VILLAGES WATER SUPPLY SYSTEM, INC.
Bill of Materials
Project : VWSSI - FCI - MARIVELES
Location : Block 07, Lot 13-15, Fiesta Communities Mariveles, Brgy. Balob,Mariveles, Bataan
Subject : VWSSI Discharge Line Slab w/ Chlorinator House / by-pass box
ChlorinatorHouse and Collector's Box
Date :
No. Description Quantity Unit Cost Amount
2 CONCRETE WORKS - Wall Footing (Foundation) V= 1.31 cu. mtrs
Cement - Portland, 40 kg/bag 9.86 bags 215.00 2,118.83
Sand, Coarse 0.92 cu. mtr 160.00 147.17
Gravel, Washed 3/4" - Ø 1.05 cu. mtrs 680.00 714.82
DSB, 10 mm-Ø x 6.00m 15.00 pcs 129.16 1,937.40
DSB, 8 mm-Ø x 6.00m 10.00 pcs 104.65 1,046.50
GI Tie Wire #16 1 1.58 kgs 60.00 95.04
3 CONCRETE WORKS - Slab (Chlorinator House, Discharge, Bypass) V= 1.12 cu. mtrs
Cement - Portland, 40 kg/bag 8.40 bags 215.00 1,806.00
Sand, Coarse 0.78 cu. mtr 160.00 125.44
Gravel, Washed 3/4" - Ø 0.90 cu. mtr 680.00 609.28
DSB, 10 mm-Ø x 6.00m 2.00 pcs 129.16 258.32
Welding Rod, 1/8" - Ø 1 0.59 kg 75.00 44.10
GI Tie Wire #16 1 0.39 kg 60.00 23.52
4 CONCRETE WORKS - Beams (LB,BB) V= 0.02 cu. mtrs
Cement - Portland, 40 kg/bag 0.18 bags 215.00 38.70
Sand, Coarse 0.02 cu. mtrs 160.00 2.69
Gravel, Washed 3/4" - Ø 0.02 cu. mtrs 680.00 13.06
DSB, 10 mm-Ø x 6.00m 2.00 pcs 129.16 258.32
Welding Rod, 1/8" - Ø 1 0.22 kgs 75.00 16.65
5 MASONRY - CHB Wall A= 25.83 sq. mtrs
CHB, 4" x 8" x 16" Ordinary 25.83 340.00 pcs 8.00 2,720.00
Cement - Portland, 40 kg/bag 8.07 bags 215.00 1,735.45
Sand, Coarse 1.39 cu. mtrs 160.00 222.76
Gravel, Washed 3/8" - Ø 0.77 cu. mtrs 680.00 526.93
DSB, 10 mm-Ø x 6.00m 19.00 pcs 129.16 2,454.04
GI Tie Wire #16 0 2.00 kgs 60.00 120.00
6 MASONRY - Plastering A= 87.66 sq. mtrs
Cement - Portland, 40 kg/bag 21.04 bags 215.00 4,523.26
Sand, Fine 4.72 cu. mtrs 160.00 754.58
7 ROOFING
RIB TYPE Roof Sheet, (Eff. Width = 0.80m)
3.00 m 3.00 pcs. 345.00 1,035.00
8 ROOF FRAMING
C-Purlins, Ga.1.6 x 2" x 6" x 20' 1.00 pcs 900.00 900.00
Hat Type Battens x 3m 5.00 pcs 100.00 500.00
Fascia Board, 3/8" x 10" x 8' 4.00 pcs 170.00 680.00
Box Type Gutter 0.40 mm X 0.457m X 2.44m 1.00 pcs 400.00 400.00
End Wall Flashing 0.40 mm X 0.405m X 2.44m 3.00 pcs 400.00 1,200.00
Vulca Seal 1.00 ltrs 60.00 60.00
Tekscrew 50.00 pcs 2.00 100.00
Metal Screw 50.00 pcs 1.00 50.00
Blind Rivets, 7mm x 50mm 50.00 pcs 1.00 50.00
22 CARPENTRY WORKS - EAVES A= 3.40 sq. mtrs
SPANDREL 3.40 SQ.M. 580.00 1,972.00
18 DOORS
Aluminum Door 1.00 sets 3,000.00 3,000.00
9 PLUMBING WORKS - Sewer Line
PVC Pipe, 4"-Ø x 10', Orange 4.00 pcs 300.00 1,200.00
PVC Elbow, 4"-Ø x 90°, Orange 1.00 pcs 38.30 38.30
34 PAINTING WORKS
MAT FIN. Topcoat, (Common Wall) 14.00 ltrs 160.00 2,240.00
Patching Compound 0.20 sack 320.00 64.00
Concrete Neutralizer 1.00 ltrs 17.00 17.00
Sandpaper, #100 2.00 pcs 15.00 30.00
Sandpaper, #120 2.00 pcs 15.00 30.00
Thinner 0.50 ltrs 39.50 19.75
10 FORMWORKS/BATTER BOARD
Lumber : 2 " x 2 " x 12 ft 1.00 pcs 184.00 184.00
Lumber : 2 " x 3 " x 12 ft 1.00 pcs 276.00 276.00
Plywood, 1/2" x 4' x 8' 1.00 pcs 750.00 750.00
CWN, 3" 1.00 kgs 48.25 48.25
CWN, 2" 1.00 kgs 51.20 51.20
Projected Material Cost : 33,664.72
Projected Labor Cost : 18,650.00
Projected Construction Cost : 52,314.72
Printed : 11/12/2018 3:03 PM Page 1 of 1