FORM # J-015 (6/17)
SAUDI ARAMCO PRE-COMMISSIONING FORM
INSTRUMENT AND CONTROL CABLES
EQUIPMENT TYPE: USER REFERENCE: QMIS#
EQUIPMENT TAG NO: J12-G-0116A DESCRIPTION: CONTINUITY & IR TEST
BI/JO NO: 10-01055-0012 PLANT NO. / LOCATION: J12 - AROMATICS
REF. DRAWINGS & DOCUMENTS:
MANUFACTURER:
MODEL NO.: N/A SERIAL NO.: N/A
COMMISSIONING DATE:
CABLE TAG NO.: SEE BELOW CABLE GLANDING: ok
CABLE TYPE : XLPE CABLE SEALING: N/A
CABLE SIZE : CABLE ROUTING: J12-FFJB-2913
CABLE MARKING: TYPE PLTC - INST
1P 18AWG
MEGGERING SWA
Insulation
PAIR/ CORE TO CORE TO CORE SHIELD Resistance
CABLE TAG NO. CORE TO CORE RESULT VALUE RESULT
TRIAD SHIELD) ARMOR (MΩ) CONTINUITY CONTINUITY Between OS &
ARMOR (MΩ)
J12-PT-1022A 1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
J12-PT-1035A 1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
1 PAIR BLK WHT >550 >550 >550 ok ok >550 PASS
FOR THE TEST EQUIPMENT USED, PLEASE ENTER THE FOLLOWING:
EQUIPMENT S/N : 3500028
EQUIPMENT NAME:
EQUIPMENT NAME: INSULATION TESTER
MANUFACTURER: FLUKE
CALIBRATION DUE DATE: 19-JULY-2018
REMARKS: Applied voltage 500 VDC….
NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist. Entries should be revised, added and
deleted and approvals adjusted to reflect the needs of the Project Acceptance Committee.
DEC / JGC SAPMT JAPID OPERATIONS
APPROVALS
Signature & Date Md Mutiur Rehman Mr. RALLA NOVIE Mr. WASIM ANWER
FORM # J-015 (6/17)
SAUDI ARAMCO PRE-COMMISSIONING FORM
INSTRUMENT AND CONTROL CABLES
EQUIPMENT TYPE: USER REFERENCE: QMIS#
EQUIPMENT TAG NO: DESCRIPTION: CONTINUITY & IR TEST
BI/JO NO: 10-01055-0012 PLANT NO. / LOCATION: J12 - AROMATICS
REF. DRAWINGS & DOCUMENTS:
MANUFACTURER:
MODEL NO.: N/A SERIAL NO.: N/A
COMMISSIONING DATE:
CABLE TAG NO.: CABLE GLANDING:
CABLE TYPE : CABLE SEALING:
CABLE SIZE : CABLE ROUTING:
CABLE MARKING:
MEGGERING
Insulation
PAIR/ CORE TO CORE TO CORE SHIELD Resistance
CABLE TAG NO. CORE TO CORE RESULT VALUE RESULT
TRIAD SHIELD) ARMOR (MΩ) CONTINUITY CONTINUITY Between OS &
ARMOR (MΩ)
FOR THE TEST EQUIPMENT USED, PLEASE ENTER THE FOLLOWING:
EQUIPMENT S/N :
EQUIPMENT NAME:
EQUIPMENT NAME:
MANUFACTURER:
CALIBRATION DUE DATE:
REMARKS: Applied voltage VDC….
NOTE: This non-mandatory form may be used as the starting point to assemble a pre-commissioning checklist. Entries should be revised, added and
deleted and approvals adjusted to reflect the needs of the Project Acceptance Committee.
DEC / JGC SAPMT JAPID OPERATIONS
APPROVALS
Signature & Date MD ZAHID RAFIQUE Mr. RALLA NOVIE Mr. WASIM ANWER