Lifting Procedure Rev.4
Lifting Procedure Rev.4
TABLE OF CONTENTS
1.0. INTRODUCTION.................................................................................................................. 4
2.0. PURPOSE............................................................................................................................ 4
3.0. SCOPE................................................................................................................................. 4
4.0. REFERENCES..................................................................................................................... 5
5.2 Signalman.................................................................................................................... 6
5.4 Rigger.......................................................................................................................... 8
6.0. PROCEDURE....................................................................................................................... 8
7.0. CRANE............................................................................................................................... 23
10.0. ATTACHMENT.................................................................................................................... 40
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
1.0. INTRODUCTION
This procedure will define some types of cranes, basic functions and safety features of the
lifting equipment used for lifting activity on COMPANY’s area and also highlights the
responsibilities of personnel involved with a responsibility for the control and use of lifting
equipment in the service for COMPANY.
This procedure shall be used for all lifting operations to be conducted for New Gas Sales
Project at Cilamaya ORF and NGLA/NGLB.
2.0. PURPOSE
The primary purpose of this document is to provide a safe practice guideline of any lifting
operations within COMPANY’s onshore and offshore area for New Gas Sales Project.
To ensure that lifting equipment meets the safety, integrity and examination requirements of
the Lifting Operations and Lifting Equipment Regulations (COMPANY’s Golden Safety
Rules and HSE Handbook 6th edition, October 2005).
3.0. SCOPE
This procedure applies to any lifting operation by cranes such as tower crane, tower crane
(On board of COMPANY’s platform) that will be under CONTRACTOR’s instruction during
constructions activities, Crawler crane 225 Ton cap. (On board of CONTRACTOR’s Work
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
barge), Truck Loader 3 Ton Cap. and Mobile Crane 45 Ton Cap. (on Cilamaya ORF), in the
COMPANY area of operations. The document covers general requirement of the lifting
equipments and the personnel involved, such as roles & responsibilities, coordination
communication, procedure operation and any emergency situation.
4.0. REFERENCES
It is therefore important that any system set up to manage lifting operations safely, must
recognize this inherent complexity and must ensure that roles and responsibilities and the
competencies for each activity are clearly defined, recognized and that there is a shared
view of interfaces and boundaries.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Planning
Selection of cranes
Selection of personnel
4. Responsible for the organization, control and safety of the lifting operation.
5.2 Signalman
To ensure that a safe system of work is implemented, and have approved work
permit. He is only one authorized to make signal to Crane Operator during lifting
operations. He must have adequate training, experience and technical knowledge to
carry out his role competently. The signalman will be also as a Lifting Coordinator.
Ensure that the appropriate lifting accessory and safe slinging technique is
identified.
Ensure all of personnel is detailed including duties and responsibilities of
each person.
Ensure no unauthorized personnel in lifting area.
Ensure clear communication with crane operator, riggers and others
involve in lifting operation.
Ensure all proximity hazards are identified and deal with.
Ensure that he is identifiable as a Signalman.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Ensure the lift is carried out safely according to the specified safe systems
of work
As Coordinator to lifting activity.
Inspects the lifting and rigging equipment.
Select proper lifting equipment.
Ensure that the load is well secured and the weight does not exceed the
safe working load of the lifting equipment.
Clear-out lifting area.
Monitor weather condition.
Stop lifting operation if any unsafe condition occur and report to the
superintendent.
He should has overall understanding on all lifting activity and scenario. He must have
valid MIGAS certificate and must have adequate training and experience to carry out
the role competently.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
5.4 Rigger
He must be certified and assessed by Third Party approved by COMPANY.
6.0. PROCEDURE
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
All lifting operations must undergo a task risk assessment in accordance with the site
Safe Systems of Work procedure(s).
Generic lifting operations shall be reviewed on a regular basis to ensure that the
original Task Risk Assessments remain valid.
For all lifting operations, the degree of risk identified during the Task Risk Assessment
shall determine the level of supervision required for the operation and the required
experience of the personnel involved.
Task Risk Assessment shall specifically consider manning requirements for safe
conduct of complex and blind lifts to ensure clear communication between all team
members participating in the lifting operation.
In any event, the person planning the operation shall have adequate practical and
theoretical knowledge and experience of planning lifting operations and be competent
to perform the task.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
As a minimum, the plan shall address the risks identified and should identify all
resources, procedures and responsibilities necessary to ensure a safe operation.
Prior to the commencement of any lifting operation, a pre job safety meeting shall be
carried out in order to assess the suitability of the Lifting Plan and to familiarise
personnel involved in the lifting operation with the risks identified.
At this time, minor variations may be necessary to take account of current conditions,
e.g. wind speeds; wave height, position of people deck layout etc. and these should
be documented.
The Lifting plan for Offshore and Onshore will be submitted to COMPANY in separate
document.
To assist with the risk assessment process, lifting operations have been divided in
four categories, which are:
a) Routine
b) Simple
c) Complicated
d) Complex
Lifts that are performed on a regular basis, which involve basic slinging
practices e.g. deck operations, material transfers.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
These lift activities by definition are repetitive and as such, the method
statements, risk assessments, plans and any supporting procedures
should be held on file.
Load with known and evaluated weight shape and centre of gravity
Lifts that involve the use of basic hoisting equipment e.g. a crane or
manual hoist (suspended from dedicated lifting structures such as pad
eyes or runaway beams) directly above the load.
Carried out by competent personnel e.g. Riggers, Deck Crew and others
who have training in hoisting & lifting/rigging skills.
Lifting Personnel
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
If a lifting job involves divers or sub-sea work or the plan indicate the
selected route for the load to travel is over live plant or a confined space, it
will be classed as complex.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Lifting operations shall be suspended when either design wind speeds for lifting
equipment are exceeded or the following average wind speeds reach, whichever is
the lower:
Onshore Lifting – 25 knots (12.86 m/sec)
sea state,
wind direction,
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
On land if there is a prolonged heavy rain, the ground may become softer than normal
and by the way, affect the stability and level of the crane. No lifting during rain or
immediately after; wait at least one hour after rain and check the brakes before
attempting lifting operations.
Where other hazards are identified, these shall be assessed in a similar fashion to
those identified on the notes, with due consideration to possible causes,
consequences and appropriate solutions.
Planning for the worst-case scenario should ensure that all hazards have been
brought to ALARP Level and the necessary mitigation actions are in place.
Lifting more than one dedicated "load" at a single time ("Piggy backing") is strictly
prohibited and should not be carried out under any circumstances.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
machinery
hoist
Use of additional
banksman/ radios
Fit tag lines
Transit damage. Falling objects Consider alternative
Load
slinging method.
damaged Sharp corners. Load falling.
Pre-lift check
Personnel injury.
Ensure emergency
access route.
Correct PPE.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
6.5.5 PERSONNEL
HAZARD POSSIBLE CAUSE CONSEQUENCE SOLUTION
Human
Inadequate training incorrect choice of Ensure adequate
factors
equipment. training.
(Knowledge based) Lack of
competence. Incorrect attachment Check competency
of lifting level of personnel
accessories. involved in lifting
operation.
Incorrect operation
of equipment. Increase
supervision.
Load swinging.
Load striking
person.
Load striking plant.
Equipment damage.
Personnel injury
Slips Incorrect choice of Pre-Job safety
equipment meetings
Lapse.
Incorrect attachment Realistic time frame
Mistakes.
of lifting to perform job.
accessories.
Increase
Human factors (Error Incorrect operation supervision.
based). of equipment
Load swinging.
Load striking
person.
Load striking plant.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Equipment damage.
Personnel injury
6.5.6 STRUCTURAL
HAZARD POSSIBLE CAUSE CONSEQUENCE SOLUTION
Incorrect load Dropped object Engineering
applied to structural calculations
Load striking person
component.
Proof load testing
Load striking plant
Lifting equipment
Structural Equipment fitted or
not fitted and Personnel injury
collapse fitted by,
assembled correctly
trained/competent
personnel
Thorough
examination by
competent person
prior to use
Inadequate surface Mobile crane Engineering
loading instability calculations
Deck collapse or Capacity for weight Deck failure Correct anchorage
Ground of load
subsidence Dropped object Spreader plates
Environmental placed under load or
Load striking person
conditions mobile crane
Load striking plant outriggers
Personnel injury Soil testing
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
After lift
1. Check equipment after use.
QUESTIONS Yes No
4 Has the load been checked and made ready for lifting (e.g. sea
fastenings released, hold down bolts removed)?
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
If the answer to all questions below is "Yes", proceed with the Routine lift.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
If the answer to any of the above is "Yes", proceed with the Simple lift
COMPLICATED LIFTS
(Part 3)
The personnel about to perform the lifting operation shall complete the table below.
Tick against factors, which are applicable and specific to this lifting operation and indicate
whether or not you have the relevant experience to deal with them.
QUESTIONS Yes No
1 Is the lift stable? (i.e. centre of gravity below the lifting points and not
offset).
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
2 Is the centre of the gravity for the load viewed as balanced and
acceptable?
3 Can the lift be performed without cross-hauling or being restrained?
4 Does the load have specific lifting attachments?
5 Is the load robust? (not fragile)
6 Does the load have a limited surface area that will not cause
instability in the wind?
7 Does the load require only one crane? e.g. no tandem lifting
8 Can the lift be performed without rotation?
9 Uncertified structural components- can the lift be carried out safely
without the need for MHC engineering calculations
If the answer to any of the above is "Yes", proceed with the Completed Lifts
Job title-----------------------------------------------------------------------------------------------------------------
Date--------------------------------------------------------------------------------------------------------------------
Approved/Endorsed by---------------------------------------------------------------------------------------------
Job Title----------------------------------------------------------------------------------------------------------------
Date------------------------------------------------------------------------------------------------------------
However if you decide that the operation is out with the scope of your competence,
indicate the reasons applicable in the table in Part 4 complex lifts before passing it
to the Lifting Technical Authority (LTA).
COMPLEX LIFTS
(Part 4)
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Tick
REASONS FOR REQUESTING ENGINEERING INPUT
box
1 The lifting operation involves divers
3 The load will be travelled over unprotected process plant and machinery
6 The lift is in a confined space and/or an area with very restricted headroom.
--------------------------------------------------------------------------------------------------------
Job title-----------------------------------------------------------------------------------------------------------------
Date--------------------------------------------------------------------------------------------------------------------
12.0. CRANE
This section will be shown and described some types of cranes and its basic function for
giving everyone knowledge when they are working using crane as a lifting equipment.
Safety features of a crane, personnel involved and their roles and responsibilities are also
important and be-focusing in this procedure.
7.1.1 OPERATIONS
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Operating Practices
o The operator should be familiar with the equipment and its proper care. If
adjustments or repairs to the crane are necessary, or any deficiencies
that impair safe operations are known, the crane should be taken out of
service or its operations restricted to eliminate the unsafe condition.
o Before starting the crane, the operator should verify the following:
a. The pre-use inspection
b. All controls are in 'off' or "Neutral" position.
c. All personnel are in the clear area.
o For mechanical cranes, the operator should operationally test the brakes
each time a load approaching the rated load is to be handled. Prior to
raising the load, exposed brakes should be warmed and rusted surface
on the drums cleaned by raising and lowering the boom and load lines
under slight brake pressure.
o The operator should response only to signals only from the appointed
signalman but should obey an emergency stop signal at any time, no
matter who gives signal.
o The operator should verify that the appropriate static and dynamic load
charts are in place for the crane configuration in use (i.e boom length,
load line reeving, counter weight etc).
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
o The operator should be aware of the heat sources such as natural gas
engines, gas turbines, flares, or any other heat source that exhausts
near the crane. Stress corrosion cracking, paint damage, accelerated
corrosion, and loss of the lubrication can result in reduced service life of
components.
o Where cranes are to be used at night, the operator should insure that
there is sufficient lighting for safe operations. The load and landing area
should be illuminated.
o The operator should keep and maintain a log of pre-use inspection with
the name, date and time of inspection. This record should be kept in an
appropriate location.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
The operator should verify that the hook load is within the crane's
applicable Static or Dynamic Rated Load at the radius at which the
Load is to be lifted.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
The operator shall not hoist, lower or swing while any personnel
are on the load or hook (other than in the personnel transfer
capsule)
No fewer than 5 (five) full wraps of the rope should remain on the
drum(s) in any operating condition. Due consideration should be
given to hoist manufacturer's recommended practices, especially
for break away anchor-type hoists.
When two or more cranes are used to lift one load, one qualified
operator should be responsible for the operation. The responsible
operator should analyze the operations, and instruct all personnel
involved in the proper positioning, rigging of the load and the
movements to be made.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
7.1.2 SIGNALS
Signals between the crane operator and the designated signalman should
be discernible, audibly or visually, at all times. The operator should not
respond unless signals are clearly understood.
7.1.2.1 INSTRUCTION
7.1.2.2 SIGNALLING
The requirements operation will be same with offshore tower crane exception this
crane will be used on land.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Mobile Crane is the other common crane, on land, which are normally fitted with
telescopic jib. They travel from site to site to perform lifts and usually have to put
down outriggers before lifting. Their ability to move with a load is very limited and so
they are generally restricted to lifts within their safe operating radius in any particular
location.
7.2.1 REQUIREMENTS
Keep the operator's area free of water, oil, and debris that could cause
hands or feet to slip from the controls. Keep the operating cab. windshields
clean and free of anything that obstructs vision.
Ensure proper functioning of the crane. If at any time a crane is found to be
in need of repair, is defective, or is in any way unsafe, take the crane out of
service until it has been restored to safe-operating condition.
Do not hoist one load on the main hoist and another load on the auxiliary
hoist at the same time. Ensure that fire extinguisher is installed at the
operator station.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Do not store gasoline, acids, caustics, or cleaning solvents that emit toxic
fumes in operating cabs. Store fuel in safety cans in safe locations. Do not
store any loose items in the cab.
Position the crane on a solid and level footing. It may be necessary in certain
situations to use heavy timber mats to build a good working foundation. The
surface area of the mats should be 3 times the surface area of the crane
outrigger pads.
When swinging the crane, watch out for centrifugal force. Swing the crane
slowly to avoid an outward swing of the load. Start and stop the swing
slowly. Attach tag lines to the load to control the swing.
Watch for boom kickback. Never operate with the boom at a higher angle
than shown on the crane capacity charts.
Use power lowering when lowering loads. When lowering heavy loads, keep
the hoist brake as reserve. Use a safety pawl on the boom-hoist drum when
not lowering.
Avoid two-blocking, caused when the hook block makes contact with boom-
point sheaves. A continuing pull on the hoist lines can break the rope or pull
the boom back over the cab on some types of booms. On hydraulically
telescoping booms, be sure to play out the hoist line when extending and
spool in the hoist line when retracting. On hydraulically telescoping booms
do not rely on the anti two-blocking device as an operating control.
Do not leave your position at the controls while the load is suspended,
unless required to do so by an approved emergency procedure.
15.0. Truck Loader 3 Ton Cap.
The crane is mounted on the truck and will be used for loading and unloading
material/equipment purpose from/to truck’s basin. This Truck Loader will be used for
onshore lifting only.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
4. The operator must make sure that there are no electric wires or any other
obstacle within the working radius of the loader.
5. The operator must inform by unauthorized persons that entry into the working
area is not permitted.
6. The stability of the vehicle and the load is based on the stabilizer leg in their
extreme position, and the loader should only be used at maximum stabilizer
spread. The stabilizers should be lowered just enough to raise the truck
chassis a little in its suspensions.
7. The tyres must still have full contact with the ground. During loading of the
truck, the stabilizer legs must be raised from time to time, to ensure that the
weight of the load is carried by the truck and not by the stabilizer legs. The
stabilizer legs are not designated to support this excessive load.
8. The best possible loader operation will be achieved when vehicle is positioned
as close to horizontal as possible. Therefore, the vehicle should be leveled to
horizontal position by means of the stabilizer legs before the loader is
operated.
9. If the ground is not form enough to take up the pressure of the stabilizer legs,
a steel plate, or the like must be placed under the foot plates.
The loader is designed to lift loads vertically and therefore diagonal stresses should
be avoided. Consequently it is not permitted to drag loads across the ground using
the extension cylinders or the slewing system. These functions may only be activated
once the load is free of the ground.
If the load is extended so far that the lifting capacity is exceeded, the main boom will
slowly begin to sink. To stop this movement the load should be brought closer toward
the loader column by means of the jib or the extension cylinder.
The Crawler Crane is also mobile on deck of Work Barge, movement is limited to
forward and backward on the deck of work barge, during lifting purpose the crawler
will be secured on the deck of Work Barge before lifting operation is carried out,.
When no lifting operation will be carried out, the boom is rested at boom rest.
The operation of crane rated at over two tons Gross Vehicle Weight (GVW) will only
be done by qualified operator who are assigned to operate the crane.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
The Supervisor and/or COMPANY Representative shall verify the validity of operator
license and qualifications prior to the start of work.
7.4.1. OPERATION
The Work Barge will be used i.e. BARUNA 3, with the dimension, 272ft
length overall, 67ft breadth and 16ft depth.
The stability of barge will be submitted to COMPANY.
Lifting procedure of Barge (BARUNA 3) shall be followed.
Load indicator shall be installed and annual calibration by authorize third
party.
Lifting shall be conducted as per safe radius against load (Follow Load Chart
Table), the load chart shall be posted on the crane cabin.
The unit will always be operated in accordance with the manufacturer’s
operating instructions.
Crane operators will always assure themselves that the unit can be operated
safely by making a complete functional check/inspection of the unit prior to
the start of any work.
Crane operators are responsible to ensure the work area is free from
obstructions or hazards.
If the continued safe operation of the unit is questionable, the activity shall
cease until such time as the concern has been resolved by the supervisor in
charge.
Crane operator shall complete a daily safety checklist.
All crane deficiencies shall be reported to the appropriate maintenance dept.
Maintenance Log Book shall be maintained.
Only authorized crane operators are permitted to operate crane. An
authorized crane operator is someone who hold a valid crane operator
license or meets these same qualifications through Third Party licensing
approved by MIGAS and who is authorized by the facility supervisor to
operate a crane.
Cranes shall be inspected and documented by the crane operator using a
checklist prior to the start of operation each day. If a crane is found to be
unsafe to operate it shall be posted “out of service”.
Only one person shall be designated as the signalman to the crane operator.
All other personnel will stand clear. If line of sight can not be established
between the crane operator and signalman, hand free audio communication
should be used.
The crane operator should never start machine movement until
communication with the signalman is established and understood. Obey
emergency stop signal given by anyone.
All cranes shall have load charts and boom angle or radius indicators
located at the crane operator’s position. Offshore cranes shall reduce the
load chart value by 25% when handling dynamic loads.
The crane operator shall ensure that the weight of any load does not exceed
the rated capacity of the crane during a transfer.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
All cranes shall be secured and pointed away and below the helicopter deck
and the crane operator shall be outside of the crane cabin while the
helicopter is operating in the area of the platform until clear from take off or
shut down.
The operator shall be in the cab any time there is a load suspended from the
hook except during helicopter operations as noted above.
Cranes with booms extended across process lines shall not be left
unattended.
Crane shall be labeled its safe working load limit and periodically inspected
and personnel shall be trained.
All crane hooks will be equipped with operating safety latches.
Lifting Plan need to be considered and must developed with Supervisor’s
decision for lifting above 1000kg or any complex lifting (eg. Lifting using two
cranes operation).
Other general lifting/rigging regulations and requirements must refer and
comply to the HSE BP Handbook 5th edition section 2.20 and 2.21.
Note :
1. During towing of work barge by Anchor handling Tug, boom crane have to rest on
boom rest and applied appropriate lashing.
2. If any rolling / pitching / heaving whereas make the heeling angle on the barge upto
3 3˚, then every lifting activities that involving crane have to be stopped.
8.1. POLICY
Effective inspections of all Lifting gear is imperative for a safe operation. It is the
responsibility of the user to visually inspect lifting equipment each time that it is used.
This is to verity that there are no obvious defects in the equipment.
8.2. DEFINITION
Lifting Equipment is defined as equipment which may be attached to and which may
be below the crane hooks; or equipment which by design is to support a lifted load
such as slings, shackles, work baskets; or equipment which would be utilized to raise
and lower a derrick / mast or block.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
This category includes slings / wire rope which are subject to a high degree
of wear and tear resulting from regular use. This category is inclusive of:
Chain slings
Eye Bolt
3
4 Shackles
Cargo nets
All category I lifting equipment shall have an initial load test before being
placed in service. Category I equipment shall receive certification annually /
every year by a third party inspector with a record kept of the inspection.
This category includes all lifting equipment, which has been purchased from
a bonafide manufacturer and by design is capable of making safe lifts up to
the Safe Working Load (SWL). This category is inclusive of:
Eye bolts
Hooks
Come-alongs
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
Air tuggers
Shackles
This category generally includes all lifting appliances which are intended for
a very specific use and which are by design, limited to a particular lift or lifted
load. This category is inclusive of:
Cargo baskets
Spreader bars
Cylinder racks
Transportable tanks
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
8.5. INSPECTIONS
Examination of lifting equipment to ensure that it is safe for use. The inspection
should also ensure that the correct lifting equipment is used. The inspection should be
done by an individual who is familiar with the equipment and he work to be performed
The color code will follow BP regulation to indicate compliance with annual inspection
and re-certification.
In the interest of safety and to assist the crane operator, the crane has various limiting
devices for the six motions to prevent damaging the crane.
a. When jibbing up, there are limits to prevent the jib coming into contact with the
back-stops.
b. When jibing down, there are limits to prevent the jib angle becoming less than
approx. 15 degrees to the horizontal. (This limit can be over-ridden to allow
parking of the jib in the rest).
c.When hoisting, there is a limit trip to prevent the hook block being pulled through the
sheaves-anti two block limit.
d. When lowering, there is a limit trip to prevent running the hoist rope completely off
the winch drum thus losing the rope, hook block and possibly the load.
e. Slewing limits area sometimes fitted but care still has to be exercised by the crane
operator (and a signalman that guide the crane) to avoid striking the jib against
obstructions such as other cranes and structures on the platform.
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
In addition to the limit trips, other safety feature of the crane is an automatic Safe Load
Indication (SLI) system backed up by visual and audible alarms. The SLI tells the crane
operator of the operating radius of the crane (i.e. where the hook is), the SWL of the crane
at that radius and the actual load on the hook. The visual alarm is usually set to activate at
approx. 95% of the crane capacity at any given radius where the audible alarm activates at
approx. 105% of the crane capacity, i.e. in an overload situation. The operating cabs will
contain a fire extinguisher, smoke hood and Life Jacket.
As with all lifting machines, cranes have a maximum safe working load but this depends on
the number of wire rope on the block sheave.
The SWL also reduces as the operating radius increase. The lifting operation shall refer to
the load radius which will be posted in the crane cab.
For loading or unloading a vessel, further reductions in capacity may apply due to dynamic
loading caused by the weather conditions.
9.1.1. Equipment
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
9.1.2.1. A minimum of five competent personnel are required for all marine
transfers (i.e. one designated signalman and one rigger on the
vessel, as well as one designated signalman, one rigger and crane
operator on the facility).
9.1.2.2. A minimum of three competent personnel are required for crane
material transfer within the facility (i.e. one crane operator, one
designated signalman and one rigger).
9.1.2.3. Respective superintendent shall assign dedicated crane operator
and signalman to carry out day to day lifting operations.
9.1.2.4. Name of the assigned personnel above shall be posted on the
STATION DUTY ROOSTER.
9.1.4. Communication
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
All lifting operations shall be carried out according to the following sequence
of actions:
Communicate
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
21.0. ATTACHMENT
10.5 ATTACHMENT – 5 : Lifting Operations (Shackle & Eye Bolt Inspection Flow
Chart)
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.1. ATTACHMENT-1
Flow Chart for Crane Operation
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.2. ATTACHMENT-2
Lifting Request Information
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.3. ATTACHMENT-3
Daily Pre-Operation Inspection Check List
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.4. ATTACHMENT-4
Lifting Operations (Rigging Inspection and Preparation
Check List)
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.5. ATTACHMENT-5
Lifting Operations (Shackle & Eye Bolt Inspection Flow
Chart)
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.6. ATTACHMENT-6
Flow Charts – Crane Pre/Daily Inspection
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.7. ATTACHMENT-7
GENERAL PROCEDURE FOR CRANE OPERATIONS
AND SAFETY
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.8. ATTACHMENT-8
LAY OUT, SPECIFICATION & CERTIFICATE MIGAS OF
CRANE BARGE BARUNA 3
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
10.9. ATTACHMENT-9
BERITA ACARA PENGUJIAN BEBAN TOWER CRANE
NGL B
404662794.doc
Company : Contractor :
EPCI FOR FACILITY MODIFICATION
AT NGL AND CILAMAYA
TO SUPPORT NEW GAS SALES PROJECT
PT. ISTANA KARANG LAUT
3 10.10. ATTACHMENT-10
SIGNAL FOR MOBILE CRANE
404662794.doc