Mariveles Chlorinator

This document is a bill of materials for the VWSSI water supply system project in Mariveles, Bataan. It lists 34 items needed including concrete, masonry materials, roofing, doors, plumbing supplies, and painting materials. The projected material cost is 33,664.72 pesos, labor cost is 18,650 pesos, and total projected construction cost is 52,314.72 pesos.

Uploaded by

Jhn Cbllr Bqng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views1 page

Mariveles Chlorinator

This document is a bill of materials for the VWSSI water supply system project in Mariveles, Bataan. It lists 34 items needed including concrete, masonry materials, roofing, doors, plumbing supplies, and painting materials. The projected material cost is 33,664.72 pesos, labor cost is 18,650 pesos, and total projected construction cost is 52,314.72 pesos.

Uploaded by

Jhn Cbllr Bqng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

VILLAGES WATER SUPPLY SYSTEM, INC.

Bill of Materials

Project : VWSSI - FCI - MARIVELES


Location : Block 07, Lot 13-15, Fiesta Communities Mariveles, Brgy. Balob,Mariveles, Bataan
Subject : VWSSI Discharge Line Slab w/ Chlorinator House / by-pass box
ChlorinatorHouse and Collector's Box
Date :

No. Description Quantity Unit Cost Amount


2 CONCRETE WORKS - Wall Footing (Foundation) V= 1.31 cu. mtrs
Cement - Portland, 40 kg/bag 9.86 bags 215.00 2,118.83
Sand, Coarse 0.92 cu. mtr 160.00 147.17
Gravel, Washed 3/4" - Ø 1.05 cu. mtrs 680.00 714.82
DSB, 10 mm-Ø x 6.00m 15.00 pcs 129.16 1,937.40
DSB, 8 mm-Ø x 6.00m 10.00 pcs 104.65 1,046.50
GI Tie Wire #16 1 1.58 kgs 60.00 95.04
3 CONCRETE WORKS - Slab (Chlorinator House, Discharge, Bypass) V= 1.12 cu. mtrs
Cement - Portland, 40 kg/bag 8.40 bags 215.00 1,806.00
Sand, Coarse 0.78 cu. mtr 160.00 125.44
Gravel, Washed 3/4" - Ø 0.90 cu. mtr 680.00 609.28
DSB, 10 mm-Ø x 6.00m 2.00 pcs 129.16 258.32
Welding Rod, 1/8" - Ø 1 0.59 kg 75.00 44.10
GI Tie Wire #16 1 0.39 kg 60.00 23.52
4 CONCRETE WORKS - Beams (LB,BB) V= 0.02 cu. mtrs
Cement - Portland, 40 kg/bag 0.18 bags 215.00 38.70
Sand, Coarse 0.02 cu. mtrs 160.00 2.69
Gravel, Washed 3/4" - Ø 0.02 cu. mtrs 680.00 13.06
DSB, 10 mm-Ø x 6.00m 2.00 pcs 129.16 258.32
Welding Rod, 1/8" - Ø 1 0.22 kgs 75.00 16.65
5 MASONRY - CHB Wall A= 25.83 sq. mtrs
CHB, 4" x 8" x 16" Ordinary 25.83 340.00 pcs 8.00 2,720.00
Cement - Portland, 40 kg/bag 8.07 bags 215.00 1,735.45
Sand, Coarse 1.39 cu. mtrs 160.00 222.76
Gravel, Washed 3/8" - Ø 0.77 cu. mtrs 680.00 526.93
DSB, 10 mm-Ø x 6.00m 19.00 pcs 129.16 2,454.04
GI Tie Wire #16 0 2.00 kgs 60.00 120.00
6 MASONRY - Plastering A= 87.66 sq. mtrs
Cement - Portland, 40 kg/bag 21.04 bags 215.00 4,523.26
Sand, Fine 4.72 cu. mtrs 160.00 754.58
7 ROOFING
RIB TYPE Roof Sheet, (Eff. Width = 0.80m)
3.00 m 3.00 pcs. 345.00 1,035.00
8 ROOF FRAMING
C-Purlins, Ga.1.6 x 2" x 6" x 20' 1.00 pcs 900.00 900.00
Hat Type Battens x 3m 5.00 pcs 100.00 500.00
Fascia Board, 3/8" x 10" x 8' 4.00 pcs 170.00 680.00
Box Type Gutter 0.40 mm X 0.457m X 2.44m 1.00 pcs 400.00 400.00
End Wall Flashing 0.40 mm X 0.405m X 2.44m 3.00 pcs 400.00 1,200.00
Vulca Seal 1.00 ltrs 60.00 60.00
Tekscrew 50.00 pcs 2.00 100.00
Metal Screw 50.00 pcs 1.00 50.00
Blind Rivets, 7mm x 50mm 50.00 pcs 1.00 50.00
22 CARPENTRY WORKS - EAVES A= 3.40 sq. mtrs
SPANDREL 3.40 SQ.M. 580.00 1,972.00
18 DOORS
Aluminum Door 1.00 sets 3,000.00 3,000.00
9 PLUMBING WORKS - Sewer Line
PVC Pipe, 4"-Ø x 10', Orange 4.00 pcs 300.00 1,200.00
PVC Elbow, 4"-Ø x 90°, Orange 1.00 pcs 38.30 38.30
34 PAINTING WORKS
MAT FIN. Topcoat, (Common Wall) 14.00 ltrs 160.00 2,240.00
Patching Compound 0.20 sack 320.00 64.00
Concrete Neutralizer 1.00 ltrs 17.00 17.00
Sandpaper, #100 2.00 pcs 15.00 30.00
Sandpaper, #120 2.00 pcs 15.00 30.00
Thinner 0.50 ltrs 39.50 19.75
10 FORMWORKS/BATTER BOARD
Lumber : 2 " x 2 " x 12 ft 1.00 pcs 184.00 184.00
Lumber : 2 " x 3 " x 12 ft 1.00 pcs 276.00 276.00
Plywood, 1/2" x 4' x 8' 1.00 pcs 750.00 750.00
CWN, 3" 1.00 kgs 48.25 48.25
CWN, 2" 1.00 kgs 51.20 51.20

Projected Material Cost : 33,664.72


Projected Labor Cost : 18,650.00

Projected Construction Cost : 52,314.72