Recommondation by Xyz

The document contains compliance reports from Bharat Heavy Electricals Limited (BHEL) addressing recommendations from an investigation report of an accident at the 2x700 MW Kakrapar Atomic Power Plant (KAPP) 3&4 project site. The compliance reports provide details on actions taken such as conducting medical examinations of workers, supervisors checking worker health before tasks, emphasizing proper safety gear use, inspecting scaffolding, and canceling height work passes for workers with medical issues. Attached records provide evidence of safety trainings, attendance, inspections and cancelled passes. A second letter from BHEL certifies that only physically fit and third party tested lifting equipment is used at the KAPP site, after

Uploaded by

M8Rskn6wc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views3 pages

Recommondation by Xyz

The document contains compliance reports from Bharat Heavy Electricals Limited (BHEL) addressing recommendations from an investigation report of an accident at the 2x700 MW Kakrapar Atomic Power Plant (KAPP) 3&4 project site. The compliance reports provide details on actions taken such as conducting medical examinations of workers, supervisors checking worker health before tasks, emphasizing proper safety gear use, inspecting scaffolding, and canceling height work passes for workers with medical issues. Attached records provide evidence of safety trainings, attendance, inspections and cancelled passes. A second letter from BHEL certifies that only physically fit and third party tested lifting equipment is used at the KAPP site, after

Uploaded by

M8Rskn6wc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

भारतहेवीइलेक्ट्रिकल्सलललिटे डपावर Bharat Heavy Electricals Limited

सेरर पलििीक्षेत्रसाईट ओलिस PS-WR Site OfficeM/s NPCIL,


एनपीसीआईएल, काकरापार KAPP (3&4), Kakrapar PO:
(3&4) Anumala,
अणुिाला वाया: व्यारा Via: VYARA
394651 गु जरात Dist. TAPI 394651 (Gujarat)

____________________________________________________________________________

PW: KAPP: SOX:


11.06.2018

M/s NPCIL KAPP (3&4),


KAKRAPAR, ANUMALA (Gujarat).
Kind Attention: Shri BL Sahu, ACE (TG&M)

Sub: 2x700 MW KAPP (3&4) – Compliance report against investigation report for accident of serious nature

Dear Sir,

Please find point wise compliance/action report of investigation report for accident of serious nature:

Investigation Recommndation to prevent Compliance


report para recurrence
No.

9(i) During the pre-employment & regular During pre employment & medical examination
medical examination workers should be worker are being brieifed & asked regarding
counseled / encouraged to disclose the health disease of workers are working at height
information about disease such as fits pron area are not having any health disease such
etc. Before joining the duty workers as fits.
should be prompted to disclose
information on disease by stressing upon
hazard and risks involved due to not
reporting of pre-existing disease. To
create awareness on this various
platforms such as induction safety
training, First aid training, Pep Talks etc.
need to be used.
9(ii) All immediate supervisors are to be All line man Enginner/Supervisor has asked to
advised to ask their workers about their workers for health condition regarding fits,
health condition before assigning work height fobia etc before assigning work such as
such as work at height. work in height.
9(iii) Anchoring of double lanyard of safety All line man Enginner/Supervisor has instructed
belt while working at height should be to workers regarding proper usage of safety belt
stressed upon regularly to workers while working at height and in pep talk also.
during safety training, Pep Talks/Pre-
job briefing. Enforcement of proper
usage of safety belt while working at
height should be done by front line
Engineers & Supervisors.
9(iv) Scaffolding pattern should be changed We are filling the JHA checklist of scaffolding
in such a way that built-in ladders are in and daily inspection is being carried out by
line to facilitate ascending /descending competent scaffolder and safety officer and
to avoid the unnecessary risk involved maintain a record.
in inadvertent man movement or
Separate ladders should be provided to
access the scaffolding and working
platform.

पंजीकृतकायाालय: बीएचईएलहाउस,लसरीिोटा ,नई लिल्ली -110 049


Regd.Office: BHEL House, Siri Fort, N.Delhi 110 049
भारतहेवीइलेक्ट्रिकल्सलललिटे डपावर Bharat Heavy Electricals Limited
सेरर पलििीक्षेत्रसाईट ओलिस PS-WR Site OfficeM/s NPCIL,
एनपीसीआईएल, काकरापार KAPP (3&4), Kakrapar PO:
(3&4) Anumala,
अणुिाला वाया: व्यारा Via: VYARA
394651 गु जरात Dist. TAPI 394651 (Gujarat)

____________________________________________________________________________

9(v) A drive should be initiated to identify During the height pass test NPCIL first aider and
the workmen who have the history of safety officer check the workers health condition
any disease such as fits etc. and cancel then they issue height pass number for allowing
the height work pass for them. height work.

With regards

Construction Manager

Attachement :
 Pep talk record
 Workers attendence record
 Scaffolding Inspection record
 Cancel height pass record

PW: KAPP: SOX:


11.06.2018

M/s NPCIL KAPP (3&4),


KAKRAPAR, ANUMALA (Gujarat).

Kind Attention: Shri BL Sahu, ACE (TG&M)

Sub: 2x700 MW KAPP (3&4) – Examination of lifting machine and tackles

Dear Sir,

With reference to your mail we have jointly inspect lifting machine and tackles which was inform to NPCIL safety
office also at that time. Some of lifting machine and tackles found unfit during testing that equipment were removed
from site.

It is to certified that we are using physically fit and third party tested lifting machine and tackles only at BHEL KAPP
Site.

With Regards

Construction Manager

पंजीकृतकायाालय: बीएचईएलहाउस,लसरीिोटा ,नई लिल्ली -110 049


Regd.Office: BHEL House, Siri Fort, N.Delhi 110 049
भारतहेवीइलेक्ट्रिकल्सलललिटे डपावर Bharat Heavy Electricals Limited
सेरर पलििीक्षेत्रसाईट ओलिस PS-WR Site OfficeM/s NPCIL,
एनपीसीआईएल, काकरापार KAPP (3&4), Kakrapar PO:
(3&4) Anumala,
अणुिाला वाया: व्यारा Via: VYARA
394651 गु जरात Dist. TAPI 394651 (Gujarat)

____________________________________________________________________________

पंजीकृतकायाालय: बीएचईएलहाउस,लसरीिोटा ,नई लिल्ली -110 049


Regd.Office: BHEL House, Siri Fort, N.Delhi 110 049

You might also like