B8 HVAC Schedule (25!4!18)

This document outlines the proposed project schedule for mechanical works on the Infineon B8 L1 Upgrading Works project from April 2018 to June 2018. It involves dismantling and relocating existing air conditioning equipment, installing new ducting and piping, and carrying out electrical and control works. The schedule is divided into four main items - air conditioning installation, mechanical works, electrical and control works, and other works such as air balancing, technical cleaning and testing & commissioning. The project aims to complete the upgrading works within the three month timeframe outlined in the schedule.

Uploaded by

lam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
211 views1 page

B8 HVAC Schedule (25!4!18)

This document outlines the proposed project schedule for mechanical works on the Infineon B8 L1 Upgrading Works project from April 2018 to June 2018. It involves dismantling and relocating existing air conditioning equipment, installing new ducting and piping, and carrying out electrical and control works. The schedule is divided into four main items - air conditioning installation, mechanical works, electrical and control works, and other works such as air balancing, technical cleaning and testing & commissioning. The project aims to complete the upgrading works within the three month timeframe outlined in the schedule.

Uploaded by

lam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 1

Project Owner : Infineon Technologies (Malaysia) Sdn Bhd Prepare By : KOOLHABA ENERGY SDN BHD

Propose Project Schedule (Mechanical)


Project Title : Infineon B8 L1 UPGRADING WORKS Issue Date : 19 APRIL '18 Revision : 0

Project APRIL' 2018 MAY ' 2018 JUNE ' 2018


Item Job Scope Duration, Week
Start End 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
F Airconditioning Installation.
1 General Condition And Preliminary
1.1 Preliminary 14 Days 17-Apr 30-Apr

1.2 Long Lead Equipment Arrival 49 Days 10-Apr 29-Apr

2 Mechanical Works
QFC CLEAN ROOM
2.1 Dismantle of Existing ACSU (2 Nos) 2 Days 8-May 11-May

2.2 Relocation of ACSU to New LAN Room (2 Nos) 4 Days 9-May 13-May

2.3 Dismantle of Existing Ducting and FCU (3 Nos) 4 Days 26-Apr 29-Apr

2.4 Ducting Installation Works at Logistic 13 Days 23-Apr 6-May

2.5 FCU Relocation Work In QFC (2 Nos) 3 Days 30-Apr 2-May

2.6 Installs Chilled Water Pipe Works for FCU (2 Nos) 4 Days 3-May 6-May

2.7 AHU & MAU Installation Works 6 Days 30-May 4-Jun

2.8 Chilled Water Pipe Works 3 Days 4-Jun 6-Jun

2.9 Installation of Supply Air Grille 4 Days 1-Jun 4-Jun

NEW SURAU, MOTHER'S ROOM & TOILET


2.1O Dismantle of Existing CWCC (4 Nos) 4 Days 27-May 30-May

2.11 Relocation of Existing CWCC (4 Nos) 4 Days 31-May 3-Jun

LOCKER ROOM
2.12 Ducting & Piping Works in Locker Room 5 Days 24-May 28-May

2.13 Relocation of FCU in Locker Room (1 Nos) 4 Days 29-May 1-Jun

2.14 Exhaust Fan Installation Works 2 Days 2-Jun 3-Jun

3 Electical & Control Works


3.1 Dismantle of Existing ACSU Wiring Works 4 Days 8-May 13-May

3.2 ACSU Wiring Works 4 Days 8-May 13-May

3.3 Dismantle of Existing FCU Wiring Works 3 Days 30-Apr 2-Apr

3.4 Sensor & Transmitter Wiring Works 8 Days 29-May 6-Jun

3.5 FCU, ACSU & CWCC Wiring Works 8 Days 29-May 6-Jun
3.6 AHU, MAU & Heater Wring Works 3 Days 30-May 1-Jun
3.7 Control Panel Installation and Wiring Works 4 Days 2-Jun 5-Jun

3.8 Test and Commissioning 2 Days 6-Jun 7-Jun

4 Others
4.1 Air Balancing and Tuning Works 2 Days 6-Jun 7-Jun

4.2 Cleanroom Technical Cleaning works 2 Days 8-Jun 9-Jun

4.3 Cleanroom T&C 1 Day 10-Jun 10-Jun