with certainty when replacement will become necessary.
   • Deferred Cost: Hot water tanks inoperative at time of inspection. Budget at least $600 for replacement.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions:
    • Portions of the plumbing system concealed by finishes and/or storage (below sinks, etc.), below the structure, or beneath
         the ground surface are not inspected.
    • Water quantity and water quality are not tested unless explicitly contracted-for and discussed in this or a separate report.
    • Clothes washing machine connections are not inspected.
    • Interiors of flues or chimneys which are not readily accessible are not inspected.
    • Water conditioning systems, solar water heaters, fire and lawn sprinkler systems, and private waste disposal systems are
         not inspected unless explicitly contracted-for and discussed in this or a separate report.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                                     Interior
DESCRIPTION OF INTERIOR
   Wall and Ceiling Materials:                   •Drywall •Tile •Suspended Tile
   Floor Surfaces:                               •Carpet •Tile •Concrete
   Window Type(s) & Glazing:                     •Fixed Pane •Double Pane
   Doors:                                        •Wood-Solid Core •Metal
INTERIOR OBSERVATIONS
   RECOMMENDATIONS / OBSERVATIONS
   Walls/Ceilings
   • Monitor: Water staining was noted in various ceiling tiles on the 2nd floor and within the warehouse walls indicating
      roof leakage.
   Windows
   • Repair: The windows are in mild disrepair. This is a common condition that does not necessitate immediate major
      repair. Trimming and adjustment, hardware improvements and glazing repairs would be logical long term improvements.
      In practice, improvements are usually made on an as needed basis only. The most important factor is that the window
      exteriors are well-maintained to avoid rot or water infiltration.
   Stairways
   • Repair: The railing for the stairway is loose and does not offer proper protection due to the width of the railing.
   • Repair, Safety Issue: The height of the stairway railing may not be sufficient to prevent a person from toppling over the
       railing. It is recommended that this condition be altered for improved safety.
   Environmental Issues
   • Monitor: There is the potential for lead content in the drinking water within the building. Lead in water may have two
      sources; the piping system of the utility delivering water to the building and/or the sold used on copper pipes prior to
      1988. This can only be confirmed by laboratory analysis. An evaluation of lead in water is beyond the scope of this
      inspection. For more information, consult the Environmental Protection Agency (E.P.A.) for further guidance and a list
      of testing labs in your area.
   • Monitor: Lead based paint was in use until approximately 1978. According to the Federal Department of Housing and
      Urban Development, a lead hazard can be present in a building of this age. This can only be confirmed by laboratory
      analysis. An evaluation of lead in paint is beyond the scope of this inspection. For more information, consult the
      Environmental Protection Agency (E.P.A.) for further guidance and a list of testing labs in your area.
   • Monitor: Radon gas is a naturally occurring gas that is invisible, odorless and tasteless. A danger exists when the gas
      percolates through the ground and enters a tightly enclosed structure (such as a building). Long term exposure to high
      levels of radon gas can cause cancer. The Environmental Protection Agency (E.P.A.) states that a radon reading of
      more than 4.0 picocuries per liter of air represents a health hazard. A radon evaluation is beyond the scope of this
      inspection (unless specifically requested). For more information, consult the Environmental Protection Agency (E.P.A.)
      for further guidance and a list of testing labs in your area.
   • Monitor: Carbon monoxide is a colorless, odorless gas that can result from a faulty fuel burning furnace, range, water
      heater, space heater or wood stove. Proper maintenance of these appliances is the best way to reduce the risk of carbon
      monoxide poisoning. For more information, consult the Consumer Product Safety Commission at 1-800-638-2772
      (C.P.S.C.) for further guidance. It would be wise to install of carbon monoxide detectors within the building.
                                                                  This confidential report is prepared exclusively for sample review
                                                                                                              © 2010 Structure & Site
                                                                                               Pages 26 of 32
The railing construction for the warehouse staircase is improper and presents a safety risk.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions
    • Furniture, storage, appliances and/or wall hangings are not moved to permit inspection and may block defects.
    • Carpeting, window treatments, central vacuum systems, building appliances, recreational facilities, paint, wallpaper, and
         other finish treatments are not inspected.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                     Mold Inspection
MOLD INSPECTION OBSERVATIONS
    A visual mold inspection was conducted within office and warehouse space.
    RECOMMENDATIONS / OBSERVATIONS
    No physical mold was observed.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions
    • Materials concealed behind finished surfaces could not be inspected.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
                                                                                                        Fire Protection
DESCRIPTION OF FIRE PROTECTION EQUIPMENT
Installed Components:
    RECOMMENDATIONS / OBSERVATIONS
    • Repair: Not all equipment observed functional. All equipment must be tested and certified.
    As we have discussed and as described in your inspection contract, this is a visual inspection limited in scope by (but not
    restricted to) the following conditions
    •   No equipment operated or tested.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
             DESCRIPTION/REQUIREMENTS:                                       OBSERVATIONS/COMMENTS:
   Parking Spaces:
         Total              Total ADA            ADA-Van           The subject property is a light manufacturing and
                                                                   office building which contains office and warehouse
         1-25                   1                     1            space. The public accommodation would be the
         26-50                  2                     1            entrance located at the front of the office building. A
                                                                   van accessible ADA parking space is not present by
       32 Actual             1 Actual             0 Actual         the office building.
         51-75                  3                     1            The property does not have sufficient ADA accessible
                                                                   parking spaces.
        76-100                  4                     1
       101-150                  5                     1            The property does have striped or designated parking
                                                                   spaces. The number of ADA accessible and van
       151-200                  6                     1            accessible parking spaces does not meet the ADA
       201-300                  7                     2            guidelines.
       301-400                  8                     2
       401-500                  9                     2
       501-1000            2% of total             1 of 6
        > 1000             20, plus 1 for          1 of 6
                           each 100, or
                         fraction thereof,
                            over 1000
   The term “parking facility” is used instead of the term “parking lot” in the ADA guidelines so that it is clear that both
   parking lots and parking structures are required to comply with these requirements. The number of parking spaces
   required to be accessible is to be calculated separately for each parking facility; the required number is not to be
   based on the total number of parking spaces provided in all of the parking facilities provided on the site.
   Path-of-Travel:
   Identify material physical barriers to the disabled from accessible       The property does not contain sufficient curb
   parking, public transportation stops, accessible passenger loading        cuts and ramps as well as walkways that
   zones, and public streets or sidewalks, to the accessible building        meet the ADA accessibility guidelines.
   entrance they serve. Path-of-travel should be construed to be a           There are insufficient ADA accessible
   path from on-site designated disabled parking spaces (if any) to the      entrances at the subject property. The
   leasing office and any facility available for use by the general          entrance hallway does not permit suitable
   public. The path-of-travel should have compliant ramps and                wheelchair access.
   railings, stair or step barriers and adequate or compliant main
   entrance doors and thresholds. Missing or noncompliant curb
   ramps, lack of or noncompliant ramps or railings, stir or step
   barriers, and inadequate or noncompliant main entrance doors and
   thresholds should be noted.
   Public Restrooms:
   The public toilet restroom facilities should accommodate the
   disabled with respect to: the existence of toilet stalls that appear to
                                                                             The public restrooms inspected at the
   be designed for accessibility, whether lavatories or the designated
   sink for the disabled are at apparent lower heights with adequate         subject property were in general compliance
   clearance underneath, and determine whether compliant                     with the ADA guidelines.
   emergency fire alarms and strobes are present within the toilet
   room facilities.
   Elevators:
    As prescribed in the pre-inspection contract, this is a visual inspection only. The inspection was limited by (but not restricted
    to) the following conditions:
    •   Limited review does not consist of a full American with Disabilities Act inspection.
Please also refer to the pre-inspection contract for a detailed explanation of the scope of this inspection.
Site Map
Vehicular entrance
Pedestrian entrance
Loading dock