Southern Luzon State University
College of Engineering
Lucban, Quezon
ME Laboratory 3
MCE23
VIDEO OUTLINE
9 KEY ELEMENTS OF COMMISSIONING
Submitted by:
May Grace D. Almirañez
BSME V-GO
Submitted to:
Engr. Ronelito San Jose
ME Department Faculty
September 18, 2018
9 Key Elements for Successful Plant Commissioning
1. Planning
Without proper planning, you will not be commissioned a plant safely and
in time.
2. Mechanical Completion
This is the time when the commissioning team takes over the system from
the construction team.
3. P&ID Checking
Commissioning Engineers were verify that everything in the field was built
according to specifications.
4. Pre commissioning
It includes cleaning of pipes, by blowing and flashing, mechanical cleaning
of vessels and tanks, no load test rants of modules, etc.
5. Commissioning
This step includes for example introduction to utilities, dry running trials,
safe fluid dynamic testing, solvent dynamic testing and process fluid test.
6. Start-Up
This means the entire plant will be taken slowly to full operation.
7. Initial Operation
This phase is necessary to prepare the performance test. During the initial
operation, the entire plant will be optimized.
8. Performance Testing
Now, we have to prove that the plant meets all specifications under
normal operating condition.
9. Post Commissioning
A reduced commissioning staff will take care and solved open punch
points. Don’t underestimate the time necessary for post commissioning
activities.
PLANNING
The first priority during commissioning is safety. To ensure the safe work
you have to think carefully about the complete commissioning process. A good tool for
risk assessment is HAZOP (Hazard Operability Analysis). The pre commissioning and
commissioning of safe plans will be carried out using system by system and unit and unit
basis. Therefore each unit is divided into process and or piping and equipment systems
or subs systems. These systems are generally defined by process boundaries and
incorporate all equipment we carried for particular service or operation part. On a Master
P&Id Set, we mark the different system with different color.
Completion, prioritization means you have to think about the right order for
commissioning systems. Which unit or system do I need when? For example, usually we
need all utility system like plant air, instrument air, steam, etc. at first in the long time of
any process system.
After you wrote down the completion and prioritization, you have to
communicate it to the construction team to let them know which system to finish and
when. You have to consider which software tool you will used to re caught your
commissioning progress and to capture your test results. It can be one using extra sheets
with some kind of databases like excels or a very specialized software tools like ICAPS
(Integrated Commissioning & Progress System). It manages preparation, execution,
monitoring of all pre commissioning and commissioning activities.
Different documents that needs to prepare before the commissioning team will be
on site.
Time Schedule
Organizational Chart
Checklists
Operating Manual
Pre-Commissioning Procedures
Commissioning Procedures
Safety Procedures
Quality Control Procedures
Security Procedures
Emergency Response Procedures
Status Progress Reporting
Test Records
Punchlist Template
We need to plan Manpower as well. That includes:
Pre-Commissioning Team
Commissioning Team
Operating Team
Maintenance Team
Client’s Team
Contractors
Vendors
Licensor
Support from Office
It is important to plan the material which will be needed during pre-commissioning and
commissioning in advance. It includes:
Blinds
Spool Pieces
Hoses
Additional Gaskets
Sample Bottles
It depends on the type of the plant you want to commission, which additional equipment
will be needed. Also, you should plan as well simple tools necessary.
MECHANICAL COMPLETION
Checking and testing of equipment and construction to confirm that the
installation is in accordance with drawings and specifications and ready for pre-
commissioning or commissioning in a safe manner and in compliance with project
requirements.
Typical tasks for mechanical completion are divided by disciplines:
Mechanical
Visual inspection for complete and correct installation.
Verification of name plate details at tanks, vessels, rotating equipment and
other machines.
Internal inspection of tanks and vessels
Hydrostatic test of vessels and tanks
Vendor representatives for large and/or complicated equipment
Piping
NDT done (nondestructive testing)
Pipe supports completed
Removal of all items subject to damage during flushing, cleaning and
pressure testing
Blowing
Flushing
Chemical cleaning
Drying
Preservation
Reinstatement
Bolt tensioning
Insulation*
Flow coding*
Structural
Inspection of all supporting machines
Electrical
Inspection
Cable trays
Cable tray supports
Cable tray fill
Cables
Bend radius
Wiring
Termination
Grounding
Megger Testing
Instrumentation
Inspection
Cable trays
Cable tray supports
Cable tray fill
Cables
Bend radius
Wiring
Termination
Grounding
Validation of instruments
Validation of valves
Loop checks
Flushing of tubing
Tightness test of tubing
P&ID CHECKING
Can be considered as system check for construction and engineering errors.
Commissioning Team or Commissioning Engineers are responsible for executing the
checks. The things that need to checked are:
Piping
Equipment
Instrumentation
Point of View
Safety Operations
Construction Maintenance
We can also perform additional tasks to assist subsequent commissioning & start-up
activities. Such additional tasks can be the following:
Temporary identification tags
Temporary signs for various lines, valves and equipment
Temporary signs for medium and flow direction
There are various documents you’ll need to perform for P&ID checks like:
Plans Standards
Drawings Hook Ups
Checklists Vendor Documents
Specifications
When you performed the P&ID Check, you will for sure find one or more deviations from
the P&ID or other specifications. In such case, you have to put this deviations into a punch
list. If you are unsure of the validity of any item, just contact the lead unit process engineer.
Any punch items which changes any feature of the P&ID must be screened by the
lead unit process engineer from a design and safety point of view before implementation.
The punch list must be transmitted to the following departments:
Construction
Engineering
QA/QC
As smooth start-up of any industrial plant depends to a large degree on the
thoroughness, the unit must be checked beforehand.
PRE-COMMISSIONING
The term Pre-Commissioning is used for activities after construction completion,
such as cleaning, catalyst loading, dry-runs and checks within the systems in order
to prepare these items/systems for the next step commissioning.
Pre-Commissioning activities can be done after or as well before mechanical
completion.
Since July 2013, Pre-Commissioning had been using API Recommended Practice
1FSC.
API Recommended Practice 1FSC
Group of energized and static tests that constitute verification that the equipment
or component is fabricated, installed, cleaned, and tested in accordance with the
design and ready for commissioning.
Also called “Static Commissioning”
Examples of Pre-Commissioning Activities:
Flushing, blowing and drying activities
Chemical cleaning
Final inspection and closing of vessels and tanks
Final reinstatement of systems or sub-systems
Air tightness “Leak” testing of systems
Lubricants application
Pre-Commissioning “Run-in” of major rotating equipment and electrical motors
Installation of filters
Packing of distillation columns
Loading of catalyst and molecular sieve beds
Refractory dry-out (if possible-mostly commissioning activity)
Vendor and factory acceptance testing
Instrument, electrical and motor loop testing
Punch listing(ongoing process)
Example of Pre-Commissioning (Petrochemical Plant)
1. Power and control system (electrical substations)
2. Building power, HVAC, fire & gas protection
3. DCS and PLC systems and instrumentation
4. Raw water and firefighting systems
5. Waste water treatment systems
6. Oily sewer/clean sewer systems and chemical sewers & neutralization pits
7. Service water/potable water/cooling water systems
8. Instrument air/plant air and refrigeration air systems
9. Water treatment systems, demineralization units and boiler water system
10. Nitrogen system
11. Flare system
12. Plant safety equipment and fire & gas detection
13. Fuel gas and fuel oil system
14. Slop systems
15. Flushing oil systems
16. Boiler systems with steam & condensate networks
17. Amine, aromatics and caustic drain systems
18. Feed & product storage systems
19. Product & feed systems
20. Sour water treatment section and chemical handling treatment section
21. Amine treatment section
22. All process systems in order of “priority”
Examples of Pre-Commissioning Procedures:
Spectacle blind installation checks
Non-return valve internals installation checks
Thermal refractory lining installation checks
Mechanical interlock checks
Fitting of all locks on valves
Packing of a distillation or scrubbing column
Packing a reactor with catalyst
Installation of filter medium and cartridges
Air blowing
Steam blowing
Water flushing
Chemical cleaning
Tightness test
Cooling water passivation
Mechanical test run of pumps
Different Pre-Commissioning Checklists
Is used to record the inspection and status of equipment items within the plant
To conform readiness for commissioning
Often to be witnessed by client, PMC & licensor
Pre-Commissioning Test Records
Pre-Commissioning test records are prepared to record the satisfactory completion
of various system preparation tasks & activities that includes:
Cleaning
Chemical cleaning
Drying
Air tightness test
Loading of catalysts
Blinds list
Performance Indicators
Construction QA/QC documentation
Systems punch list (commissioning punch)
Piping pre-commissioning activities
Stationary equipment pre-commissioning activities
Rotating equipment pre-commissioning activities
Instrumentation pre-commissioning activities
Tightness tests
Reporting (Total, Completed & Remaining Tasks)
Pre-Commissioning Additional Records
Request for mechanical completion acceptance
Mechanical completion certificate
Release for pre-commissioning notice
Punch list report of outstanding punch points
During pre-commissioning, you will use also Vendor Specialists
For major items or rotating machinery, major utility systems and special electrical
and instrument control equipment
Package units
The licensor will responsible in conducting the:
Final inspection of “critical” equipment installation
Supervision of catalyst and chemical loading
At the end of Pre-Commissioning, we will get a Milestone called RFC.
RFC (Ready For Commissioning) – means pre-commissioning activities are
completed and the systems are ready to commence commissioning
API Recommended Practice 1FSC – is the minor milestone in project when pre-
commissioning activities for a discipline (electrical, instrumentation, mechanical,
piping, etc.) are essentially complete and ready to commence commissioning.
Protocol – is used for documenting RFC
COMMISSIONING
Commissioning is usually the phase in a project after pre-commissioning when
design process fluids are introduced to the systems and sub-systems. Sometimes
commissioning means running the systems with a safe fluid only.
Commissioning moves the project from the “end of construction” closed to the
commercial operation status.
A complete, well-planned and accurately documented commissioning effort is one
of the key factors that contributes to a trouble-free-start-up (the next step).
API Recommended Practice 1FSC
Group of energized and dynamic tests that constitute verification that each
system or subsystem is fabricated, installed, cleaned and tested in
accordance with design and the systems are ready for start-up.
Grey Area
Cold Commissioning
Hot Commissioning
Cold Commissioning
Dry Commissioning
are the tests and procedures that are conducted without solvents or process
fluids yet introduced to the plant.
Sometimes already done during pre-commissioning
Example activities
Interlock and emergency shut-down tests
Control system sequence checks
Wet Commissioning
Water or a solvent has been introduced into the systems or subsystems.
Tests and procedures conduced with water or solvent
We can play here operating scenarios and we see how system behave
Example activities
Running pumps with closed loops
Interlock and emergency shut-down tests
Hot Commissioning
synonym to “Live Commissioning”
Design process fluids are introduced to the systems and sub-systems
Activities similar to “Wet Commissioning”
RFC (Ready For Commissioning)
Means pre-commissioning activities are completed and the systems are ready to
commence commissioning
API Recommended Practice 1FSC – is the minor milestone in project when pre-
commissioning activities for a discipline (electrical, instrumentation, mechanical,
piping, etc.) are essentially complete and ready to commence commissioning.
Protocol – is used for documenting RFC
In ensuring safety during commissioning, we must conduct:
PTW (Permit to Work) – Is PTW system adequate?
Security – Fencing of facilities, access control, protection from on-going
construction areas, etc.
Emergency response – These procedures must be in place, commissioning staff
trained in their role in such procedures and practical drills held to confirm
effectiveness.
List of some commissioning common activities:
Functional checks Final drying
Operating adjustments Purging/Inerting
Final leak testing First fills
Operation of systems and subsystems
Completion of system turn over and completion package
Sequence for Commissioning process
Commissioning of the facilities will be carried out on a system-by system and unit-
by-unit basis.
Utilize a backwards approach
Control systems, DCS, PLC
Utilities (air, nitrogen, water, steam)
Product storage, tank systems and loading
Core process units (reaction, distillation)
Raw materials feeds
Raw materials storage
Commissioning Procedures Examples:
Utilities and Services
Water Solvent Commissioning
Process Fluid Commissioning
Interfaces Examples:
Operation and Maintenance
Done by the company
“Hands-on” activities for commissioning (and start-up operation and
performance test) of the plant under the direction, advice, and
supervision of the contractor’s commissioning staff, but directly
coordinated/supervised by company’s commissioning staff.
Product Quality Control
Done by the company
Performing product quality control laboratory analysis for the new
facilities under the supervision of the contractor during the
commissioning and performance test phase.
Production Planning
Done by the company & contractor
Company’s production planning for the existing facilities and contractor’s
production plan for the commissioning and operation of the new facilities
must be integrated during the commissioning, start-up and initial operation
phase.
This commence with first requirements for fuel gas, etc. from the existing
plant for boilers tart-up and heater’s dry through initial feedstock transfer
and final product storage, blending and shipping.
Emergency Response, Security, Safety
Done by the company & contractor
Contractor’s emergency response plan for commissioning will require the
support of company and company’s local facilities/services.
The new plant will be integrated with the existing facilities at commissioning
and start-up. Security of the new facilities requires coordination with the
existing.
Operations safety procedures and permit system for the new facilities must
be coordinated with the existing facilities from initial commissioning and
start-up.
Maintenance Support
Done by the company
Company will perform “hands-on” duties and give technical support during
commissioning and start-up for routine maintenance activities and checks.
Such works will be coordinated with the company’s maintenance team.
Vendors
Done by the contractor
All commissioning activities by contractor’s vendor specialist will be carried
out under the supervision of contractor’s commissioning team.
Licensor
Where necessary, the process licensor may supervise the commissioning of
relevant systems and provide technical assistance.
Process operating parameters and conditions will be advised by process
licensor’s process engineers.
Pre-Start-Up Safety Review (PSSR)
Last part of commissioning process
Usually done by systems
Usually managed by commissioning manager
Client commissioning teamA
Contractor commissioning team
Licensor
Ready For Start-Up (RFSU)
API Recommended Practice 1FSC
Signifies that system construction, pre-commissioning and commissioning work
are complete and the required safety verification is ready to commence start-up.
Has to be put down in a protocol.
START-UP
The phase in a project where the entire plant (all systems and sub-systems) are
taken into operation. Process fluids are introduced and process conditions are
established with the intent of making products.
Ready For Start-Up
Signifies that system construction, pre-commissioning and commissioning work
are complete and the required safety verification is ready to commence start-up.
Has to be put down in a protocol.
Shift Works:
Client Vendors
Contractor Licensor
Shift log book
Who
How
What
Paper or electronically
Client and/or contactor
Pre-Start-Up Safety Review
Usually by systems
Usually managed by commissioning manager
Client commissioning team
Contractor commissioning team
Licensor
Pre-Start-Up Checks (What is required to be in place before start-up
Utilities
Feed
Product Storage
Start-Up Procedures Examples:
Pipe & equipment purging
Pipe & equipment evacuation
Initial introduction of feed & chemicals
Initial heating or cooling
To put a catalyst or other media into initial condition
Valve positions for start-up
Start-up sequence
Holding steps
Detailed procedures how the systems and the whole plant is brought into
operation
“Normal” operation including data
Shut down
Emergency shut down
Interfaces Examples:
Operations and Maintenance (by company)
Hands-on activities
Product Quality Control (by company)
Product quality control laboratory analysis
Production Planning (by company & contractor)
Emergency Response, Security, Safety (by company & contractor)
Maintenance Support (by company)
Hands-on duties & technical support
Vendors (by contractor)
Licensor
Where necessary, the process licensor may supervise the start-up of relevant
systems and provide technical assistance.
Process operating parameters and conditions will be advised by process
licensor’s process engineers.
INITIAL OPERATION
The entire plant is running in continuous operation, fine-tuned and prepared for the
performance test.
Shift Works
Client Vendors
Contractor Licensor
Shift Log Book (Hopefully already set-up during star-up phase
Who Paper or electronically
How Client and/or contractor
What
Activities
Fine tuning of control loops
Tuning of process
Testing of operational limits (emergency shut-down?)
Preparation of performance test
Data collection
Equipment data
Process data
Performance data
Interfaces Examples:
Operations and Maintenance (by company)
Hands-on activities
Product Quality Control (by company)
Product quality control laboratory analysis
Production Planning (by company & contractor)
Emergency Response, Security, Safety (by company & contractor)
Maintenance Support (by company)
Hands-on duties & technical support
Vendors (by contractor)
Licensor
Where necessary, the process licensor may supervise the start-up of relevant
systems and provide technical assistance.
Process operating parameters and conditions will be advised by process
licensor’s process engineers.
PERFORMANCE TESTING
Mutual agreement between client, contractor and licensor
To check if the plant is operating according to design
API Recommended Practice 1FSC
Performance testing involves operating the facility and carrying out a series of
defined tasks, demonstrations and tests to measure the new plant and equipment
against the contract, design and nameplate parameters.
Duration
Varies from plant to plant and industry to industry
Examples:
Simple Water Treatment Plant (24-72 hours)
Sulphuric Acid Plant 3x4500 tons per day (4x5 consecutive days)
800 MW Coal Fired Power Station (Several months)
Shift Works
Client Vendors
Contractor Licensor
Shift Log Book (Hopefully already set-up during star-up phase
Who Paper or electronically
How Client and/or contractor
What
Mutual Agreement
Company and contractor mutually agree on performance test procedures, test,
sequences, schedules and other conditions for carrying out the performance
testing.
Interfaces Examples:
Operations and Maintenance (by company)
Hands-on activities
Product Quality Control (by company)
Product quality control laboratory analysis
Production Planning (by company & contractor)
Emergency Response, Security, Safety (by company & contractor)
Maintenance Support (by company)
Hands-on duties & technical support
Vendors (by contractor)
Licensor
Where necessary, the process licensor may supervise the start-up of relevant
systems and provide technical assistance.
Process operating parameters and conditions will be advised by process
licensor’s process engineers.
Don’t Forget
Are you able to take all necessary readings?
Does everybody involved knows where to take the readings
Does everybody knows what can be touched and what should not be touched
during performance testing?
Is the laboratory ready?
Do you have enough sample bottles?
Does everybody know when and how to take samples?
Does everybody know where and how to store samples?
Final Acceptance (FAC)
After successful performance test
Care and custody transferred from contractor to client
Handover
POST COMMISSIONING
The phase starting after handing over the plant to the client (FAC) – until operations
assistance is not needed anymore and the outstanding punch points are solved.
Activities:
Adjustments, modifications and fault correction
Completion of outstanding punchlist items
The first routine maintenance checks are performed, findings evaluated and
reported
Process equipment and items covered by warranty are observed for possible
problems
Operating data is collected and evaluated to ensure consistent plant operations
are maintained
Interfaces Examples:
Contractor
Solving of outstanding punch points
Usually, at the beginning a few experienced commissioning engineers from
the “old” crew
Later usually just one
He or she is the first contact person for the client in the daily routine
Usually, just in day shift
Company
Production Planning
Operations
Maintenance
Product Quality Control
Emergency Response, Security, Safety
Vendors (by company)
For repair works
Licensor
Where necessary, the process licensor may supervise the operation of
relevant systems and provide technical assistance
Duration
Varies from plant to plant and industry to industry
From a couple of months till years