Material: Ordinary Portland Cement Item Element Component Calculation Total

The document provides a breakdown of the estimated materials needed to construct a building, including ordinary Portland cement, sand, ready mix concrete, and steel rebar. It estimates the quantities of each material needed for various building elements like walls, floors, foundations, and frames. The total amounts calculated are 6,023 kg of ordinary Portland cement, 33,618 kg of sand, 12 cubic meters of ready mix concrete, and an unspecified amount of 6mm diameter steel rebar.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
138 views5 pages

Material: Ordinary Portland Cement Item Element Component Calculation Total

The document provides a breakdown of the estimated materials needed to construct a building, including ordinary Portland cement, sand, ready mix concrete, and steel rebar. It estimates the quantities of each material needed for various building elements like walls, floors, foundations, and frames. The total amounts calculated are 6,023 kg of ordinary Portland cement, 33,618 kg of sand, 12 cubic meters of ready mix concrete, and an unspecified amount of 6mm diameter steel rebar.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Material:  Ordinary  Portland  Cement

Item Element Component Calculation Total  

1 External  Wall Cement  mortar  (1:6)  in 1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 55m2  half  brick  thick  wall  requires  3.85m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
3.85m3  of  mortar  requires  781kg  of  OPC                          781

2 External  Wall Cement  mortar  (1:6)  in 1m2  one  brick  thick  wall  requires  0.15m3  of  mortar
one  brickwall 46m2  one  brick  thick  wall  requires  6.90m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
6.90m3  of  mortar  requires  1400kg  of  OPC                    1,400

3 Internal  Wall Cement  mortar  (1:6)  in   1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 78m2  half  brick  thick  wall  requires  5.46m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
5.46m3  of  mortar  requires  1108kg  of  OPC                    1,108

4 Internal  Wall  Finishes Cement  screed  (1:4) 20mm  of  95m2  of  backings  is  1.90m3  of  cement  screed
1m3  of  screed  requires  (1/5)  x  1420kg  of  OPC
1.90m3  of  screed  requires  540kg  of  OPC                          540

5 Internal  Wall  Finishes Cement  plaster  (1:4) 20mm  of  132m2  of  finish  is  2.64m3  of  plaster
1m3  of  plaster  requires  (1/5)  x  1420kg  of  OPC
2.64m3  of  plaster  requires  750kg  of  OPC                          750

6 Internal  Floor  Finishes Cement  paving  (1:3) 20mm  of  18m2  of  backings  is  0.36m3  of  cement  paving
1m3  of  screed  requires  (1/4)  x  1420kg  of  OPC
0.36m3  of  paving  requires  128kg  of  OPC                          128

7 Internal  Floor  Finishes Cement  screed  (1:3) 20mm  of  98m2  of  backings  is  1.96m3  of  cement  screed
1m3  of  screed  requires  (1/4)  x  1420kg  of  OPC
1.96m3  of  screed  requires  696kg  of  OPC                          696

8 External  Finishes Cement  plaster  (1:4)  to   20mm  of  91m2  of  finish  is  1.82m3  of  plaster
wall 1m3  of  plaster  requires  (1/5)  x  1420kg  of  OPC
1.82m3  of  plaster  requires  517kg  of  OPC                          517

9 External  Finishes Cement  screed  (1:4)  to   20mm  of  18m2  of  backings  is  0.36m3  of  cement  screed
floor 1m3  of  screed  requires  (1/5)  x  1420kg  of  OPC
0.36m3  of  screed  requires  103kg  of  OPC                          103

TOTAL  (kg)                      6,023


Material:  Sand
Item Element Component Calculation Total  

1 External  Wall Cement  mortar  (1:6)  in 1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 55m2  half  brick  thick  wall  requires  3.85m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
3.85m3  of  mortar  requires  5280kg  of  sand                    5,280

10 External  Wall Cement  mortar  (1:6)  in 1m2  one  brick  thick  wall  requires  0.15m3  of  mortar
one  brickwall 46m2  one  brick  thick  wall  requires  6.90m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
6.90m3  of  mortar  requires  9463kg  of  sand                    9,463

11 Internal  Wall Cement  mortar  (1:6)  in   1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 78m2  half  brick  thick  wall  requires  5.46m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
5.46m3  of  mortar  requires  7488kg  of  sand                    7,488

12 Internal  Wall  Finishes Cement  screed  (1:4) 20mm  of  95m2  of  backings  is  1.90m3  of  cement  screed
1m3  of  screed  requires  (4/5)  x  1600kg  of  sand
1.90m3  of  screed  requires  2432kg  of  sand                    2,432

13 Internal  Wall  Finishes Cement  plaster  (1:4) 20mm  of  132m2  of  finish  is  2.64m3  of  plaster
1m3  of  plaster  requires  (4/5)  x  1600kg  of  sand
2.64m3  of  plaster  requires  3380kg  of  sand                    3,380

14 Internal  Floor  Finishes Cement  paving  (1:3) 20mm  of  18m2  of  backings  is  0.36m3  of  cement  paving
1m3  of  screed  requires  (3/4)  x  1600kg  of  sand
0.36m3  of  paving  requires  432kg  of  sand                          432

15 Internal  Floor  Finishes Cement  screed  (1:3) 20mm  of  98m2  of  backings  is  1.96m3  of  cement  screed
1m3  of  screed  requires  (3/4)  x  1600kg  of  sand
1.96m3  of  screed  requires  2352kg  of  sand                    2,352

16 External  Finishes Cement  plaster  (1:4)  to   20mm  of  91m2  of  finish  is  1.82m3  of  plaster
wall 1m3  of  plaster  requires  (4/5)  x  1600kg  of  sand
1.82m3  of  plaster  requires  2330kg  of  sand                    2,330

17 External  Finishes Cement  screed  (1:4)  to   20mm  of  18m2  of  backings  is  0.36m3  of  cement  screed
floor 1m3  of  screed  requires  (4/5)  x  1600kg  of  sand
0.36m3  of  screed  requires  461kg  of  sand                          461

TOTAL  (kg)                  33,618

Material:  Ready  Mix  Concrete  Grade  25


Item Element Component Calculation  Total    

1 Work  Below  Lowest   Reinforced  concrete Pad  footing                                    1


Floor  Finish work Column  stump                                    1
Ground  beam                                  4

2 Frame Reinforced  concrete Beam                                    6


work

TOTAL  (m3)                                12


Material:  6mm  diameter  mild  steel  rebar
Item Element Component Calculation  Total    

1 External  Wall Bonding  ties 162  nos  of  450mm  bonding  ties                              73

2 Internal  Wall Bonding  ties 36  nos  of  450mm  bonding  ties                              16

TOTAL  (m)                                89

Material:  8mm  diameter  mild  steel  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   Mild  steel  rebar In  column  stump                              34


Floor  Finish In  ground  beam                          116

2 Frame Mild  steel  rebar In  column                              76


In  beam                              73

TOTAL  (kg)                            299


Material:  10mm  diameter  mild  steel  rebar
Item Element Component Calculation  Total    

1 Work  Below  Lowest   Mild  steel  rebar In  pad  footing                                  7


Floor  Finish In  ground  beam                          101

2 Frame Mild  steel  rebar In  beam                          100

TOTAL  (kg)                            208

Material:  10mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  ground  beam                          300


Floor  Finish

2 Frame High  tensile  rebar In  beam                          250

TOTAL  (kg)                            550

Material:  12mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  pad  footing                              17


Floor  Finish In  column  stumps                              90
In  ground  beam                          349

2 Frame High  tensile  rebar In  column                          208


In  beam                          270

TOTAL  (kg)                            934

Material:  16mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  pad  footing                              20


Floor  Finish In  column  stumps                          100

2 Frame High  tensile  rebar In  column                          222

TOTAL  (kg)                            342


Material:  Cement  and  sand  bricks
Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 1m2  of  brickwall  requires  59  pieces  of  bricks
55m2  of  brickwall  requires  3245  pieces  of  bricks                    3,245

2 External  Wall One  brickwall 1m2  of  brickwall  requires  118  pieces  of  bricks
46m2  of  brickwall  requires  5428  pieces  of  bricks                    5,428

3 Internal  Wall Half  brickwall 1m2  of  brickwall  requires  59  pieces  of  bricks
78m2  of  brickwall  requires  4602  pieces  of  bricks                    4,602

TOTAL  (nos)                  13,275

Material:  Exmet
Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 10  nos  of  exmet  required  at  3m  high  wall
18.33m  long  wall  requires  184m  of  exmet                          184

2 External  Wall One  brickwall 10  nos  of  exmet  required  at  3m  high  wall
15.33m  long  wall  requires  154m  of  exmet                          154

3 Internal  Wall Half  brickwall 10  nos  of  exmet  required  at  3m  high  wall
26.00m  long  wall  requires  260m  of  exmet                          260

TOTAL  (m)                            598

Material:  Damp  proof  course  (6.1m  x  1m)


Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 115mm  wide                              24

2 External  Wall One  brickwall 225mm  wide                              22

3 Internal  Wall Half  brickwall 115mm  wide                              26

TOTAL  (m)                                72


Material:  Dulux  Interior  Basecoat  Sealer
Item Element Component Calculation Total  

1 Internal  Wall  Finishes Painting 100m2  requires  10  litres  of  paint
132m2  requires  13.2  litres  of  paint                        13.2

2 Internal  Ceiling  Finishes Painting 100m2  requires  10  litres  of  paint
104m2  requires  10.4  litres  of  paint                        10.4

3 External  Finishes Painting  to  wall 100m2  requires  10  litres  of  paint
91m2  requires  9.1  litres  of  paint                            9.1

4 External  Finishes Painting  to  soffit 100m2  requires  10  litres  of  paint
36m2  requires  3.6  litres  of  paint                            3.6

TOTAL  (litres)                                36

Material:  Dulux  ICI  Maxilite  Trade  Emulsion  Paint


Item Element Component Calculation Total  

1 Internal  Wall  Finishes Painting 100m2  requires  9.52  litres  of  paint
132m2  requires  12.57  litres  of  paint
2  coats  requires  25.14  litres  of  paint                        25.1

2 Internal  Ceiling  Finishes Painting 100m2  requires  9.52  litres  of  paint
104m2  requires  9.90  litres  of  paint
2  coats  requires  19.80  litres  of  paint                        19.8

3 External  Finishes Painting  to  wall 100m2  requires  9.52  litres  of  paint
91m2  requires  8.66  litres  of  paint
2  coats  requires  17.33  litres  of  paint                        17.3

4 External  Finishes Painting  to  soffit 100m2  requires  9.52  litres  of  paint
36m2  requires  3.43  litres  of  paint
2  coats  requires  6.85  litres  of  paint                            6.9

TOTAL  (m2)                                69