0% found this document useful (0 votes)
162 views1 page

Daily Progress Report HSE: Date 17/9/18 Equipments Used

1. A daily progress report from 17/9/18 summarizes work including the installation of water tanks, excavation works using backhoes and trucks, concrete works, barricade installation, and material shifting. 2. The report notes 9 workers including operators, helpers, and engineers, as well as protective equipment issues and permits raised. 3. Observations include materials stacked near excavation sites which could lead to cave-ins, and safety talks were conducted on manual excavation.

Uploaded by

jithin shankar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
162 views1 page

Daily Progress Report HSE: Date 17/9/18 Equipments Used

1. A daily progress report from 17/9/18 summarizes work including the installation of water tanks, excavation works using backhoes and trucks, concrete works, barricade installation, and material shifting. 2. The report notes 9 workers including operators, helpers, and engineers, as well as protective equipment issues and permits raised. 3. Observations include materials stacked near excavation sites which could lead to cave-ins, and safety talks were conducted on manual excavation.

Uploaded by

jithin shankar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Progress Report HSE

DATE 17/9/18

SL NO PROCESS EQUIPMENTS USED

1 installation of water tank ,condensded water tank Back hoe


1 excavation work-mannul & mechanical
2 shifitng of spoils , concrete works
Trucks /Transit mixer
3 hard barrication works & sign board fixing
4 shiftng of materials ,& survey works
2 MANPOWER OBSERVATIONS
subcontractor OIL PIPES
THANASING CHAUHAN It is observe that some of
labour -2 survior-1 helpers HSE PERSON the materials are stack near
2 0 to excavation this may
1 leads to cavin
operator -2 engineer-1 supervisor
1
total - 9 no
3 MEIL Employees CONTROL MEASURES
Remove all the from the
Civil HR Person HSE edge of excavtion
engineers-1 -1 PERSONS
1 2
DRIVER-1
ADMIN-1 DYM-1
2 PERSONEL PROTECTIVE EQUIPMENTS ISSUED NA
3 PERMIT RAISED -SPARK,CONFINED SPACE,VECHICLE ENTRY PERMIT

TODAY INDUCTION TBT MANNUL EXCAVTION


STATUS 0 CONDUCTED YES TOPIC
Prepared By
jithin shankar hse manager

You might also like