75% found this document useful (4 votes)
9K views4 pages

Progress Billing Sample: Item Amount

The document is a progress billing sample that lists 13 items of work completed on a construction project and their amounts. It provides a detailed breakdown of the civil/structural and masonry works completed to date including column footings, beams, slabs, walls and plastering. The total amount billed for the completed work is 14,939,982.02.

Uploaded by

aj abobo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
75% found this document useful (4 votes)
9K views4 pages

Progress Billing Sample: Item Amount

The document is a progress billing sample that lists 13 items of work completed on a construction project and their amounts. It provides a detailed breakdown of the civil/structural and masonry works completed to date including column footings, beams, slabs, walls and plastering. The total amount billed for the completed work is 14,939,982.02.

Uploaded by

aj abobo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROGRESS BILLING SAMPLE

ITEM AMOUNT
1 MOBILIZATION 71, 456.00
2 SAFETY 38, 976.00
a. Personnel Protective Equipment
3 EARTHWORKS
a. Layout 31,180.80
b. Excavation 866,566.40
c. Filling to desired Ground flr. Elevation 140,313.60
d. Removal of Existing Structures
4 CIVIL/ STRUCTURAL & MASONRY WORKS
a. Column Footing 721,469.15
b. Tie Beams 603,517.38
c. Columns up to 2nd Floor 1,259,223.62
d. Second Floor Beams 1,014,753.15
e. Second Floor Slabs with Plain Cement Finish 707,334.75
f. Stairs , Concrete Benches and Ramps 198,819.18
g. Columns up to Roof Beams 561,042.63
h. Roof Beams 379,574.27
i. Ground Floor Slabs with Plain Cement Finish 558,224.02
j. Wall Footings 42,683.92
k. Filing of CIIB Wall 1,355,780.16
l. Cement Plastering with Plain Cement Finish entire 465,711.23
Building
m. Entrance Canopy Concrete Fascia and Gutter 17,936.75
n. Concrete Railings and Ramp Railings 235, 619.01
5 ROOF FRAMING 2,127,823.27
6 ROOFING 831,547.76
7 CEILING FRAMES AND BOARDS SECOND FLOOR 505,381.14
INCLUDING CR GROUND FLOOR
8 DOORS AND WINDOWS 702,941.24
9 CR TILES AND FTXTURES 347,704.90
10 FORM WORKS 626,204.01
11 ELECTRICAL WIRES AND FIXTURES 338,930.09
12 WATER AND SEWER LINES 110,339.50
13 SEPTIC TANK 84,928.72

TOTAL 14,939,982.02
PERT (PROGRAM EVALUATION REVIEW TECHNIQUE)/ CPM (CRITICAL PATH METHOD)

You might also like