This document summarizes a study on the possibility of applying Building Information Modeling (BIM) in Syrian building projects. An online and in-person questionnaire was distributed to 89 Syrian engineers from both public and private sectors. The study found that while Syrian engineers have some awareness of BIM, more than 44% believe full adoption in Syria will occur within 5 years. Respondents identified benefits of BIM as well as economic, technical, organizational, legal and human challenges to its adoption. The study concludes it is a first step toward introducing BIM to improve the Syrian construction industry.

Uploaded by

Dat Doan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
967 views7 pages

Syria

This document summarizes a study on the possibility of applying Building Information Modeling (BIM) in Syrian building projects. An online and in-person questionnaire was distributed to 89 Syrian engineers from both public and private sectors. The study found that while Syrian engineers have some awareness of BIM, more than 44% believe full adoption in Syria will occur within 5 years. Respondents identified benefits of BIM as well as economic, technical, organizational, legal and human challenges to its adoption. The study concludes it is a first step toward introducing BIM to improve the Syrian construction industry.

Uploaded by

Dat Doan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

POSSIBILITY OF APPLYING BIM IN SYRIAN BUILDING PROJECTS


Sonia Ahmed1, 2, Petr Dlask1, Mohamed Shaban3, Omar Selim2
1
Czech Technical University in Prague, Czech Republic;
2
BIMarabia, United Kingdom; 3AL-Baath University, Syria
sonia_ahmad24@yahoo.com, shabanm85@gmail.com, omar.selm@gmail.com

Abstract. As a developing country and according to the situations of war and siege experienced by it Syria has a
good percentage of the Middle East nations in the field of adopting new technologies and systems. This research
demonstrates the awareness of BIM between Syrian engineers in the public sector and the possibility of
mandating BIM in the near future. A quantitative statistic did achieve the research aim using both open and
closed questionnaire. The research showed that Syrian construction and engineering workers know a little about
the BIM. However, more than 44 % via 89 respondents reported that the full adoption of BIM in Syria will be
within the next five years with the emphasis on the need to develop the BIM standard before the start. About
61 % of the respondents believe that BIM can be useful in the design stage, while 21 % indicated that they can
implement BIM in both design and construction stage of the project. Whatever the case, 49 % of respondents
found that BIM can solve 50-75 % of the current building problems. Respondents identified the most expected
benefits of BIM, also barriers and challenges that hinder the application of BIM: economic, technical,
organizational, legal and human challenges. In addition to that, the risks were explained that may occur within
the projects implemented using BIM. This study in association with Syrian organizations and universities
showed the tendency towards the philosophy of building information modeling for the new generation of Syrian
engineering. About 37 % of the respondents considered Syria government to be the main engine for the BIM
adoptions; while more than 22 % believe that the designer is the main engine to adopt and convince others about
the benefits of BIM during the building projects life cycle. Unfortunately, due to the lack of the budget allocated
for the training and rehabilitation of employees, or fear of the high cost of adopting this technology and the use
of programs 31 % of staff rely on self-training, and only 24 % of them receive formal training in addition to their
effort. Researchers believe that this research will be the first step towards soft moving to BIM in Syrian projects.

Keywords: BIM, building, modelling, quantitative statistic.

Introduction
Building problems in most of the world are general with some exceptions depending on the
nature, policy, and privacy of the work in each country [1]. To achieve the best performance, the client
satisfaction must arrive by meeting the quality of the project within the specified cost and time [2].
The aim of this study is to explain the possibility of using the BIM technology, which achieved
excellent results for the countries that adopted it; in Syrian building sector. Eastman offered BIM as
“The use of computers instead of drawings in building design” [3]. BIM also can be required as a
procedural and technological shift in the AEC industry [4]. Penttilä in 2006 said that, if there was no
BIM, another system would have been found in any name and may have been abbreviated BIM also or
virtual building [5].
Implementation strategies have been established for the use of BIM on construction projects
worldwide. For example, the UK government has mandated the use of BIM level 2 for government
projects by 2016 [6]. According to [7] “hundreds of organizations around the world adopted BIM and
gained its benefits, met clients and users’ satisfaction and increased their profits by 5-12 %”. Most of
these countries have previously suffered from the constraints of adopting the BIM because the
traditionalists refused to change their way of working; in addition to this fact, [8] cited that “the 2012
McGraw Hill Construction Smart Market Report showed that 71 % of designers and contractors in the
US are now using BIM to some extent”. And according to the NBS 2017: over the six years, BIM
adoption has increased over 8 % each year, on average”. So, given the impressive results currently
reading in monthly and annual reports of the significant benefits and continuous improvements of all
parties involved in building projects around the developed world, and based on the results of research
and critical reviews in the building industry, and the similarity and significant convergence of the
imbalances and problems between most of the developed world and the third world countries [3], a
practical step has been taken in improving the reality of building in the Arab world by introducing the
benefits of implementing the BIM within building projects, and the search for the most critical barriers
and challenges and plans to avoid it. Also the multi-national firms that have multiple offices across the
Middle East region imposed a wider adoption of BIM in construction processes there, but according to

DOI: 10.22616/ERDev2018.17.N101 524


ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

[10] only 20 % of AEC organizations in the Middle East are using BIM or are in the process of
adopting BIM, with most professionals within this region still looking at BIM just as an advanced
AutoCAD tool; in addition to the fact that the transitions to new instruments are always difficult.
Raising awareness related to the benefits of BIM and increasing the training opportunities in the
Middle East are necessary in order to allow all stakeholders to benefit substantially from BIM.
According to the war conditions; Syria was an exception, but there is understanding of the need
for the introducing modern technologies and advanced management tools to building projects in Syria,
like other countries that suffered from poor performance and lack of technology in the past [11].
Beside the desire of the Syrian engineers and government to reconstruct Syria with local hands and
expertise, BIM now has a study plan at all undergraduate, Master, Ph.D. degree courses at Syrian
universities. In addition, there are individual and local training, conferences, workshops etc. So, a
gradual transition towards the adoption of BIM has really started in Syria.

Search Problem
Although the adoption of Building Information Modelling is used widely all over the world, it is
considered a new philosophy in Syria. And the next reconstruction stage needs using of new
technologies like BIM, which form the suitable solution for this stage.

Materials and methods


As a first step, the authors began reviewing literature reviews on the implementation of BIM in
the Middle East and worldwide. To achieve the objective of this study quantitative statistic of the
possibility of the application of BIM in the Syrian building sector was done. An online questionnaire
was built; it is the fastest and easiest way to have the respondents’ opinion, and it could be easily
accessed by construction professionals anywhere in the under war region. Also, an open questionnaire
was created by proceeding face to face meeting with the aim to explain BIM and to enhance the closed
questionnaire’s results. The questionnaire general structure contained a suitable title, brief introduction
and explanation of the research. It consisted of thirty-four questions – clear, simple and flowing
smoothly on to the next. Respondents were 89 people, they were chosen through probability sampling
procedures. It is a perfect percentage and represents a segment of the Syrian engineers in several
regions and reflects the Syrian position in the current circumstances. The questions determined the
knowledge about the modelling of building information in the engineering community – the excepted
benefits of BIM, defined barriers and challenges that hinder its application including economic,
technical, organizational, legal and human challenges. In addition, some information about: the future
of BIM and the potential for adoption in the coming years, the risks that may occur within the projects
implemented using BIM, who is responsible for approval from the respondents and other answers that
we will be discussed in detail. A Likert scale was used; it consisted of five points 1 – strongly agree,
2 – agree, 3 – neutral, 4 – disagree, 5 – strongly disagree. For some questions the respondents could
choose more than one answer. In addition, some questions gave the respondents the freedom of giving
a different answer by the option of “other (please specify)”.
The pilot study was completed to test the survey instrument. Invitations were sent to construction
professionals in the Syrian construction industry by emails, LinkedIn, and BIMarabia website. The
invitation contained a description of the research and its aim, and the link at the end of the invitations,
which takes respondents to the online questionnaire. The questionnaire has targeted universities,
consulting firms, contractors, manufacturers, construction managers and site engineers, which belong
to both the public and the private sector for a more accurate result.

Results and discussion


The scientific degrees of respondents varied from Bachelor to Diploma, Master, and Ph.D. in
Engineering in most of its specializations, the highest of which is civil engineering (60 %), followed
by architectural (25.8 %), mechanical, electrical and others. The highest percentage of respondents
were designers, project managers, consultants and other working groups in several different
companies: studies, Execution, Syrian Universities, and Engineers Syndicates located in several
governorates, in addition, some private engineering offices, buildings belonging to the Ministry of
Health, Culture, Tourism, Ministry of Public Works, Ministry of Housing and others.

525
ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

Survey findings
In general, the study showed that the percentage of engineering knowledge about Building
Information Modelling is represented by about 50 % of the respondents. The results of the survey
show that (10) out of (42) engineers have worked on at least two projects related to modelling, these
results are right, relative to the novelty of this issue in the Middle East in general. The experience of
the highest proportion of respondents in the engineering work exceeded 15 years, knowing that 20 %
of them are still in the first stage after graduation with years of experience ranging from 2 to 5 years.
As the survey shows, 30 % of the respondents work in the field of residential building (designers,
project managers, consultants) and 26 % as the second rank for the education sector, represented by
the Syrian universities spread throughout the Syrian areas. Only 5 % of the respondents work in the
industrial sector. Only about 20 % use the 3D software in more than 90 % of their projects. 30 % of
the respondents use the architectural and structural Revit, only 13 % use the MEP, but 75 % still use
AutoCAD, with a note that some of them use AutoCAD beside of using of Revit. Fig.1. shows that
56 % of respondents consider themselves to be BIM users at present, although they often use only one
program, the Revit. Their vision differed to the definition of BIM, but the majority (53.7 %) felt that
BIM was a new technology and technic in work.

Fig. 1. Percentage of BIM users, percent %, source Authors, 2017


Many of the participating engineers confirmed the electronic delivery as a solution for not losing
and damaging the information, and the ability to use it faster, if needed later. In responders’ opinion,
63 % of the companies and individuals surveyed used both paper and electronic documentation, the
use of electronic copies was only 15 %. Only 50 % of users find that their companies believe in
cooperative work and this greatly facilitates the possibility of going to work with the BIM.
Unfortunately, decision-makers in most Syrian companies know little about the importance of this
technology with a weakness of the budget allocated for the training of employees and fear of the high
cost of adopting this technology. Based on that, 31 % of the staff rely on individual training, and 24 %
of them receive formal training in addition to their effort. See Table 1.
Table 1
The most commonly used method for delivering project data and outputs, source: authors, 2017
Answer choices Responses, %
Formal training for a specified period of working hours 15
Engineers take formal training outside working hours 16
Combination of formal and individual training 24
Working with a team of specialists on a realistic project 19
Individual training 31
There is no training 13
Other 3
28 % believe that despite the low rate of implementation of BIM in Syrian projects and its rarity
in many companies, the adoption of this technology will be during the next five years. About 35 % of
the respondents believe that this should be compulsory and under the guidance of the government,
which is considered by about 37 % of the respondents to be the primary engine for the adoption of the
BIM. While more than 22 % believe that the designer is the main engine to adopt and convince others

526
ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

about the benefits of building information modeling (BIM) as part of construction projects in Syria.
Most of the countries around the world that have entered the BIM system have sought to set corporate
standards and then move to general national principles and standards, where there are now more than
70 codes around the world for the BIM system and its uses. About the importance and necessity of
having a BIM code, 29 % believe that the process of setting an individual standard to deal with the
principles and techniques of BIM is fundamental, while another 50 % find it essential and 9 % find it
not very important.
Another set of questions focused on defining at any stage of the project lifecycle whether it is now
possible to apply the BIM system to the Syrian construction industry. The findings as shown in Fig. 2.
indicate that 61 % of the respondents believe that BIM can be useful in the design stage, while 21 %
indicated that they can implement BIM in both design and construction stage of the project.
Unfortunately, 8 % said that it is impossible to use BIM now.

Fig. 2. Best stage to apply BIM to Syrian construction industry,


percent %, source: authors, 2017
As a result of the importance of risks facing the traditional work and the need to identify, manage
and distribute responsibility among the participating parties, it was necessary to mention the most
important risks that may face the projects that will be implemented using the BIM [12].
• Risks of lack of clarity (unclear specifications, customer requirements, required quality of
achievements).
• Misappropriateness of information and significant errors in construction works.
• 3D models and their 2D exports have not updated due to lack of cooperation between the
parties of the project. See Table 2.
Table 2
Main risks facing projects implemented using BIM, source: author results, 2017
Answer choices Responses %
Risk of lack of clarity 45.0
No evidence to support supply chine experience in the BIM projects 28.0
Lack of cooperation between the parties of the project 37.0
Wrong transmission of the information, and consequently errors on site 39.6
Accidents and inaccuracies of technology 20.0
Risk of non-compliance with contract terms 30.0
Inaccuracy in information provided by tenders for estimating quantities and costs. 20.0
Delay in schedules 13.0
A survey in the United States and Europe confirmed that BIM adoption rose dramatically from
28 % in 2007 to 71 % in 2012 and is still booming to the present [13]. The responses in this survey
emphasized the problems of cost overruns and delays, rework, and frequency of change orders as the
most current Syrian building problems; 49 % of the respondents saying that BIM can solve these
problems and the most expected benefits from the BIM application were assessed and ranked in the
top five.

527
ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

• Change in a specific place of design followed by an automatic change in all sections and
interfaces associated with it.
• Detect design errors, conflicts and minimize rework.
• Save the cost of the project.
• Enable collaboration between different project parties and improve communication.
• Save the project time.
To achieve the analysis aim the barriers and challenges facing BIM implementation in Syrian
construction environment had to be investigated. As shown below, the respondents identified the most
barriers and obstacles that hinder the application of BIM in five sets: economic, technical,
organizational, legal, and human challenges.
• Economic challenges.
‒ Lack of demand for BIM by other parties involved in the projects.
‒ Lack of clarity of investment due to BIM application.
‒ The recruitment of BIM specialists and additional staff.
• Technical challenges.
‒ The need for a strong Internet connection and uninterrupted power.
‒ Believing that existing techniques are adequate, there is no need to apply BIM.
‒ Insufficient standards and protocols related to BIM.
‒ Interoperability as one of the standard challenges of BIM [14].
• Organizational challenges.
‒ Weak cooperation between different disciplines.
‒ Inadequate government efforts to adopt and implement BIM.
‒ The need to manage sophisticated data with the level of evolution of the model.
• Legal challenges.
‒ The need to formulate BIM contracts.
‒ Lack of clarity of responsibilities between project parties.
• Human challenges.
‒ Lack of experience and lack of staff trained for BIM programs.
‒ Weak knowledge of the benefits offered by BIM.
‒ The sharp resistance to change, especially the aged persons, and the engineer’s
affection to their familiar programs.
The last question in this search focused on the respondent’s opinion of what are the most
important items that serve in the localization of building information modelling technology? The most
important answers according to their frequency were as follows.
• To raise awareness of cooperation culture between different parties.
• Government policy to make the use of BIM technology mandatory through the development
of individual laws.
• Establish an educational base for BIM technology by making it part of the curricula of
universities.
• Provide government support for the implementation of BIM technology in private companies
and institutions.
• Allocate financial funding to support the costs of BIM technology.
• Engaging with international specialists with expertise in BIM technology.
• Development of contracts and legal materials governing the use of BIM technology.

Result discussion
From the NBS reports and other statistics in this field, when compared to the questionnaire
results, it can be said that BIM adoption in Syria started as in so many countries from the education
sector. And it is currently being implemented in certain aspects of construction projects especially
during the design stage. During one of the necessary meetings between the authors and the manager of
GCEC (The General Consultant and Engineering Company) as an open questionnaire, it was found
that the company by its manager made the decision of beginning a pilot project by using BIM. 43 % of

528
ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

the responders said that they used BIM, more of them know only little about BIM and use only one
BIM software – Revit. However, the authors presented their desire in forming the BIM team in this
company and were going step by step towards completing the first pilot project. From the fact that (10)
out of (42) engineers have worked on at least two projects related to modeling, 43 % of the
respondents use the architectural and structural and MEP Revit, Syrian engineers were able to
determine the big benefit that could be accepted from using BIM at the design stage. Some of them
know the BIM technology as they like to identify it from their work in some Arabic countries as Qatar,
Arab Emirate, which is considered the BIM leader in the Middle East [10].
They learned from their experience of using BIM tools how it minimizes the most important
problem such as cost and time overrun. Consequently, it can be indicated that the return on BIM
investment will be as a motive for companies’ owners to implement BIM in future. In addition, the
respondents observed that the implementation of BIM will be able in the next five years. Furthermore,
they also identified the barriers and challenges that hinder the application of BIM: economic,
technical, organizational, legal, and human challenges. The experience of the highest proportion of
respondents in the engineering work exceeded 15 years, knowing that 20 % of them are still in the first
stage after graduation with years of experience ranging from 2 to 5 years. As the survey shows, 30 %
of the respondents work in the field of residential construction and 26 % as the second rank for the
education sector, represented by the Syrian universities spread throughout the Syrian areas.
Unfortunately, those with experience over 15 years reject BIM technology; they do not like to change
the way they used to work. However, the authors tried to explain to the traditional engineers that they
will have big experience, which companies always need.

Conclusions
1. Respondents were 89 people representing the segment of the Syrian engineers in several regions
and reflect the Syrian position in the current circumstances.
2. About 35 % of the respondents believe that this should be compulsory and under the guidance of
the government.
3. More than 22 % believe that the designer is the main engine to adopt and convince others about
the benefits of building information modeling (BIM) as part of construction projects in Syria.
4. 49 % of respondents found that BIM can solve 50-75 % of current buildings problems. 61 % of
the respondents believe that BIM can be useful in the design stage, while 21 % indicated that they
can implement BIM in both design and construction stage of the project.
5. In Syria of BIM still is not adopting, but it may be mandated during the next 5 years.
6. 43 % of respondents are using Revit (Architectural, Structural, MEP) and consider themselves as
BIM users.
7. Furthermore, the main perceived obstacles to BIM implementation were identified as economic,
technical, organizational, legal, and human challenges.
8. The authors noted the fact that 15 % only use electronic documentation. Also only 24 % of the
staff received formal training in addition to their effort.
9. 29 % believe that the process of setting an individual standard to deal with the principles and
techniques of BIM is fundamental, while another 50 % find it essential and 9 % find it not very
important.

Acknowledgments
This work was supported by the Grant Agency of the Czech Technical University in Prague, grant
No. SGS17/121/OHK1/2T/11

Footnote
1. BIMarabia: the first e-magazine specialist on BIM. 2015. [online].
http://bimarabia.com/bimarabia-english/
2. BIMdictionary: available at www.bimdictionary.com
3. Succar B.: Founder of BIM Think-space (Oct 2005), available at
http://www.bimthinkspace.com/about.html/

529
ENGINEERING FOR RURAL DEVELOPMENT Jelgava, 23.-25.05.2018.

References
[1] Ahmed S., Dlaska P., Hassan B., Beshara M. “Pre-Cast Concrete, a Key Option for the
Reconstruction Phase after War”, Procedia Engineering, 2017, pp. 211-219. DOI:
10.1016/j.proeng.2017.08.074.
[2] Ahmed S., Hasan B., Jrad F., Dlask P. Analyzing the Change Orders Impact on Building Projects.
Journal of Engineering and Applied Sciences, 11(7), 2016, pp. 1532-1537. [online][19.03.2018]
Available at: http://medwelljournals.com/abstract/?doi=jeasci.2016.1532.1537
[3] Eastman C. The use of Computer instead of Drawings in Building Design. American Institute of
Architecture, 63(3), 1975, pp. 46-50. [online] [19.03.2018] Available at:
https://www.academia.edu/8519182/The_Use_of_Computers_Instead_of_Drawing_in_Building_
Design_-_1975
[4] Succar B. Building information modeling framework: A research and delivery foundation for
industry stakeholders. Automation in Construction, 18, 2009, pp. 357-375.
[5] Penttilä H. Describing the Changes in Architectural Information Technology to Understand
Design Complexity And Free-Form Architectural Expression. ITcon, 11, 2006, pp. 395-408.
[online] [19.03.2018] Available at: http://www.itcon.org/2006/29
[6] Constructing Excellence. UK Industry Performance Report: Based on the UK Construction
Industry Key Performance Indicators. Constructing Excellence, 2008.
[7] Jernigan F. BIG BIM little bim – the practical approach to building information modeling -
Integrated practice did the right way! 1st Edition, Kindle Edition. [online] [19.03.2018] Available
at: https://www.amazon.com/BIG-BIM-little-bim-information-ebook/dp/B0010AE7PS.
[8] Moreno C., Olbina S., Issa R. School of building construction, University of Florida, USA, 2013,
[online] [19.03.2018] Available at: https://doi.org/10.1061/9780784413616.056
[9] NBS. NBS National BIM Report. United Kingdom: RIBA Enterprises, 2017. [online]
[19.03.2018] Available at: https://www.thenbs.com/knowledge/nbs-national-bim-report-2017
[10] Gerges M., Austin S., Mayouf M., Ahiakwo O., Jaeger M., Saad A., Gohary T.E. An investigation
into the implementation of Building Information Modeling in the Middle East, ITcon Vol. 22,
2017, pp. 1-15. [online] [19.03.2018] Available at: http://www.itcon.org/2017/1
[11] Mia R. Performance Management for Syrian Construction Projects. International Journal of
Construction Engineering and Management. 5(3), 2016, pp. 65-78. DOI:
10.5923/j.ijcem.20160503.01.
[12] Matejka P., Tomek A. “Ontology of BIM in a Construction Project Life Cycle”. Procedia
Engineering, Elsevier, 2017. [online] [19.03.2018] Available at:
https://doi.org/10.1016/j.proeng.2017.08.065
[13] Associated General Contractors of America. The Contractor’s Guide to BIM, 1st edition. Las
Vegas: AGC Research Foundation publisher, 2015. [online] [19.03.2018] Available at:
https://www.engr.psu.edu/ae/thesis/portfolios/2008/tjs288/Research/AGC_GuideToBIM.pdf
[14] Bouška R. Evaluation of Maturity of BIM Tools across Different Software Platforms. Procedia
Engineering, 2016, 481 p.

530

You might also like