Commissioning Handover Process Guide

This flowchart outlines the key stages and deliverables of the handover process from construction to full operations of a production system. The stages include mechanical completion and pre-commissioning, commissioning, startup and initial production, and performance testing. Key deliverables include certificates issued at each stage verifying readiness for the next stage, including the final handover and acceptance certificates signed off when ownership is transferred to operations.

Uploaded by

cryovikas1975
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
902 views2 pages

Commissioning Handover Process Guide

This flowchart outlines the key stages and deliverables of the handover process from construction to full operations of a production system. The stages include mechanical completion and pre-commissioning, commissioning, startup and initial production, and performance testing. Key deliverables include certificates issued at each stage verifying readiness for the next stage, including the final handover and acceptance certificates signed off when ownership is transferred to operations.

Uploaded by

cryovikas1975
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

HANDOVER PROCESS KEY DELIVERABLES

MECHANICAL HANDOVER
COMPLETION & CERTIFICATE
PRE-COMMISSIONING

READY INTEGRATED
PRODUCTION
FOR SYSTEM
NO COMMISSIONING ? COMPLETE

YES

COMMISSIONING

COMMISSIONING
HANDOVER
CERTIFICATE
OPERATIONS
READINESS ?
NO
OPERATIONS
MANAGEMENT
YES SYSTEM
IN PLACE

UTILITY SYSTEMS
READY COMMISSIONED
&
FOR OPERATIONAL
OPERATIONS

Pre-Startup
Audit
(PSUA)

READY
FOR HYDROCARBON
STARTUP SYSTEMS
COMMISSIONED

OPERATIONS
READINESS ?
NO
ASSET CUSTODIAN
YES ACCEPTS
CUSTODIANSHIP

STARTUP & INITIAL


PRODUCTION

PERFORMANCE
TESTING

FINAL
ACCEPTANCE
AUDIT

FINAL
ACCEPTANCE OF HANDOVER
OWNERSHIP CERTIFICATE

Handover by Area/ No Hydrocarbons Hydrocarbons Present


Sub System/System
RFC
MC Handover PC Handover Handover RFO – Non RFSU Handover Transfer of Transfer of
HC Systems VCR sign off Custodianship Ownership
Point
SoF Issued

Construction Completion Pre-Commissioning Commissioning of Start-Up/


Activity Operate
Mech Comp “A” Checks “B” Checks Systems Ramp Up

Ready For Operation Provisional Acceptance Final Acceptance


Utility - Non Hydrocarbon - Reliability Run - Normal Operation
Mechanical Completion Pre Com Completion - Capacity Tests - Completion of Guarantee
systems handed over.
- Handover from Construction - Systems powered up - Punch List Complete Period
Operations will Operate on
to Commissioning - DAC Per Discipline - Performance Verification
behalf of Project
- DAC Per Discipline - PC Cert Issued per System - Handover Doc’n
Certification - MC Cert Issued - Punch List
RFO Certs Issued per System
- Punch List Verification System/Sub System
Ready for Commissioning Ready For Start Up
- Punch List Verification - Commissioning Documentation
- RFC Cert Issued per System Operational Performance Tests
- Verification of PSUA actions closed
- VCR sign off (where used)
- RFSU Cert Issued
- SoF signed by Delivery &
Acceptance teams

Project QA Audits Ops Readiness Pre-Start-Up Audit


and Reviews Reviews PSUA Review -
Aprpox 3 months prior
- Approx 6 weeks before
- Carried out - Carried out SU Final Acceptance
Assurance periodically throughout periodically throughout
to PSUA.
- Verification of Design
SoF signed
Audit
project. - Assess the state of
project. and Build & State of
- Assess the quality of Operational Readiness Note: VCR
- Assess the state of Readiness for SU
the project related to RFSU may support
Operational - Verification of Ops
- Verify project plans activities. SoF
Preparedness in line Readiness for SU
and progress. with project progress.

Project with C&SU Led by Integrated


Responsibility Project
Commissioning Team Including
Operations Led with
Team CSU/Project Support Operator Ownership Commercial Operations
Operations

Main Contractor
Contractor HSE in Transition Operations

Care, Custody
& Control Project Key Project to Asset TransitionPhase Asset Owner
PROJECT DURATION WITHOUT SUBSYSTEM APPROACH

MECHANICAL COMPLETION

PRE-COMMISSIONING

COMMISSIONING

STARTUP

PROJECT DURATION WITH SUBSYSTEM APPROACH

MECHANICAL
COMPLETION
PRE-COMMISSIONING
COMMISSIONING
STARTUP
SUBSYSTEM 2 MECHANICAL
PROCESS UTILITIES COMPLETION
PRE-COMMISSIONING
COMMISSIONING
TIME SAVING
STARTUP
SUBSYSTEM 3 MECHANICAL
CONTROLS COMPLETION
PRE-COMMISSIONING
COMMISSIONING
STARTUP
SUBSYSTEM 4 MECHANICAL
SAFEGUARDING COMPLETION
PRE-COMMISSIONING
COMMISSIONING
STARTUP
SUBSYSTEM 5 MECHANICAL
HYDROCARBONS COMPLETION
PRE-COMMISSIONING
COMMISSIONING
STARTUP