Government of Haryana: Standard Bidding Document
Government of Haryana: Standard Bidding Document
Table of Contents
Item wise sealed bids on agreement basis/ work order basis are invited by the undersigned, on behalf
of Governor of Haryana, from Contractors/L&C Societies of eligible class registered with Haryana
Irrigation & Water Resources Department or any branch of P.W.D. Haryana. Contractors registered
with CPWD, MES, Railways, Central Government, other State Governments or State Government
undertakings, PSUs are also eligible for participation in the bid shown in the table below:
 Sr.                  Name of work                    Estimate Earnest money              Period of    Cost of bid
 No.                                                  d cost in    (Rs.)                  completi     documents
                                                      lacs                                on
     1                        2                           3     Contractor Society            5                6
 1          Laying RCC Pipe for filling of dry pond   19.50         39000/-     19500/-   8 Months     1000/-
            of Village Tihar Malik from RD 19000/R
            Guhna Minor
 2          Reconstruction of V.R. Bridge at RD       73.47         147940/-    73470/-   12 Months    5000/-
            29650 of Sink Bahadurpur Drain./
 3          Berm cutting from inner section of        5.09          10180/-     5090/-    2 Closures   1000/-
            Bhalaut Sub Branch from RD 38820 oi
            83000
 4          Berm cutting from inner section of        5.22          10440/-    5220/-     2 Closures   1000/-
            Bhalaut Sub Branch from RD 10000 to
            38820
 5          Restoring the bank of Tributary drain     12.72         25440/-     12720/-   6 Months     1000/-
            No. 4 for separating Village Ponds at
            various ponds at various locations
 6          Repair & Maintenance of Gates &           6.96          13920/-    6960/-     4 Months     1000/-
            Gearing at Head RD 83200 Butana
            Branch
 7          Repair of damaged parapets of bridges     2.72          5440/-     2720/-     2Months      500/-
            in Gangessar Section (Butana Branch)
 8          Repair of damaged parapets of bridges     2.60          5200/-     2600/-     2 Months     500/-
            in Rana Kheri Section (Butana Branch)
 9          Making Service Road Jseepable of          1.26          2520/-     1260/-     2 Months     500/-
            Butana Branch fromRD 17000 to
            83200
 10         Making Pucca Road from Canal Rest         1.85          3700/-     1850/-     2 Months     500/-
            House Rana Kheri to Pucca Gohana
            Safidon Road (on labour rate)
 11         Repairing parapets of Bhalaut Sub         1.91          3820/-     1910/-     2 Months     500/-
            Branch in Sub Divn. No. I, Ditch Drain
            along BSB & ditch drain along JLN .
The Tender documents containing detailed terms and conditions can be seen and down load as per Key date.
Time/Date of Submission : from 11.00 Hrs. 4.10.2017 upto 13.00 Hr. on 18.10.2017
Name of Work : -
Name of Agency :-
Agreement No. :-
Item wise sealed Bids on Agreement Basis/ work order Basis are hereby invited by the Executive
Engineer, Gohana Water Services Division, Gohana on behalf of Governor of Haryana from the
Contractors/L&C Societies of eligible class registered with Haryana Irrigation & Water Resources
Department or any branch of P.W.D. Haryana. Contractors registered with CPWD, MES, Railways,
Central Government, other State Governments or State Government undertakings, PSUs are also
eligible for bid shown in the table with the following terms and conditions:-
   1. Bid    document        can   be   downloaded      from    the   website    www.hid.gov.in      &
       https://etenders.hry.nic.in from the date of publication up to 03.10.2017 upto 18:00 Hrs.
       for a non-refundable cost of bid document of Rs.---------- as above List.
       In case of online bids (off line payments) the scanned copy of instruments for payment
       of cost of document shall be up loaded with the online bid submission.
   2. The work will be reserved for Coop. L & C Societies & Contractor mentioned at Sr. No. 1 to 11.
       If the rates given by the Coop. L & C Society are found more than the rates approved by the
       competent authority in the immediate past for similar works then the tenders will only be opened
       to both i.e. Coop. L & C Societies as well as contractors. Earnest money @ 2% cost of the work
       in the shape of DAC/FD etc. has to be deposited by the contractors. The work mentioned at
       Sr. No. 1 to 11 is for both Coop. L & C Societies & Contractors.
   3. Any registered Society/ contractor can purchase the bid documents after payment of
4. Key Dates:-
Time/Date of Submission : from 11.00 Hrs. 4.10.2017 upto 13.00 Hr. on 18.10.2017
         All Bids will be opened by the Executive Engineer, Gohana W/S Division, Gohana at
         15:00 Hrs. on 18.10.2017 in the presence of bidders or their duly authorized
         representatives who may like to be present.
satisfactory manner and both as regards materials and otherwise in every respect, in strict
accordance with the specifications. The Contractor shall also conform exactly, fully and faithfully to the
      designs, drawing and instructions in writing relating to the work signed by the Executive
      Engineer Incharge and lodged in his office and to which the Contractor shall be entitled to have
      access at such office or site of the work for the purpose of inspection during office hours and
      the Contractor shall, if he so requires, be entitled at his own expense, to make or cause to be
      made copies of specifications and of all such design, drawing and instructions, as aforesaid. A
      certificate of having executed works as per approved design and specification, etc. shall be
      given by the Contractor in his each monthly bill. The specification of works, material, and
      methodology of execution, drawing and design shall be signed by the Contractor and Executive
      Engineer while executing agreement and shall form part of agreement.
14.   Pre-bid meeting shall be held in the office of ___________at …………………hours on …………………
      (For works costing more than Rs. 2.00 crores)
15.   A successful bidder, not already registered with the Irrigation & Water Resources Department,
      Haryana will have to submit his application for registration with the Irrigation& Water Resources
      Department, Haryana within 15 days of opening of bids and deposit the necessary license fee,
      within this period. However, enlistment shall not be a prerequisite for submitting bids.
16.   In case of online bids (e-tendering) all the prospective bidders are required to possess digital
      signature certificate (DSC) through any certifying authority designated by the Govt. of India and
      enroll themselves and DSC on the website is to be used for tender purposes.
17.   Prospective bidders are encouraged to seek help specifically provided for contractors on the e-
      tender portal for submission process of the bids and the bidder will be solely responsible for any
      error in online submission of the bid.
18.   The jurisdiction of court will be at Gohana.
SECTION 1
INSTRUCTIONS TO BIDDERS
                                        Instruction to Bidders
                                             Table of Contents
Clause Content                         Page       Clause        Content               Page
                                       No.                                            No.
A. General                             11-18      D. Submission of Bids               23
1.      Scope of Bid                   11         18.      Submission of Bids         23
2.      Source of Funds                11         19.      Deadline for submission of 23
                                                           bids
3.      Eligible Contractor/           11         E. Opening of Bids and Evaluation 23-27
        Agencies
4.      Qualification of Bidders       11-17      20.           Bid Opening                23-25
5.      One Contractor/Agency per      17         21.           Process to be Confidential 25
        bid
6.      Cost of Bids                   17         22.      Clarification of Financial         25-26
                                                           Bids
7.      Site Visit                     18         23.      Examination of Bids and            26
                                                           Determination of
                                                           Responsiveness
B. Bid Documents                       18-19      24.      Correction of Errors               26-27
8.      Bid documents                  18-19      25.      Evaluation and                     27
                                                           Comparison of Financial
                                                           Bids
9.      Pre-bid meeting: (Mandatory 19            F. Award of Contract                        27-30
        for work of value more than
        Rs. 2.00 crore)
10.     Amendment of Bid            19            26.           Award of Contract             27-28
        Documents
C. Preparation of Bids              20-22         27.           Notification of Award and     28
                                                                Signing of Agreement
11.     Documents comprising bid       20         28.           Performance Security          28-30
12.     Contract Price                 20-21      29.           Debarring                     30
13.     Validity of Bids               21         30.           Completion of work            30
14.     Currency of the Bid and        21         31.           Withdrawal of items           30
        payment
15.     Earnest Money                  21-22      32.       Corrupt or Fraudulent             30
                                                            Practices
16.     Forfeiture of Earnest Money 22            33.       Advance payment                   30
17.     Format and signing of bids 22             G. Joint Venture                            30-37
                                                  34.       Terms and conditions for          30-37
                                                            Joint Venture (JV)
                   4.2       (ii) For the works covered under 4.2 (i) (a & c) above,
                                    following qualification criteria will be followed:
                             (A)    To qualify for award of the Contract, each bidder in
                                    its name should have in the last 5 years:
                                   (a)    Achieved in at least one year, a minimum annual
                                          financial turnover (in all classes of civil
                                          engineering construction works only) of 75% of
                                          the annual estimated value of work @. This
                                          should be duly audited by Chartered Accountant.
                                   (b)    Satisfactorily completed, as a prime contractor,
                                          one work of similar nature in a single contract of
                                          value not less than 80% of the value of work@.
                                                        Or
                                          Two works of similar nature of value not less
                                          than 50% of the value of work. @
                                                        Or
                                          Three works of similar nature of value not less
                                          than 40% of the value of work. @
                                   (c)    Executed in any one year the following minimum
                                          quantities of work [50% of the annual estimated
                                          quantities for works with more than 1 year
                                          completion period and 50% of the estimated
                   Note:
                      a) Project Manager – will be required for works costing more
                         than 5 crores. He must possess a degree in civil
                         engineering or equivalent.
                      b) Project Engineer – will be required for works costing more
                         than 1 crores. He must possess a diploma in civil engineering
                         or equivalent and for works costing more than 5 crore the
                         degree of civil engineering or equivalent is required.
4.5 Bid Capacity (To be evaluated for works costing more than `
                                  time)
                                  Bidders who meet the minimum qualification criteria will be
                                  qualified only if their available bid capacity is more than the total
                                  bid value. The available bid capacity will be calculated as under:
                                    Assessed Available Bid capacity = (A x N x M-B), Where
                            A     = Maximum value @ of civil engineering works executed in any one
                                    year during the last five years taking into account the completed as
                                    well as works in progress.
                            N     = Number of years prescribed for completion of works for which bids
                                    are invited.
                            B     = Value at ……………..(the year of execution of the work) price level
                                    of existing commitments and on-going works to be completed
                                    during the next ……… months (period of completion of the works
                                    for which bids are invited).
                            M     = …….(2 or such higher value not exceeding 3 as may be specified by
                                    the Engineer-in-charge herewith and if the value is not filled in, then
                                    it will be considered as 2.5 by default.)
                          Note: The statements showing the value of existing commitments and
                          ongoing works as well as the stipulated period of completion remaining
                          for each of works listed should be countersigned by the Engineer-in-
                          Charge, not below the rank of an Executive Engineer or equivalent.
                          (@) at price level of the current financial year (when bids are opened).
                          The cost of works, executed during previous years, shall be given
                          weightage of 10% per year (compounded yearly) to bring it to the
                          current price level for the year in which bids are opened.
5. One Contractor/        Each Contractor shall submit only one bid. A Contractor who submits
Agency per bid            more than one bid for each work will be disqualified.
6. Cost of Bids            Contractor/Agency shall bear all costs to submit their bid for the work
                           and the department will in no case be responsible and liable for those
                           costs.
7. Site Visit              7.1 The Contractor/Agency is advised to visit and examine the site of
                                 works and its surroundings and obtain for himself on his own
                                 responsibility and at his own cost all information that may be
                             necessary for preparing the bids and entering into a Contract for
                            construction of works. The costs of visiting the site shall be at the
                                 Contractor’s /Agency’s own expense.
                             7.2 The Bidder must visit and see for himself the site conditions
                              including the geological and hydraulic data before bidding. The
                                 Haryana Irrigation & Water Resources Department will not be
                                      responsible if any of the information mentioned in the site
                               investigation report is found at variance with the site conditions
                                 during execution of the work, and consequences thereof, and
                               nothing extra will be payable to him after approval of the tender
                                  rates on account of any variation discovered therein.
                            7.3 Contractor/Agency must assess the availability of sufficient good
                            quality water for construction purposes including that for curing as
                                  specified.
                            7.4 The Contractor/Agency should examine the route for carriage of
                                  construction material upto site of work.
B. Bid Document
8. Bid Documents           8.1 Contents of Bid Document
                                  As per table the set of bidding documents comprises the
                             documents listed below and addenda issued in accordance with
                                Clause 10:
                            Section Particulars
                                    Invitation for Bids
                              1     Instructions to Bidders
                              2     Qualification Information, and other forms
                              3     Conditions of contract
                              4     Special Conditions of Contract
                              5     Contract Data
                              6     Technical Specification
                              7     Form of bid
                              8     Bill of Quantities
                              9     Securities and other forms
                              10    Drawings
                              11    Documents to be furnished by bidder
11. Documents      11.1 The Bidder shall bear all costs associated with the preparation and
comprising bid          submission of its bid, and the Purchaser shall not be responsible
                        or liable for those costs, regardless of the conduct or outcome of
                             the bidding process.
                   11.2 The bid to be submitted by the bidder (refer Clause 8.1) shall be
                             in two separate parts:
                             Part-I shall be named “Technical Bid” which will be submitted
                        online,unless otherwise specified in the NIT and scanned copies
                                of all the requisite documents will be uploaded and original
                        documents will be submitted upto the time of opening of bids , till
                             allowed to do so and it will include the following:-
                              (i)      For bidding documents downloaded from website (refer
                                           IFB), the cost of bidding document will be paid as
                                        specified.
                              (ii)     Bid Security in the form specified under clause 15.
                              (iii) Qualification Information and supporting documents as
                                        specified in Section-2.
                              (iv)      Certificate, undertakings, affidavits as specified in
                                        Section 2.
                              (v)      Information pursuant to Clause 4 of Section 1.
                              (vi) Undertaking that the bid shall remain valid for the period
                                        specified in Clause 13 of Section 1.
                             Part-II shall be named “Financial Bid” and shall comprise of:
                              (i)      Form of Bid as specified in Section 7.
                              (ii)     (Priced Bill of Quantities for items specified in Section 8.
                              (iii)      Both bids will be submitted online in accordance with
                                        Clause 19 unless otherwise specified.
                        11.3 All documents relating to the bid shall be in the Hindi/English
                             language.
12. Contract Price     12.1 The Contract price shall be for the whole work based on the priced
                              bill of quantities submitted by the Contractor/Agencies.
                       12.2 The Contractor/Agency shall fill the rates and prices for all the
                              items in the works described in the bill of quantities. Items for
                              which no rate or price are entered by the Contractor/Agency will not
      17. Format and       17.1 The original and copies of the bid shall be typed or hand
         written signing of bids          and shall be signed by a person or persons duly
authorized to sign on behalf of the Contractor/agencies. The person who has signed the
bid documents shall initial all pages of the bid documents where entries or amendments
     have been made. All documents attached with the bid should be duly signed by the
                                                                               authorized
                            signatory with date.(For Manual Mode)
                          17.2 The rates should be per unit and written in figures, words
                               along with worked out amount. In case of error, the rates
                               written in words will prevail. However, if the rates are given
                               in one form only, then the same shall be considered.
                          17.3 The bid documents shall contain no alterations or additions,
                               except those to comply with instructions issued by the Engineer,
                               or as necessary, to correct errors made by the Contractor/agency,
                               in which case such corrections shall be initialed by the persons
                               signing the bid document. (For Manual Mode)
                          17.4 Bidders shall submit offers that fully comply with the
                               requirements of the bidding documents, including the
                               conditions of contract, basic technical design as indicated in
                               the drawing and specifications. Conditional offer will not be
                               considered further in the process of bid evaluation.
D. Submission of Bids
18. Submission of         18.1 Submission of Bids (Offline)
Bids
                                  (a)   The Contractor/Agency shall seal the original and copy of
                                        the bids in separate envelopes, marked “original” and “copy”
                                        and put these envelopes insides one another envelope,
                                        addressed to the Engineer at the following address.
                          Executive Engineer, Gohana W/S Division, Gohana
                          Do not open Before 18.10.2017 at 15:00 Hrs.
                                  (b)   If the envelope is not sealed and marked as above the
                                        Engineer will assume no responsibility for the
                                        misplacement or premature opening of the bid.
                                  (c)   The envelope containing documents of Technical Bids which
                                        cannot be submitted online (i) be addressed to the Engineer
                                        at the address given in Contract Dates, (ii) bear             the
                                        identification as indicated in clause 20.1 above.
19.3 No bid can be modified after the deadline for submission of bids.
F. Award of Contract
26. Award of        The Engineer will award the Contract to the Contractor/ Agency whose
Contract            bid has been determined to be substantially responsive to the bid
                    document and who has attained the lowest evaluated bid price and whose
                    financial bid has been accepted for award of contract by the Competent
                    Authority provided that such Contractor has been determined to be
                    eligible within the available bid capacity.
27. Notification of 27.1 The Bidder whose Bid has been accepted will be notified of the
Award and Signing          award by the Engineer prior to expiration of the Bid validity
of Agreement               period by cable, telex e-mail or facsimile confirmed by registered
                           letter. This letter (hereinafter and in the Conditions of Contract
                           called the “Letter of Acceptance”) will state the sum that the
                           Employer will pay the Contractor in consideration of the
                           execution, completion, and maintenance of the Works by the
                           Contractor as prescribed by the Contract (hereinafter and in the
                           Contract called the “Contract Price”).
                    27.2 Any concession by the contractor during negotiation will also
                           form part of letter of acceptance and that would be deemed to the
                                   part of the contract agreement. The notification of award will constitute
                                   the formation of the Contract, subject only to the furnishing of
                               the award, forfeiture of the Bid Security and debarring the agency
                               for participating in any bid for one year. Action will be taken to
                               allot work to the next lowest bidder as specified under clause 27.6.
                          28.4 Generally, no consideration shall be given to the offers received
                               after scheduled time of receipt of bids. But if the subsequent offer
                               even from a non-tenderer (received within one week of the
                               previous offer and before the decisions of the contract) is not just
                               marginally but significantly favourable to the Government (to the
                               extent of 5% of the lowest bid amount in case of works costing
                               more than Rs.5.00 crores, 10% in case of works more than Rs.1.00
                               crore but less than Rs.5.00 crores, 20% for in case of works more
                               than Rs.5.00 lacs but less than Rs.1.00 crore and 30% in case of
                               works less than Rs.5.00 lacs or any other limits as decided by
                               Government from time to time), then the subsequent offer can be
                               considered provided the bidder deposits the bid security and
                               unconditional bank guarantee for the difference of the amounts
                               between the offer of the lowest agency and the subsequent fresh
                               offer. In that case, short notice fresh sealed bids shall be invited,
                               with special invitation to the previous participants including the
                               subsequent bidder mentioned above, but with the stipulation that
                               the subsequent bidder shall not bid higher than his previous offer,
                               otherwise his bid security and bank guarantee shall be forfeited.
                               Tender shall be allotted to the lowest valid bid received.
                          28.5 The letter of acceptance shall be issued to the contractor for an
                               amount of its financial offer as evaluated. If this amount is more
                               than 20% above the administrative approval, Govt. /Client’s
                               approval shall be taken. In any case, revised administrative
                               approval shall be sought if the excess over the amount of
                               administrative approval is more than 10%. The client department
                               shall be given sufficient time to arrive at decision, say 30-45 days.
29. Debarring             If the agency submits Financial Bid through e-tendering but fails to
                          submit either bid security or the Technical bid or both, then the agency
                          will be debarred from participating in any bid in Haryana Irrigation &
                          Water Resources Department for one year.
30. Completion of         The agency to whom the work is allotted shall complete the entire work
work                      as per drawing irrespective of quantities in the DNIT. The agency is
                          bound to consult the drawings before submitting bids.
31. Withdrawal of         The Employer can withdraw any item at any stage. No claim on account
items                     of withdrawal will be entertained.
32. Corrupt or            The Engineer will reject a proposal for award if it determines that the
Fraudulent                Bidder recommended for award has engaged in corrupt or fraudulent
Practices                 practices in competing for the contract in question and will declare the
SECTION 2
                                         CONTRACTOR’S BID
Description of the Works :
……………………………………………………………………………………
To:
                  The Executive Engineer,
Address:
                  [1] Gohana Water Services Division, Gohana
Sir,
We offer to execute the work described above in accordance with the conditions of Contract
accompanying this Bid for the Contract Price of Rs.[2] ……………………..….(in figures)
Yours Faithfully,
Authorized
Signatory [2]
Name and Title of Signatory: …………………………………………………………………
Name of Bidder:……………………………………………..………………………………
Address:………………………………………………………………………………………..
Income Tax Pan No.:.………………………………………………………………………….
      [1] To be filled in before issue of the Bid Documents, by the tender issuing authority.
      [2] To be filled in by the bidder, together with his particulars and date of
         submission at the bottom of the Form of Bid.
                                B. QUALIFICATION INFORMATION
       The information to be filled in by the bidder in the following pages will be used for purpose of
Technical Bid Evaluation as provided for in Clause 4 of the ‘Qualification of bidders’. This information
will not be incorporated in the Contract. The Contractor may attach more pages if required.
1.     For individual bidders
1.1    Constitution or legal status of bidder (attach copy).
       Place of registration:                      ……………………………………………...………………
       Principal Place of Business:                ……………………………………………………………...
       Power of attorney of signatory of Bid (attach)
1.2    Total value of Civil Engineering
       Construction work performed in the
       Last Five years (in Rs. Lacs): ……………………………………………...………………
1.3    Civil Engineering Works including earth work performed as prime Contractor ( in the same
       name) over the last Five years ( from 2011-12 To 2014-16).
        Project     Name of       Description   Contract      Value of   Date    Stipulated      Actual date     Remarks
        Name       Employee/       of work        No.         Contact      of     period of          of         explaining
                    Engineer                                   (Rs. in   Issue   completion      completion    reasons for
                    with full                                   lac)       of                                  delay if any
                     address                                             work                                  and if work
                                                                         order                                 completed.
       For 1.3 &1.3(a) certificates from employer/Engineer shall be attached by the contractor.
 1.4    Information on Litigation and arbitration history in which the bidder is involved.(attach more
       sheets if required).
       Other Part (ies)         Employer/Engineer Cause of dispute            Amount involved Remarks
                                                                                              showing Present
                                                                                              status
1.5 Statement of compliance under the requirements of Sub clause 3.2 of the Instructions to Bidders.
      ……………………………………………………………………………………………………..................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
      ..........................................................................................................................................................................................
1.6   Proposed work method and schedule. The bidder should attach description, drawings
      and charts as necessary to comply with the requirements of the Contracts documents.
                                       LETTER OF ACCEPTANCE
(Letter head paper of the Engineer)
                                                                         Dated: ……………………
To
………………………………………………………………
………………………………………………………………
………………………………………………………………(name and address, of the
Contractor) Dear Sirs,
       This is to notify you that your tender dated…………………………….. for execution of
……………………………………………………………………………… (name of the Contract and
identification number as……..………for Rs ……………..………………… (amount in figures)
Rs.………………………………………………… …………( amount in words), as corrected and
modified in accordance with the instructions is hereby, accepted by us/our agency.
       You are hereby requested to furnish performance security in the form detailed in Para
28of Instructions to Bidders (ITB) for an amount equivalent to Rs. …………………………
within 15 days of the receipt of this letter of acceptance and sign the Contract, failing which
action as stated in Para 28 of ITB will be taken.
Yours faithfully,
Executive Engineer,
………………………………….….
……………………………..………
……………………………………..
To
………………………………………
………………………………………
Dear Sirs,
Pursuant to your furnishing the requisite performance security and signing of the Contract for the
work of …………………………………………………………………...……………………………….
……………………………………………………………………………………………………………..
at a Bid Price of Rs………………. , (Rupees…………………………………………………….only)
you are hereby instructed to proceed with the execution of the said works in accordance with the
Contract agreement.
Yours faithfully,
                                       AGREEMENT FORM
              (TO BE EXECUTED ON A NON JUDICIAL STAMP PAPER OF RS.15/-)
Agreement Deed
This agreement, made on the ………… day of ………. 20 … between the Governor of Haryana, acting
through ………………… ……………………………….. [name and address of Engineer] (hereinafter
called “the Engineer” which expression shall, unless the Contract otherwise requires, be deemed to
include his successors and assigns) of the one part and …………..…………………..….. [name and
address of Contractor] (hereinafter called “ the Contractor” which expression shall unless the Contract
otherwise requires, be deemed to include his successors and assigns) of the other part.
SECTION-3
CONDITIONS OF CONTRACT
                                        Conditions of Contract
                                              Table of Contents
Clause Content                    Page            Clause         Content                           Page
                                  No.                                                              No.
A. General                        45-54           C. Quality Control                               56
1.      Definitions               45-47           29             Identifying Defects               56
2.      Interpretation            47-48           30             Tests                             56
3.      Language of Bid           48              31             Correction of Defects             56
4.      Engineer to act on behalf 48              32             Uncorrected Defects               56
          of employer
5.        Communications in             48        D. COST CONTROL                                  56-63
          writing
6.        Sub-Contract                  48    33                 Bill of quantities                56
7.        Personal                      48    34                 Increase in cost of works/items   56
8.        Other Contractors             48-49 35                 Changes in the quantities,        57-58
                                                                 design, specification and
                                                                 payment thereof
9         Risk                          49        36             Break up of rates                 58
10.      Site Investigation Report      49        37             Cash Flow Forecast                58
11.      Dewatering arrangement         49        38             Payment certificates              58-59
12.      Queries about Contract         49        39             Compensation Events               59-60
         data
13       Possession of Site             49-50 40                 Deductions from bills             60
14       Access to the Site             50    41                 Retention Money/Security          60-61
                                                                 Deposit
15       Start of work                  50        42             Liquidated Damages                61
16       Works to be completed by       50        43             Price Adjustment                  61-62
         the Intended Date
17       Instructions                   50-51 44                 Cash Flow Forecasts               62
18       Defect Liability period        51    45                 Loss or damage to the             62
                                                                 work/material
19     Safety                           51        46             Certificate of completion         62
20     Things of historical value       51        47             Taking over site on completion    62
       found at site
21     Environmental Protection         51        48             Advance Payment                   62-63
22     Insurance                        51-52     49             Secured advance                   63
23     Dispute Redressal System         52-54     E.FINISHING THE CONTRACT                         63-66
B. Time Control                         54-55     50       Certificate of Final Payment            63
24      Programme                       54        51             Breach of Contract                63-65
25     Extension of the Intended        54-55     52             Consequences of breach of         65
       Completion Date                                           contract
26     Delays ordered by                55        53             Release from Performance          65
       Engineer
27     Management Meetings              55        54             As built drawings                 65-66
28     Early warning                    55        55             Retention Money                   66
                                Conditions of Contract
                                          A. General
1.Definitions          1.1 Terms which are defined in the Contract Data are also defined
                            in the Conditions of Contract but keep their defined meanings.
                            Capital initials are used to identify defined terms.
                        (a)     BILL OF QUANTITIES (BOQ) means the priced and
                                completed Bill of Quantities forming part of the Tender
                                Document.
                        (b)     COMPLETION DATE is the date of completion of the works
                                as certified by the Engineer.
                        (c)     CONTRACT is the Contract between engineer/employer and
                                the Contractor to execute, complete and maintain the works.
                        (d)     CONTRACT DATA defines the documents and other
                                information which comprise the Contract.
                        (e)     CONTRACTOR is a person or corporate body whose bid to
                                carry out the Works has been accepted by the Engineer.
                        (f)     CONTRACT PRICE is the price stated in the Letter of
                                Acceptance and thereafter as adjusted in accordance with the
                                provisions of the Contract. (Clause 12 of ITB)
                        (g)     COMPENSATION EVENTS are those defined in Clause 40 of
                                Conditions of Contract.
                        (h)     COMPETENT AUTHORITY is the authority competent to
                                exercise the financial powers as provided for, in the D.F.R.
                                (Departmental Financial Rules) in respect of officers of
                                Haryana Irrigation & Water Resources Department, of the
                                Govt. of Haryana or other relevant provisions under various
                                Govt. of Haryana rules and regulations.
                        (i)     DAYS are calendar days; months are the calendar months.
                        (j)     DEFECT is any part of the Works not completed in accordance
                                with the Contract.
                        (k)     DEFECT LIABILITY PERIOD is the period named in the
                                Contract Data and calculated from the completion Date.
                        (l)     EMPLOYER is the Governor of Haryana acting through Chief
                                Engineer (concerned), Haryana Irrigation & Water Resources
                                Department, Sinchai Bhawan, Panchkula for works costing
                                more than Rs.50.00 crore and concerned Superintending
                                       what part of site was not handed over and the execution of
                                       which part of the work was affected. If the contractor had
                                       sufficient work front and the balance site is handed over in
                                       the meantime, he shall not be entitled to time extension
      14. Access to the The Contractor shall allow the Engineer and any person
    authorized by Site         the Engineer or any other person to perform his duties
         required to perform his duties access to the site, to any place where work in
 connection with the Contract is being carried out or is intended to be carried out and
                                      to any place where materials or plant are being
                      manufactured/fabricated/assembled for the works.
15. Start of work           15.1 The Contractor shall construct and install the works in
                                 accordance with the Specification and Drawings.
                            15.2 The Contractor may commence execution of the works
                                 on the Start Date and shall carry out the works in
                                 accordance with the programme submitted by the
                                 Contractor, as updated with the approval of the Engineer,
                                 and complete them by the Intended Completion Date.
                            15.2 The Contractor shall be responsible for design of
                                 Temporary Works.
                            15.3 The Engineers approval shall not alter the Contractors
                                 responsibility for design of the Temporary Works.
                            15.4 The Contactor shall obtain approval of third parties to the
                                 design of the Temporary Works where required, subject
                                 to approval by Engineer.
                            15.5 All Drawings prepared by the Contractor for the execution
                                 of the temporary or permanent Works, are subject to prior
                                 approval by the Engineer before their use.
16. Works to be             16.1 The Works are to be completed by the intended
    completed by the             Completion Date
    Intended Date           16.2 The Contractor will commence execution of the works on the
                                 Start Date and shall carry out the works in accordance with the
                                 action program submitted by the Contractor, as updated with the
                                 approval of the Engineer and complete them by the Intended
                                 Completion Date. The completion shall include making the site
                                 good and free from post construction maladies.
17. Instructions            17.1 The Contractor shall carry out all instructions of the Engineer,
                                 which comply with the applicable laws where the site is
                                 located.
                            17.2 Engineer can delegate any of his duties and responsibilities to
                            22.3 If the Contractor does not provide any of the policies and
                                 certificates required, the Employer may affect the insurance
                                 which the Contractor should have provided and recover
                                     premium the Employer has paid, from payments otherwise due
                                     to the Contractor or, if no payments are due then premium
Engineer.
                        (ii) One official member not below the rank of the Chief
                             Engineer and
24. Programme 24.1. Within the time stated in the Contract Data, the Contractor
                          shall submit to the Engineer, a work Program along with
                          PERT/CPM chart, method statement and quality
                          management plan.
                    24.2. An update of the Program shall be a Program showing the
                          actual progress achieved on each activity and the effect of
                          the progress achieved on the timing of the remaining work
                          including any changes to the sequence of the activities.
                    24.3. The Contractor shall submit to the Engineer, for approval,
                          an updated Program at intervals no longer than the
                          period stated in the Contract data. If the Contractor does
                          not submit an updated Program within this period, the
                          Engineer may withhold the amount stated in Contract
                          data from the next payment certificate and continue to
                          withhold this amount until the next payment after the date
                          on which the overdue Program has been submitted.
                            24.4. The Engineer’s approval of the Program shall not alter
                                  the Contractor’s obligations. The Contractor may revise
                                  the Program and submit it to the Engineer again at any
                                  time. A revised Program is to show the effect of
                                  variations and compensation events, if any.
25. Extension of the 25.1. The Engineer shall extend the Intended Completion Date if a
    Intended                Compensation Event occurs or a Variation is issued which
   Completion Date                     makes it impossible for completion to be achieved by the
                                       Intended Completion Date without the Contractor taking steps
                                       to accelerate the remaining work and which would cause the
                                       Contractor to incur additional cost. However Engineer shall
                                  seek approval of competent authority.
                            25.2. The Engineer shall examine whether and by how much to
                                  extend intended Completion Date within 15 days of the
                                       Contractor asking the Engineer for a decision upon the effect
                                       of a Compensation Event of Variation and refer it for decision
                                       to the Competent Authority and submitting full supporting
                                       information. If the Contractor has failed to give early warning
                                       of a delay or has failed to co-operate in dealing with a delay,
                                        C. Quality Control
29. Identifying The Engineer shall check the Contractor’s work and notify the
    Defects          Contractor of any Defects that are found. Such checking shall not
                            affect the Contractor’s responsibility. The Engineer may instruct the
                            Contractor to search for a defect and to uncover and test any work
                            that the Engineer considers may be defective.
30. Tests                  If the Engineer instructs the Contractor to carry out a test not specified
                           in the Specifications to check whether any work has a defect and the
                         test shows that it has, the Contractor shall pay for the test and any
                            samples. If there is no defect the test shall be a Compensation Event,
                            and the cost shall be borne by the department as Compensation Event.
31. Correction of          31.1 The Engineer shall give notice to the Contractor of any defects
   Defects                       before the end of the Defects Liability Period, which begins at
                                 completion and is defined in the Contract Data. The Defects
                                 Liability Period shall be extended for as long as the defects
                           remain to be corrected.
                     31.2. Whenever a notice of a defect is given, the Contractor
                           shall correct the notified defect within the length of time
                           specified by the Engineer’s notice.
32. Uncorrected In the event of the Contractor failing to remedy the defects, or
    Defects          remove the material that is of inferior quality than the quality
                     contracted for, within a period specified by the Engineer, on his
                     demand, then the Contractor shall be liable to pay compensation
                            which shall be determined by the Engineer, depending on the nature
                            of defect, provided that it shall not exceed the amount which will be
                            required to set it right, by the Engineer himself or through an outside
                            agency whichever is higher.
                                          D. Cost Control
33. Bill of quantities 33.1. The Bill of Quantities shall contain items for the construction,
                              installation, testing and commissioning work to be done
                              by the Contractor.
                     33.2. The Bill of Quantities is used to calculate the Contractor’s
                            Price. The Contractor is paid for the quantities of the work
                            done at the rate in Bill of Quantities for each item.
34. Increase in cost If total cost of work exceeds by more than 5% and individual
    of works/items quantity for any particular item exceed by more than 50%, the further
                     execution will be done on the already approved rates after approval
                     by the competent / sanctioning authority.
35. Changes in the 35.1. The Engineer shall have the power to make any alterations,
quantities, design,      omissions or additions to, or substitutions for, the original
specification and        specifications, drawings, designs and instructions that may
payment thereof          appear to him to be necessary during the progress of the work
                         and the Contractor shall carry out the work in accordance with
                         any instructions which may be given to him in writing signed
                         by the Engineer and any such alterations, omissions, additions
                         or substituted work, which the Contractor may be directed to
                         do in the manner, as specified above as part of the work, shall
                         be carried out by the Contractor on the same conditions in all
                         respects on which he agreed to do the main work. The time
                         for the completion of the work shall be extended in the
                         proportion that the cost of the altered, additional or substituted
                         work bears to the original Contract Work and the decision of
                         the Engineer, after approval from the competent authority,
                         shall be conclusive to such a proportion or as may be decided
                         by Engineer defining up on nature of enhanced work. The
                         rates for such altered, additional or substituted work under
                         this clause shall be worked out in accordance with the
                         following provisions in their respective orders.
                            35.2   If the rates for the reduced, altered, additional or substituted
                                   works, are specified in the Bill of Quantity the Contractor is
                                   bound to carry out the reduced, additional, altered or
                                   substituted work at the same rates as are specified in the
                                   Contract.
                            35.3 If the rates for the altered, additional or substituted work are
                                   not specifically provided in the Contract for the work, then
                                   such rates will be derived from the rates for a similar class of
                                   work as are specified in the Contract for the work.
                            35.4 If the rates for the altered, additional or substituted work can
                                   not be determined in the manner specified above, then the
                                   rates for such work/item shall be worked out on the basis of
                                   the Haryana Schedule of Rates plus/minus the percentage of
                                   the total bid amount vis-à-vis the estimated cost of the entire
                                   work put to bid.
                            35.5 If the rates for such work cannot be determined in any of the
                                   manners specified above, then the Contractor shall, within
                                   seven days of being ordered to carry out such alteration,
                                   addition or substitution, provide to the Engineer with a
                                     Engineer.
                           38.4 The value of work executed shall comprise the value of
                                the quantities completed as per the Bill of Quantities.
                           38.5 The value of work executed shall include the valuation of
                                variation, and compensation events.
                           38.6 The Engineer may exclude any item certified in a previous
                                certificate or reduce the proportion of any previously
                                certified in any certificate in the light of later information.
                           38.7 Full rates will be paid in running account bills for the
                                executed works as per specifications, if any work is found
                                substandard after quality control tests, deductions, as per
                                PWD code, will be made from the future running bills or
                                from retention money and performance security if further
                                running bill is not due to the contractor.
39. Compensation 39.1 The Contractor shall not be entitled to compensation to the
    Events              extent that the Engineers interests are adversely affected by the
                        Contractor not having given early warning or not having
                        cooperated with the Engineer.
                   39.2 The following are Compensation Events, for the purpose of
                        extension in time only, unless they are caused by the
                        Contractor:
                        39.2.1 The Engineer, during the currency of the work, orders
                                 a delay beyond 30 days on any account.
                                     39.2.2 The Engineer gives an instruction for dealing with an
                                            unforeseen condition caused by the Engineer or
                                            additional work required for safety or other reasons.
                                     39.2.3 The Engineer unnecessarily delays issuing a certificate
                                             of completion.
                                     39.2.4 Other Compensatory events as given in Contract Data.
                                     39.2.5 The Employer modifies the schedule of other
                                            contractors in a way which affects the work of the
                                            contractor under the contract.
                                 39.2.6 Other contractors, public authorities, utilities or the
                                         Employer do not work within the dates and other
                                         constraints stated in the Contract, and they cause delay
                                         or extra cost to the Contractor.
                           39.3 If a compensation event would cause additional cost or would
                                 prevent the work being completed by the Intended Completion
                                 days;
                      (c)        the Employer or the Contractor is made bankrupt or goes into
                                 liquidation other than for a reconstruction or amalgamation;
                      (d)        a payment certified by the Engineer is not paid by the
                                 Employer to the Contractor within 56 days of the date of
                                 the Engineer’s certificate;
                      (e)        the Engineer gives Notice that failure to correct a
                                 particular Defect is a fundamental breach of Contract
                                 and the Contractor fails to correct it within a reasonable
                                 period of time determined by the Engineer;
                      (f)        the Contractor does not maintain a security/safety which
                                 is required.
                      (g)        if the Contractor, in the judgment of the Employer has
                                 engaged in corrupt or fraudulent practices in competing
                                 for or in executing the Contract
                      (h)        Non-employment of key personnel as per Clause 4.2 (ii)
                                 B (b) of ITB.
                      (i)        Progress of work is very slow and in the opinion of the
                                 Engineer, the contractor is not likely to complete the
                                 work even within 1½ times of the originally scheduled
                                 construction period without sufficient reasons.
                                 For the purpose of this paragraph “corrupt practice” means
                                 the offering, giving, receiving or soliciting of anything of
                                 value to influence the action of a public official in the
                                 procurement process or in contract execution, “Fraudulent
                                 practice: means a misrepresentation of facts in order to
                                 influence a procurement process or the execution of a
                                 contract to the detriment of the Employer, and includes
                                 collusive practice among Bidders (prior to or after bid
                                 submission) designed to establish bid prices at artificial
                                 non-competitive levels and to deprive the Employer of the
                                 benefits of free and open competition.”
                      51.2       When either party to the Contract gives notice of a
                                 breach of contract to the Engineer for a cause other
                                 than those listed under Sub Clause 50.1 above, the
                                 Engineer, with the approval of the Competent Authority,
                                 shall decide whether the breach is fundamental or not.
                      51.3       Notwithstanding the above, the Engineer, with the
                                 approval of the Competent Authority, may terminate the
                                 Contract for convenience.
SECTION-4
                                              SECTION-4
                            SPECIAL CONDITIONS OF CONTRACT
1.   The various works shall be done in line to line level and grade. The periodical checking of these by
     the Engineer or Engineer’s representative shall not absolve the Contractor of his responsibility
     regarding their accuracy. In case of any deviation or discrepancy in line, level or grade at the
     meeting faces, the Contractor shall make good the discrepancy at his own cost and without any
     compensation for the additional work, if any involved. The Engineer shall further have right, if need
     be, to rectify the discrepancies and recover the cost from the Contractor.
2.   All materials, before being incorporated in the work, shall be inspected by the Engineer
     or his representative and, if necessary, tested before use. Any work, on which such
     materials are used without approval and written permission of the Engineer, is liable to
     be considered as defective and not acceptable.
     2.1       The day to day and periodical tests, to be carried out on materials, mixes and
               placed concrete, etc., shall be specified by the Engineer from time to time and
               the Contractor shall allow all the facilities and cooperation towards collections of
               samples etc. All labour for collecting samples for tests will be supplied by the
               Contractor free of cost to the Engineer. Testing charges shall be borne by the
               Contractor in all cases. Transportation of work samples from work site to and fro
               from the laboratory shall be arranged by the Contractor at his own cost.
     2.2       An authorized representative of the Contractor shall remain present at the time when the
               samples are taken and shall authenticate the facts, if so required. If the Contractor’s
               representative fails to be present as aforesaid, the samples or cores, etc. as are taken
               by the Engineer or his representatives shall be considered to be authentic. The
               Contractor will however be informed of the details of such samples having been taken.
     2.3       The materials, mixes and the cores shall be tested day to day and periodically at the
               laboratory and the results given thereby shall be considered correct and authentic by the
               Contractor. The Contractor shall be given access to all operations and tests that may be
               carried out as aforesaid so that he may satisfy himself regarding the procedure and
               method adopted. It shall then be the Contractor’s responsibility to produce the works,
               materials and finished item to the standards based on the laboratory design and tests.
     2.4       The methods of sampling, testing, procedures and standards shall be laid down
               by the Engineer from time to time.
     2.5       The quality and quantity of material shall be the responsibility of the Contractor,
               irrespective of the test results being good.
3.   Arrangement of water and electric power, etc. required by the Contractor for the work
     shall be made by him at his own cost. Engineer will, however, recommend to the
     concerned State Electricity Utilities for providing the connection and power to the
     Contractor, however, the Engineer will bear no responsibility in this respect.
     3.1       Contractor shall not be allowed to start the work till Engineer is satisfied with the proper
               arrangement of good quality water for execution of work including curing for 28 days.
               For this, the Contractor shall have to construct water storage tanks of sufficient capacity.
               No extra payment shall be made on this account. Any delay in execution of work due to
               non-availability of sufficient water will be responsibility of the Contractor.
4.   The Contractor shall not set fire to any standing jungle, trees, ‘bush’ wood or grass
     without a written permission from the Engineer.
     4.1       When such permission is given and also in all cases when destroying of dug trees,
               bush wood, grass, etc. by fire the Contractor shall take necessary measures to
               prevent such fire spreading to or otherwise damaging surrounding property.
     4.2       Any damage caused by the spreading of such fire, whether in or beyond limits of
               the Engineer’s property shall be made good by the Contractor within a period
               specified by the Engineer or in default the amount of the damage shall be
               recovered by the Engineer from the Contractor’s bill as damages or deducted by
               any other duly authorized officer from any sums that may be due or become due
               from the Employer to the Contractor under the Contract or otherwise.
     4.3       The Contractor shall bear the expenses of defending any action of law
               proceedings that may be brought by any person by injury sustained owing to
               neglect of precautions to prevent the spread of fire and shall pay any damage,
               and cost that may be awarded in consequence.
5.   The Engineer may order the Contractor to suspend any work that may be subject to
     damage by climatic conditions and no claim of the Contractor will be entertained by the
     Engineer on this account.
6.   A site order book shall be kept on the site of the work. As far as possible, all orders, regarding
     the work are to be entered in this Book. All entries therein shall be signed by the Engineer or his
     authorized representative and the Contractor or his authorized representative. In important
     cases, the Engineer will countersign the entries which have been made. The site order book
     shall not be removed from the work site except with the written permission of the Engineer and
     the Contractor or his representative shall be bound to take note of all instructions and directions
     meant for the Contractor as entered in the site order book without having to be called on
     separately to note them. The authorized representative of the Engineer shall submit periodically
     copies of the remarks in the site order book to the Engineer for record and to the Contractor for
     submitting compliance report.
7.   The Contractor shall confirm to the regulations, bye-laws or any other statutory rules
     made by any local authority or by the Government and shall protect and indemnify the
     Engineer against any claims or liability arising from or based on the violations of any
     such laws, ordinance, regulations, orders and decrees, etc.
8.   The Contractor shall make his own arrangement for supply of all materials including
     cement and steel. The Contractor shall be responsible for all transportation and storage
     of the materials at site and shall bear all the related costs. The Engineer shall be
     entitled, at any time, to inspect or examine all such materials. The Contractor shall
     provide reasonable assistance for inspection or examination as may be required.
     8.1       The Contractor shall keep an accurate record for use of materials like cement and steel
               used in the works in a manner prescribed by the Engineer.
     8.2       Large stock of cement shall not be kept at the work site but only sufficient quantities
               shall be kept to ensure continuity of the work. The Contractor shall provide and maintain
               efficient water proof storage sheds for cement on the site of work. It shall be stacked on
               the platform 30 cm above the floor level and shall be covered with tarpaulin or any other
               impervious covering material in order to protect the cement bags from moisture. The
               cement shall be neatly stacked in an orderly manner so as to allow an easy access and
                count. The arrangement of storage and utilization shall be such as to ensure the
                utilization of cement in order of its arrival at the stores and the Contractor shall
                maintain satisfactory records which would at any time show the date of receipt
                and proposed utilization of cement lying in the stores at site.
9.    The Contractor shall comply with all labour laws, rules and regulations thereof as
      applicable from time to time in respect of the labour engaged directly or indirectly on the
      work by him or through his sub-Contractor.
10.   The Contractor shall, so for as reasonably practicable, having regard to local conditions,
      provide on the site, to the satisfaction of the Engineer, an adequate supply of drinking
      and other water for the use of the Contractor’s staff and work force.
11.   At every workplace at which 50 or more women workers are ordinarily employed there
      shall be two huts for use by children under the age of 6 years belonging to such
      women. One hut shall be used for infants to play and other for bed rooms. The huts
      shall not be constructed on a lower standard than the following:-
      (i)       Thatched roofs over tin roofs.
      (ii)      Mud floors and walls of bricks
      (iii)     Plants spread over the mud floor and covered with matting.
      (iv)      The huts shall be provided with suitable and sufficient openings for light and ventilation.
                There shall be adequate provision of sweepers to keep the places clean. Adequate
                arrangement for toilet facilities and fuel will be made by Contractor for labour at site.
12.   The Contractor shall also construct and equip at his cost a working office with electricity
      and water arrangement for site Engineer.
13.   The contractor shall also provide instruments for setting up field laboratory at his own
      cost to site Engineer. No separate payment shall be made for this.
14.   The Contractor shall pay not less than fair-wages to the labour engaged in his work
      directly by him or through his sub-Contractor. Fair wage would mean the wage, whether
      for the whole or piece work, as notified from time to time and where such wage
      prescribed by the District Authorities of the district in which the work is done.
15.   The Engineer shall have the right to deduct from the money due to Contractor any sum required
or estimated to be required for making good the loss suffered by a worker or workers by reason
      of non-fulfillment of the condition of Contract for the benefit of the workers vis-à-vis the
      Haryana Government, the Contractor shall be primarily liable for all payments to be
      made under and for the observance of the rules, regulations and labour law without
      prejudice to his right to claim indemnity from his sub-Contractor.
17.   Force Majeure
      Neither party shall be liable to each other, for any loss or damages, occasioned by or
      arising out of acts of God such as unprecedented floods, volcanic eruptions,
      earthquakes or other invasion of nature and other such acts.
18.   Cement contents
      Actual cement required for the aggregates in concrete to be used shall be determined
      by laboratory test while designing the concrete mixes. If the cement contents of the
      design mix of that grade come less than the provision of cement contents provided in
      the Haryana Scheduled of Rates, (with latest amendments) due to durability conditions,
      the cement contents as provided in the Haryana Schedule of Rates shall be used and
      no extra payment on this account shall be made to the contractor.
19.   Labour
      The Contractor shall, unless otherwise provided in the Contract, make his own arrangement for
      the engagement of all staff and labour, local or other, and for their payment, housing, feeding
      and transport. The Contractor shall, if required by the Engineer, deliver to the Engineer a return
      in detail, in such form and at such intervals as the Engineer may prescribe, showing the staff
      and the numbers of the various classes of labour from time to time employed by the Contractor
      on the site and such other information as the Engineer may require.
20.   Compliance with labour regulations
      During continuance of the contract, the Contractor and his sub contractors shall abide at all time
      by all existing labour enactments and rules made there under, regulations, notifications and bye
      laws of the State or Central Government or local authority and any other labour law (including
      rules), regulations, bye laws that may be passed or notification that may be issued under any
      labour law in future either by the State or the Central Government or the local authority. Salient
      features of some the major labour laws that are applicable to construction industry are given
      below. The Contractor shall keep the employer indemnified in case any action is taken against
to be provided by the Contractor to contract labour and in case the Contractor fails to
provide, the same are required to be provided, by the Principal Employer by Law.
employing 100 or more workmen (employment size reduced by some of the State and
Central Government to 50). The Act provides for laying down rules governing the
          conditions of employment by the Employer on matters provided in the Act and get the
          same certified by the designated Authority.
(xii)     Trade Union Act 1926: The Act lays down the procedure for registration of trade
          unions of workmen and employers. The Trade Unions registered under the Act
          have been given certain immunities from civil and criminal liabilities.
(xiii)    Child Labour (Prohibition & Regulation) Act 1986: The Act prohibits employment of
          children below 14 years of age in certain occupations and processes and provides for
          regulation of employment of children in all other occupation and processes. Employment
          of Child Labour is prohibited in Building and Construction Industry.
(xvi)     Inter-State Migrant workmen’s (Regulation of Employment & Conditions of Services)
          Act 1979: The Act is applicable to an establishment which employs 5 or more inter-
          state migrant workmen through an intermediary (who has recruited workmen in one
          state for employment in the establishment situated in another state). The Inter-State
          migrant workmen, in an establishment to which this Act becomes applicable, are
          required to be provided certain facilities such as housing, medical aid, traveling
          expenses from home up to the establishment and back, etc.
(xv)      The Building Other Construction workers (Regulation of Employment and Conditions
          of Services) Act 1996 and the Cess Act 1996: All the establishment who carry on
          any building or other construction work and employs 10 or more workers are
          covered under this Act. All such establishments are required to pay cess at the rate
          not exceeding 2% of the cost of construction as may be modified by the
          Government. The Employer of the establishment is required to provide safety
          measures at the Building or construction work and other welfare measures, such as
          Canteens, First Aid facilities, Ambulance, Housing accommodation for workers near
          the work place etc. The Employer to whom the Act applies has to obtain a
          registration certificate from the Registering Officer appointed by the Government.
(xvi)     Factories Act 1948: The Act lays down the procedure for approval at plans before setting up
a factory, health and safety provisions, welfare provisions, working hours, annual earned
     (iii)     The Environment (Protection) Act 1986: This provides for the protection and
               improvement of environment and for matters connected therewith, and the prevention of
               hazards to human beings, other living creatures, plants and property. ‘Environment’
               includes water, air and land and the interrelationship which exists among and between
water, air and land, and human beings, other living creatures, plants, micro-organism and
                property.
      (iv)      The Public Liability Insurance Act 1991: This provides for public liability insurance for the
                purpose of providing immediate relief to the persons affected by accident occurring
                while handling hazardous substances and for matters connected herewith or incidental
                thereto. Hazardous substance means any substance or preparation which is defined as
                hazardous substance under the Environment (Protection) Act 1986, and exceeding such
                quantity as may be specified by notification by the Central Government.
22.   Substantial Completion
      (a)       If any part of the Permanent Works has been substantially completed and has
                satisfactorily passed any Test on Completion prescribed by the Contract, the
                Engineer may issue a Taking Over Certificate in respect of that part of the
                Permanent Works before completion of the whole of the Works and, upon the
                issue of such Certificate, the Contractor shall be deemed to have undertaken to
                complete with due expedition any outstanding work in that part of the Permanent
                Works during the Defects Liability Period.
      (b)       When the whole of the Works have been substantially completed and have satisfactorily
                passed any Tests on Completion prescribed by the Contract, the Contractor may give a
                notice to that effect to the Engineer, with a copy to the Employer, accompanied by a
                written undertaking to finish with due expedition any outstanding work during the
                Defects Liability Period. Such notice and undertaking shall be deemed to be a request
                by the Contractor for the Engineer to issue a Taking-Over Certificate in respect of the
                Works. The Engineer shall, within 21 days of the date of delivery of such notice, either
                issue to the Contractor, with a copy to the Employer, a Taking-Over Certificate, stating
                the date on which, in his opinion, the Works were substantially completed in accordance
                with the Contract, or give instructions in writing to the contractor specifying all the work
                which, in the Engineer's opinion, is required to be done by the Contractor before the
                issue of such Certificate. The Engineer shall also notify the Contractor of any defects in
                the Works affecting substantial completion that may appear after such instructions and
                before completion of the Works specified therein. The Contractor shall be entitled to
                receive such Taking-Over Certificate within 21 days of completion, to the satisfaction of
                the Engineer, of the Works so specified and remedying any defects so notified.
SECTION-5
CONTRACT DATA
SECTION 5
CONTRACT DATA
1.    The Employer is
      Name                             :   Governor of Haryana through……….                        [Cl 1.1 of COC]
      Address                          :   Executive Engineer, Gohana W/S Division, Gohana
 2.   Name of the Engineer:                Navtej Sihag                                           [Cl 1.1 of COC]
      Address                          :   Executive Engineer, Gohana W/S Division, Gohana
3.    Names of Authorized Representatives of the Engineer:- SDO, Gohana W/S Sub
                                           Division Gohana                                       [Cl 1.1 of COC]
4.    The Name and identification number of the Contract is ………………………………..
      Internal clearance of ---------------------------------------------. (Insert name and
7.    Milestone dates:
      Milestone 1 i.e. 25% date……… in 5 days (whole work upto a value of 20%)
      Milestone 2 i.e. 50% date …….…in 10 days (whole work upto a cumulative value
      of 45%) Milestone 3 i.e. 100% date ………… in 20 days (Complete works)
8.    The following documents also form part of the Contract: i.e. undertaking of the bidder, if any
      ………………………………………….……………………………                                                               [Cl 2.3 of COC]
9.    The Contractor shall submit a programme for the work within 21 days of delivery of the letter of
      Acceptance. The period between Program update shall be 60 days. [Cl 22of COC]
10.    The site possession dates shall be within 10 days of execution of Contract.
                                                                                        [Cl 13of COC]
       The site is located at Near village-----------.
       And is shown in drawing No………………………………………………………………………
11.    The Defects liability period shall be 90 days for works costing upto Rs. 50 lacs and 180 days for
       works costing above Rs. 50 Lacs, except for pucca works, for which it shall be 1 year from the
       date of issue of completion certificate.                               [Cl 1.1 and 18of COC]
12.    The minimum insurance cover for physical property, injury and death is Rs.5 lacs per occurrence
       with the number of occurrences limited to four. After each occurrence, contractor will pay
       additional premium necessary to make insurance valid for four occurrences always. Engineer
       will be indemnified against any risk. Insurance will be taken in joint names of the Engineer and
       Contractor and a copy will be lodged with the Engineer.                          [Cl 22 of COC]
 13.   The following events shall also be Compensation Events.                [Cl 1.1 and 40 of COC]
       (Cross out if not applicable)
       (i)       Substantially adverse ground conditions encountered during the course of execution of
                 work not provided for in the bidding document.
       (ii)      Removal of underground utilities detected subsequently.
       (iii)     Removal of unsuitable material like marsh, debris, dumps, etc not caused by the
                 contractor and not included in the BOQ.
       (iv)      Presence of historical, archeological or religious structures, monuments interfering with
                 the works detected later on.
       (v)       Restriction of access to ground imposed by civil, judicial, or military authority.
       (vi)      None handing over of all the parts of the site to the contractor.
       (vii)     If no defect is found in a test as directed by Engineer outside the specific tests as per
                 Clause 30.
14.    The Proportion of payment retained (retention money):6% from each bill subject to a maximum
subject to maximum 10% of value for the work/final Contract provided that the amount of
        Liquidated Damages will not exceed 20% of the value of balance work after due date of
        completion.                                                                     [Cl 42 of COC]
16.     Percentage for the work not completed will be 20%.                              [Cl 52 of COC]
17.     The standard form of Performance Security acceptable to the Employer shall be an
        unconditional Bank Guarantee of the type as presented in the Bid Document.
18.     Jurisdiction of Court:
        In the event of any matter concerning this Contract, the Competent Court shall be the court
        having jurisdiction over the place where the agreement was executed.
  19.   The laws, which apply to the contract, are the laws of the land.                 [Cl 3 of COC]
  20.   The language of the Contract documents is English.                               [Cl 3 of COC]
  21.   Limit of subcontracting [not more than 50% of the initial contract price]        [Cl 6 of COC]
  22.   Limit of Joint Venture [not less than 10 crore of the cost of invited bid].      [Cl 34 of ITB]
  23.   The currency of the Contract is Indian Rupees.                                   [Cl 14of ITB]
24.     As built drawings
        The date by which “as built” drawings (in scale as directed) in 2 sets are required is within 28 days
        amount to be withheld for failing to supply “as built” drawing by the date required equal
        to 0.25% of Contract Price. [Cl 54 of COC]
25. Price Adjustment clause:                                                            [Cl 43 of COC]
        The formula (C) for adjustment of price is”
of issue of certificate of completion of whole or section of the work, as the case may be.The
        (i)       Price adjustment for increase or decrease in the cost of cement procured by the
                  Contractor shall be paid in accordance with the following formula:-
                  Vc = 0.85 X Pc/ 100 X R X (Ci-Co) / Co
                  Vc = Increase or decrease in the cost of work for during the quarter under
                           consideration due to changes in rates for cement.
                  Co = The all India average wholesale price index for cement for the quarter
                           preceding the date of opening of bids as published by Ministry of
                           Industrial Government of India, New Delhi.
          Ci = The all India average wholesale price index for cement for the quarter under
                   consideration published by Ministry of Industrial Government of India,
                   New Delhi.
          Pc = Percentage of cement component of the work.
Adjustment for steel components:
(ii)      Price adjustment for increase or decrease in the cost of steel procured by the
          Contractor shall be paid in accordance with the following formula:-
          Vs = 0.85 X Ps/ 100 X R X (Si-So) / So
          Vs = Increase or decrease in the cost of work during the quarter under
                   consideration due to changes in rates for steel.
          So = The all India average wholesale price index for steel (Bar & Rods) for the
                   quarter proceeding the date of opening of bids as published by Ministry of
                   Industrial Development Government of India, New Delhi.
          Si = The all India average wholesale price index for steel (Bar & Rods) for the
                   quarter under consideration as published by Ministry of Industrial
                   Development Government of India, New Delhi.
          Ps = Percentage of steel component of the work.
Note: For the application of this clause, index (Bar & Rods) has been chosen to
      represent steel groups.
Adjustment of POL (Fuel & lubricants) Components.
(iii)     Price adjustment for increase or decrease in the cost of POL (Fuel & Lubricants)
          shall be paid in accordance with the following formula:
          Vf = 0.85 X Pf/ 100 X R X (Fi-Fo) / Fo
          Vf = Increase or decrease in the cost of work during the quarter under
                   consideration due to changes in rates for fuel & lubricants.
          Fo = The average official retails price of high speed diesel (HSD) at the existing
                   consumer pump of IOC on the days prior to the date of opening of bids.
          Fi = The average official retails price of high speed diesel (HSD) at the existing
                                                          th
                   consumer pump of IOC on the 15              day of the middle calendar month of
                   the quarter under consideration.
          Vm= Increase or decrease in the cost of work during the quarter under consideration
                   due to charges in the rates for local material other than cement, steel, bitumen and
                   POL.
          Mo=      The all India average wholesale price index (all commodities) for the quarter
                   preceding the date of opening of Bids as published by the Ministry of Industrial
                   Development, Government of India, New Delhi.
          Mi=      The all India average wholesale price index (all commodities) for the quarter
                   under consideration as published by the Ministry of Industrial Development, New
                   Delhi.
                 Pm= Percentage of local material component (other than cement, steel, bitumen and
                          POL) of all the work.
                          Percentage of various items of particular work shall be decided by the authority
                          Competent to sanction the estimate in       consultation with engineer-in-charge
                          before calling of tenders and these will be filled in against item as under:-
                          CementPc                                ……………….
                          SteelPs                                 ……………….
                          LabourPl                                ……………….
                          Bitumen Pb                              ……………….
                          POL Pf                                  ……………….
                          Plant & Machinery spares Pp             ……………….
                          localMaterial Pm                        ……………….
                          Total                                   100%
26.    Mobilization Advance, Machinery Advance and Secured Advance                        [Cl 48 of COC]
       Advances:
 Sr.    Name of Advance     Amount (in Rs.)            Conditions to be fulfilled
 No.
 1.  Mobilization         5% of the contract On submission of un conditional Bank
                          price               Guarantee (to be drawn before end of 20%
                                              of contract period).
 2.  Secured advance for 75% of       Invoice a) The material are in accordance with the
     non-perishable       value or market        specification for works.
     materials brought to value-lower of the b) Such material have been delivered to
     site.                two.                      site and are properly stored and
                                                  protected against damage               to
                                                  satisfaction of the Engineer. The
                                                contractor shall store the bulk material
                                                  in measurable stacks.
                                                  c) The Contractor’s records of the
                                                     requirements, orders, receipts and use
                                                       of materials are kept in and such
                                                        records shall be available for
                                                   inspection by the Engineer.
                                              d) The Contactor has submitted with his
                                                     monthly statement the estimated value
                                                       of the materials on site with such
                                                     documents as may be for purpose for
(The advance payment will be paid to the Contractor no later than 28 days after fulfillment of the above
conditions)
27.       Repayment of advance payment for mobilization and equipment:                                      [Cl 48 of
COC]
          The advance loan shall be repaid with percentage deductions from the interim payments
          certified by the Engineer under the Contract. Deductions shall commence in the next
          Interim Payment Certificate following that in which the total of all such payments to the
          Contractor has reached not less than 20 per cent of the contract or 6 (Six) months from the
          date of payment of first installment on advance, whichever period concludes earlier, shall
          be made at such rate from all Interim Payment Certificate that the loan and interest thereon
          shall be completely repaid prior to the expiry of the original time for completion.
29.       Repayment of secured advance:                                                        [Cl 49 of COC]
          The advance shall be repaid from each succeeding monthly payments to the extent
          material for which advance was previously paid have been incorporated into the works.
SEALED with the Common Seal of the said Bank this…………………..…..day of…………..20….
                (e)      where it is discovered at any stage before and even during the currency of
                         work, if allotted to the Contractor, that he has made misleading or false
                         statements in order to get the work allotted.
We undertake to pay to the Engineer the above amount upon receipt of his first written demand,
without the Engineer having to substantiate his demand, and without cavil or argument, without his
needing to prove or to show grounds or reasons for his demand for the sum specified.
We hereby waive the necessity of the Engineer demanding the said debt from the Contractor
before presenting us with the demand, provided that the Engineer will note that the amount
claimed by him is due to the occurrence of any one or more conditions, specified above.
This Guarantee will remain in force upto and including the date………………(B) days after the
deadline for submission of Bids as such deadline is stated in the instructions or as it may be
extended by the Engineer, notice of which extension(s) to the Bank is hereby waived. Any
demand in respect of this Guarantee should reach the Bank not later than the above date.
(A)   The Bidder should insert the amount of the guarantee in words and figures
      denominated in Indian Rupees. This figure should be the same as shown in Column 4
      of the table shown in the detailed notice inviting tenders.
(B)   …….Days after the end of validity period of the Bid. No.of Days/Date should be inserted
      by the Engineer, before issue.
         And whereas it has been stipulated by you in the said Contract that the Contractor shall furnish
         you with a Bank Guarantee by a recognised scheduled bank for the sum specified therein as
         security for compliance with his obligations in accordance with the Contract;
         And whereas we have agreed to give the Contractor such a Bank Guarantee;
         Now, therefore, we hereby affirm that we are the Guarantor and responsible to you, on behalf of the
         Contractor, up to a total of Rs.….........................……………. [amount of Guarantee] Rupees
         …………………………………………………. [in words] (1), such sum being payable, and we
         undertake to pay you, upon your first written demand and without cavil or argument, any sum or sums
         within the limits of Rs..………………… [amount of guarantee] (1) as aforesaid without your needing to
         prove or to show grounds or reasons for your demand for the sum specified therein.
         We hereby waive the necessity of your demanding the said debt from the Contractor before
         presenting us with the demand.
         We further agree that no change or addition to or other modification of the terms of the Contract
         of the Works to be performed there under or of any of the Contract documents which may be
         made between you and the Contractor shall in any way release us from any liability under this
         guarantee, and we hereby waive notice of any such change, addition or Modifications.
         This guarantee shall be valid until the date of issue of the Defects Correction Certificate.
Contract Price…………………………………………….