Tennessee Water Wastewater Utility
Partnership
Aeration Efficiency
and Optimization
Lee E. Ferrell, P.E., BCEE, CEM,
LEED Green Assoc.
Make the most of
SM
your energy
Aeration in Water Wastewater
2
WWW Challenges: Drivers/Trends
●Demand for WWW ●Reduced financial resources
●Age of infrastructure ●Energy efficiency awareness
●Legislative compliance ●Energy use
Typical wastewater process
0.5% 0.3% 0.1% energy usage breakdown
1.4% Aeration
3.2% Collection
3.9%
Anaerobic Digestion
8.1%
Lighting and Buildings
Belt Press
14.2% 54.1%
Clarifiers
Grit
14.3%
RAS
Chlorination
Pumping = 87% Gravity Thickening
Process = 91.9%
3
Water
energy use
71% of consumed electricity is used to
turn motors
65% of this energy is used for fluid
applications
Wastewater
energy use
Aeration System Overview and
Fundamentals
5
Overview
● The blower system:
Components End-use
– Blower – Water treatment
– Motors, engines – Wastewater treatment
– Piping – Water distribution
– Valves and fittings – Power generation
– Controls and – Irrigation
instruments
– Heat exchangers
– Tanks
– Others
6
Overview, continued
Electric utility System Approach
feeder ● Component optimization involves
segregating components and analyzing in
Transformer isolation
● System optimization involves studying
how the group functions as one as well as
Motor
breaker/starter how changing one component can help
the efficiency of another
Adjustable
speed drive
(electrical)
Served
Motor Coupling Blower Air System
Process(es)
7
Dresser Roots Wastewater Aeration Controls
Control Systems for Total Value
Dissolved Oxygen (DO) Control to Minimize Air Flow
Blower Control to Optimize Efficiency
Direct Flow Control and Most Open Valve Control
to Minimize Pressure
Blower Protection to Maintain Your Investment
8
DO Control Fundamentals
It’s all about the bubbles!
9
Aeration Energy
● Mechanical Aerators
● VFD Reduces Energy
● Challenge:
● Limit due to suspension
of solids
● Install submersed mixers
● Low Aerator speed
saves energy
● Mixer energy may be
less than savings
● Not needed at high
aeration
10
Jet or Diffused
Air
● Energy reduction via:
● Basin/Zone air control
● Blower control
● Challenge
● Air used to mix water
● Blower efficiency only as
good as air distribution
11
DO Control Fundamentals
Air is supplied to aeration basins in suspended growth diffused
air processes to provided oxygen needed to maintain biological
activity in the aeration basins.
Oxygen required is basically proportional to organic loading –
both BOD5 reduction and Nitrification
Air also provides mixing to keep the bacteria suspended and
aids in flocculation
12
DO Control Fundamentals
Aeration Control System Objectives:
Satisfy the Oxygen Demand of the Treatment Process
Achieve Process Requirements at the lowest
possible cost
13
DO Control Fundamentals
DO (Dissolved Oxygen) concentration is an indirect
indicator of proper air flow to the process
“Normal” DO concentration means the process is not
oxygen limited
If you have very low or zero DO you cannot have adequate
process performance
You can have high DO and not have adequate process
performance
Most operators set DO concentration too high
Typical 2.0 BOD – can be as low as 1.0
Typical 3.0 Nitrification – can be as low as 1.0
If BNR use as low as possible to avoid “oxygen poisoning
14
DO Control Fundamentals
Low DO can cause undesirable organisms to develop
High DO can cause poor settling, undesirable organisms to
develop
Excess DO does always not result in more biological
activity
Bugs don’t work twice as hard at 4.0 ppm DO than they do
at 2.0 ppm DO
High DO just wastes power
15
DO Control Fundamentals
16
DO Control Fundamentals
● O2 for BOD5 Reduction:
LbO 2
Re quire dO2_f or_B OD = 1.1
Lb B OD
● O2 for Nitrification (NH3 to NO3):
LbO 2
Requ iredO2 _fo r_ Nitrifi ca tio n= 4.6
Lb NH
3
In BNR systems denitrification typically recovers 25% of O2 used for
nitrification
17
DO Control Fundamentals
Total Air Flow Required:
0.335 mgd
S C FM = ppmBO Dremoved 1.1 ppmNH 3converted 4.6
O TE
● mgd = Wastewater flow rate, million gallons per day
● SCFM = Air Flow Rate, Standard Cubic Feet per Minute (68°F, 14.7 psia, 36% RH)
● OTE = Actual Oxygen Transfer Efficiency, Site Conditions
OTE is not a constant!
18
DO Control Fundamentals
Oxygen Demand Varies in Time from Diurnal
Variations
Typical Diurnal Flow Variation
140
120
Flow, % ADF
100
80
60
40
20
0
12:00 AM 08:00 AM 04:00 PM 12:00 AM
04:00 AM 12:00 PM 08:00 PM
Tim e o f Da y
Ratio of Peak to Minimum Flow is Typically 2:1
19
OTE and DO Control
When load increases at a constant air flow DO
concentration drops
Concentration does not drop to zero because OTE
changes and may compensate for increased loading
OTE is NOT a constant!
20
OTE and DO Control
OTE Varies with Air Flow per Diffuser
OTE Variation with Flow
DO ppm
0.50 1.00 1.50 2.00 2.50 3.00 3.50
14.0%
12.0%
Oxygen Transfer
Efficiency (OTE)
10.0%
8.0%
6.0%
4.0%
0.00 1.00 2.00 3.00 4.00 5.00
SCFM per Diffuser
21
OTE and DO Control
OTE Varies with DO Concentration:
OTE Variation with DO
SCFM per Diffuser
1.00 2.00 3.00 4.00
14.0%
Oxygen Transfer
Efficiency (OTE)
12.0%
10.0%
8.0%
6.0%
4.0%
0.00 1.00 2.00 3.00 4.00
DO Concentration, ppm
22
OTE and DO Control
At steady state the Oxygen Transfer Rate (OTR)
demanded by the process is equal to the OTR provided
by the aeration system. When this is not true, the
process is not steady state and the DO concentration
changes until a new equilibrium is established at new
steady state conditions.
OTE SCFM air %O2 OTR OUR TankVolume
23
OTE and DO Control
Response of DO to 20% Load Increase
Starting at 3.0 ppm DO
Oxygen Transfer Rate Variation with Air Flow
Response to 20% Organic Load Incre ase
6.00
1.0 2.0 3.0 4.0 5.0 SCFM/diffuser
5.00
4.00
1 3
DO, ppm
3.00
2.00
2
1.00
0.00
20.0 40.0 60.0 80.0 100.0 120.0
Oxygen Transfer Rate (OTR), kg/hr
1) Initial operation at 50 kg/hr OTR, 2 SCFM per diffuser, 3.0 ppm DO
2) 20% load increase to 60 kg/hr OTR, 2 SCFM per diffuser, DO drops to 1.3 ppm
3) Operation at 60 kg/hr OTR, air flow increases to 2.5 SCFM per diffuser,
restore 3.0 ppm DO
25% flow change required to
correct 20% load change!
24
DO Control
DO Control Operation:
Establish Targets (Setpoints)
Response to Deviations from Targets:
If DO > Setpoint reduce oxygen supply
If DO < Setpoint increase oxygen supply
Control basin and blower air flow
25
DO Control
● Automatic DO Control will save 25%
to 40% of Aeration System Energy
Compared to Manual Control
26
DO Control
Savings Proportional to Driving Force of O2
Increased System Complexity Must Be Justified by
Increased Savings
Group Basin DO Control
Individual Basin DO and Air Flow Control with Most-Open-Valve
(MOV)
Individual Zone DO and Flow Control for Each Basin
27
Basic Control System
28
Blower Control Concepts
Once the Optimum Aeration System Air Flow Has Been
Determined It Is Necessary to Provide the Correct Flow
From the Blowers
The Purpose of Blower Control is to Provide the
Correct Air Flow
Process Requires Controlled Mass Flow Rate
Control Technique Varies With Type of Blower
29
Blower Control Concepts
Positive Displacement (PD)
Constant flow at constant speed
Pressure varies with system requirements
Use VFDs (Variable Frequency Drives) to modulate air flow
Power consumption directly proportional to flow and pressure
30
Blower Control Concepts
57
BHP @ Constatnt Pressure
52
47
42
37 Performance
32 Design
27
22
17
12
1000 2000 3000 4000 5000
BLOWER SPEED (RPM)
1212
1012
812
ICFM
Performance
612
Design
412
212
12
1000 2000 3000 4000 5000
BLOWER SPEED (RPM)
31
Blower Control Concepts
Multistage Centrifugal
Variable flow at Approximately Constant Pressure
Usually controlled by inlet throttling to modulate flow
VFDs to modulate air flow will improve efficiency and
turndown (with appropriate curves)
32
Blower Control Concepts
110
AVERAGE TEMP 61 F NO CONTROL
INLET THROTTLED HIGH TEMP 100 F
100
AVERAGE TEMP
90 NO CONTROL
% POWER
80
70
60
AVERAGE TEMP
REDUCED SPEED 57.3 Hz
50
40
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
120
AVERAGE TEMP AVERAGE TEMP 61 F
INLET THROTTLED NO CONTROL
110
100
% GAUGE PRESSURE
AVERAGE TEMP
REDUCED SPEED 57.3 Hz
90
80
SYSTEM CURVE
70
NO CONTROL
HIGH TEMP 100 F
60
50
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
33
Blower Control Concepts
Single Stage Centrifugal
Variable flow
Pressure varies with load
High efficiency
Most common > 500 hp
Inlet Guide Vanes and/or Variable Discharge Diffusers to
modulate flow and improve turndown
34
Blower Control Concepts - IGV
110
MAX IGV OPENING
100
90
% POWER
80
REDUCED IGV OPENING
70
60
50
40
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
120
MAX IGV OPENING
110
REDUCED IGV OPENING
100
% GAUGE PRESSURE
FRICTION LOSSES
90
80
STATIC PRESSURE
70
60
50
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
35
Blower Control Concepts – Variable
DDV 110
MAX DDV OPENING
100
90
% POWER
80
70
MIN DDV OPENING
60
50
40
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
120
MIN DDV OPENING MAX DDV OPENING
110
100
% GAUGE PRESSURE
FRICTION LOSSES
90
80
STATIC PRESSURE
70
60
50
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
36
Blower Control Concepts
Dual Vane Operation Maintains Efficie ncy
120
MAX IGV and DDV OPENING
110
BEP
X
% GAUGE PRESSURE
100
90
80
70
60
MIN IGV at MAX DDV OPENING
MIN IGV and DDV POSITION
50
0 10 20 30 40 50 60 70 80 90 100 110
% MASS FLOW RATE
37
Blower Control Concepts
Evaluate Total Blower Performance
Equipment Cost
Installation Cost
Maintenance Cost
ENERGY COST
38
Blower Energy Evaluation
Use realistic inlet conditions
Average temperature and pressure
Include inlet losses
Use expected range of operating air flow
The Blower With the Highest Design Point Efficiency May Not
Provide Lowest Power Consumption
Include control system characteristics in evaluation
Determine if energy payback justifies higher initial investment
39
Manual Diffused Air Control Scheme
● Advantages
● Economical Construction
Aeration Aeration
● Disadvantages
DO DO
● Energy Intensive
● Efficiency = Continual adjustment
Basin Basin
● Solution
● Motor Starters/RVSS
[
Blower
Aeration
[
DO Blower
Basin
[
Blower
40
Average Diffused Air Control Scheme
● Average Basin DO controls blowers
Aeration Aeration
● Advantages
● Less operator intensive than manual DO DO
● Economical construction compared Basin Basin
to automatic distribution
● Disadvantages
● Rough control = Energy Intensive
● “Goldilocks effect”
M
[
● Solution Blower
Aeration
● Motor Starters/RVSS M
[
● PLC for blower control DO Blower
Basin M
[
Blower
41
Basin Control Schemes
● Each Basin Controls DO
● Flow to each basin measured
● Blowers adjusted to meet total Aeration Aeration
demand
DO DO
● Advantages Basin Basin
● More accurate control
) ( ) (
● Manual observation eliminated
M
● Disadvantages
M
● Inter-basin DO variation ) ( M
[
Blower
Aeration
● Solution M
[
● Motor Starters / RVSS Blower
DO
● PLC for Basin and Blower Control Basin M
[
Blower
42
Multi Zone Control Scheme
● Each zone controls its DO
M M
) (
) (
DO DO
● Advantages Aeration Aeration
● Greatest energy savings M M
) (
) (
● No/Low operator intervention DO DO
● Minimize inter-basin DO Basin Basin
M M
variation
) (
) (
DO DO
● Disadvantages
● Most expensive to construct
● Energy Savings / Process
Stability Tradeoff M
M
[
) (
DO Blower
● Solution Aeration
M
● Motor starters/RVSS M
[
) (
● PLC DO Blower
●Basin valve control Basin M
M
[
●Blower inlet valve control DO ) ( Blower
43
● Inlet Throttling
● Traditional method
● Inlet Valve controls air volume
● Fixed speed
●Fixed curve
●Surge is at fixed
power/amperage
● Surge done through:
●Current meter
●Power meter
44
VFD Based Blower Control
● Better energy savings then inlet throttling valve
● But with limits
● Must design differently
45
P.D.
Blowers
under
different
rules
46
Inlet Throttling
● Curve sized for 60 Hertz VFD
● Throttled to meet
demand
● Surge Control via power
or current meters ●Curve sized for 80%
operating time
●Full Speed
● ~ 10% of the time
● Accept Power &
Pressure rise
●Surge control
algorithm with flow 47
Blower Energy Evaluation
Typical Diurnal Flow Air Estimated Air
Variation
150%
% of Average
100%
50%
0%
12:00 AM 04:00 AM 08:00 AM 12:00 PM 04:00 PM 08:00 PM 12:00 AM
Time of Day
48
Flow Control Basics
DO concentration depends on air flow, NOT on
Pressure
Blowers create air flow, not pressure
The system creates pressure through resistance to air
flow
49
Flow Control Basics
What is operating point?
50
Flow Control Basics
The System Curve identifies the relationship between flow
and back pressure (resistance to flow)
51
Flow Control Basics
Combining the System Curve and the Blower Curve
defines the actual operating air flow
52
Pressure Control Basics
DO is not a function of system pressure. DO control
requires control of air flow only.
Blower control means modulating air flow rates.
Pressure control is designed to minimize interference
between basins and to coordinate blower output and
basin air flow demand.
Use of direct flow control and MOV logic to reduce
pressure and power
53
Pressure Control
Excess Pressure Simply Wastes Power
54
Pressure Control
Pressure control has a number of problems:
Problems with Pressure Control:
Instability
Basin and blower control loops “fight” each other
Difficulties operating at extremes of blower capacity
Interactions with multiple basins
Tuning difficulties and re-tuning requirements
Inherent PID tuning complications
One blower vs. two blowers running
Night vs. day operation
Wasted power – 10% or more
55
Direct Flow Control
56
Direct Flow Control
Basin Air Flow Control Saves Power Because “Identical”
Basins Don’t Perform Identically
Variations Due to Influent Channels
Variations Due to RAS
Variations Due to Air Piping and Manual Valve Adjustments
Direct Flow Control Approach
Summation of basin flow requirements = total blower flow
Δ flow, not absolute setpoint
Modulate blowers into safe operating range
57
Direct Flow Control
Eliminates need for pressure control to save power and energy
cost
Totalize changes in air flow for tanks and modulate blowers air
flow accordingly
Integrate air flow control at BOTH ends of air piping
58
Most-Open-Valve Control Concepts
Excess blower discharge pressure wastes power
Operators tend to set pressure setpoint too high –
often 1 to 1.5 psig above requirement
Optimum energy use is achieved when the pressure in the
header is just enough to overcome static pressure plus friction
loss through the worst case diffuser
header
Most-Open-Valve Control is a technique for power minimization,
not a blower control or DO control technique
59
Most-Open-Valve Control Concepts
Impact of excess pressure on blower power:
PD blowers: very significant
Inlet throttled multi-stage centrifugals: minor
Inlet guide vane controlled single-stage or multi-stage
centrifugals: significant
VFD controlled multi-stage centrifugals: very significant
60
Most-Open-Valve Control Concepts
Most-Open-Valve (MOV) implies that one basin air flow control
valve is at maximum position to minimize system pressure
MOV logic is independent of blower control logic
Older style pressure control based systems typically use a
changing pressure setpoint based on valve positions
61
Energy Efficiency in Pumps and Blowers
• Load Characteristics
Water Wastewater Load Characteristics
Variable Constant Constant
Torque Torque Power
Typical Centrifugal Pumps Positive No applications
and Blowers Displacement
Applications Pumps, Blowers,
Mixers, and
Chemical Feed
Pumps
Energy Substantial Lowest Potential No Potential
Potential – Largest
Savings of all VFD
Potential applications
The Main
Target ( first The Next
priority) Step ( second
priority)
62
VFD Benefits with Blowers
63
VFD Benefits with Pumps
• Physical Laws for Centrifugal Loads
Its Pure Physics: Due to the laws that govern centrifugal pumps,
the flow of water decreases directly with pump speed
Affinity laws of centrifugal loads :
Flow = f (motor speed)
Pressure = f (motor speed)2
Power = f (motor speed)3
64
VFD Benefits with Pumps
• Physical Laws for Centrifugal Loads
A motor running at 80% of full speed requires 51% of
the electricity of a motor running at full speed.
65
VFD Benefits with Pumps
• Physical Laws for Centrifugal Loads
A motor running at 50% of full speed requires 12.5% of
the electricity of a motor running at full speed.
66
Aeration Efficiency and Optimization
67
Efficiency of Blower Systems
• Equations for efficiency
Blower Energy Usa ge Blower Efficiency Measuremen t
0.011503 * (Q * pi * X ) kW kW
kW MGD Q
( Motor * Blower * Drive )
(Q * pi * X )
Q Blower inlet volu metric flowrate, ICFM Motor * Blower * Drive
(0.011503 * k W)
pi Blower inlet pressure, psia
η efficiency (Q * pi * X )
Wire to air
X Blower adiabatic factor (0.011503 * k W)
0.283
pd
X 1
pi
pd Blower discharge pressure, psia
pi Blower inlet pressure, psia
68
Blower Energy Optimization is Complex
• Simple Guidelines for reducing
energy usage
Match blower airflow to the process
requirements
Minimize system discharge pressure and
inlet losses
Provide flexibility and adequate turndown
for loading variations
69
VFD Benefits with Blowers
• Other Benefits
In addition to Energy Saving, using a VFD has many other
advantages:
• Less mechanical stress on motor and system
• Less mechanical devices - Less Maintenance
• Process regulation with PID regulators, load management
functions
• Reduce noise, resonance avoidance
• Performance and flexibility, range settings, above base
operations
• Easier installation and settings, drive mechanics
• Can be controlled with Automation, Communication networks
70
Process Energy Optimization
Automation is the Key
• Develop consistent and
appropriate milestone and
deliverable expectations
• Standardize program schedule
tracking requirements
• Establish key energy
management performance
metrics
• Produce meaningful reports
that allow for clear and concise
decision-making
• Install additional monitoring
equipment as needed
71
Benchmarking and Key
Performance Indicators
72
Possible Benchmarking KPIs
• kWh/MG
• kWh/OTR
• kWh/lb BOD Removed
• kWh/TSS Removed
73
Thank you for your time
Lee E Ferrell, P.E., BCEE
Schneider Electric Water Wastewater Competency Center
864-784-1002
lee.ferrell@us.schneider-electric.com
http://www.schneider-electric.us/solutions/water-wastewater/
74
Appendix
75