TURBINE COLD
START UP
PROCEDURE
Initial Condition of Turbine
Turbine is under Cold condition
HP & IP starting probe temp is less than
1500C
AOP,JOP & OVEF in service
TG Rotor on Turning Gear
Speed = 19
Ensure all related work permits are returned
Ensure TG rotor is on Barring Gear (in auto) &
all oil pumps in auto
Ensure sufficient CST level & keep one hot well
make up in service with recirculation
Ensure adequate level in condenser Hot well.
(About 650mm)
Ensure Deaerator at adequate level (About
2500mm)
Ensure one CW pump is running
Ensure one TCW booster pump & CCW pump
in service with one PHE
Ensure Turbine Lube oil cooler water valves in
open condition
Ensure all the Turbine drain valves (MAL-
12,13,14,22,23&24) & MST,CRH and HRH line
drains MOV & GV in full open condition
Ensure drain before Boiler Main Stop valve in
open condition (MOV & GV)
Ensure drain before MST to AST PRDS in open
(MOV & GV)
Ensure AST header atmosphere drain in open
Ensure Main Ejector PCV in Auto & in Full open
condition (Pr. Set at 15 Bar)
Ensure opening of Steam trap GV & Bypass valve
in Seam of Main Ejectors & open one of the Main
Ejectors steam valve
Ensure full opening of drain before HP Bypass
valves. (Steam trap GV & Bypass valve)
Ensure opening of Stem trap GV & its Bypass
valves in the seal steam header drain line.
Ensure charging of BFPs & charge the feed line
through gravity by opening the discharge valve
& release the air
Ensure charging of CEPs
Start one Boiler Feed Pump & charge the Feed
Water circuit including HP Heaters & keep
another BFP in standby
Start one CEP & charge condensate circuit
including LP Heaters
Start The TV camera pump after venting
Start second CW pump
Open Bypass valve of Boiler Main Stop Valve
Start warming up of MST to AST PRDS
Ensure running of one Oil pump in HP Bypass
OSU & check for Oil leak at HP & LP Bypass
valves
Commission MST to AST PRDS & put AST
Pressure & Temperature control in Auto (set at
15 Bar & 3000C). Maintain AST header
pressure above 15 Bar.
Warm up the Boiler & FOPH steam line from
AST header
Warm up Deaerator preheating line & start
preheat the Deaerator tank (Keep Deaerator
motorized vents full open)
Warm up AST to Pilot Ejector & Seal Steam
system
Open the Main Valves at AST header for Boiler
& FOPH Steam lines
Ensure AST header pressure above 15 Bar &
Temp above 2500C
Commission AST pegging steam to Deaerator
& gradually raise the Deaerator pressure to
1 Bar
Prepare the system for Condenser Vacuum
raising (For Turbine Seal steam admission
minimum 500C super heat is necessary)
Ensure Main Ejectors siphon filling line is in
Open Condition
Start Vacuum pulling through Pilot Ejector
(Before raising vacuum ensure TG Rotor on
Barring Gear and Re-Heater drains & vents at
Boiler side closed)
When the vacuum is about 0.2 Bar (a), open
the Boiler Main Stop Valve (Take care of Drum
Level)
Close Drain Valve before Boiler Stop Valve
Ensure full vacuum is reached
Commission the HP & LP Bypass system and
keep in Auto
Ensure minimum super heat of 500C for HP B/P
opening
Ensure initial opening of HP B/P valves always
above 20% (Take care of Drum Level)
Close Steam Trap B/P valve in the drain line
before HP B/P valves
Ensure LP B/P pressure set at 7 Bar in full Auto
& check for opening of LP B/P valves
Ensure opening of HP & LP Bypass valves
above 20% (Check for temp pick up at the
Turbine)
Commission one Main Ejector when Main
Ejector steam pressure at 15 Bar & Temp is
above 2500C and close Pilot Ejector air valve
Maintain Main Ejector shell level by 250mm
(Observe for any vacuum drop)
Open CRH to Deaerator pegging steam valve
and maintain Deaerator pressure above 1 Bar
Ensure all the Turbine drain valves (MAL Valves) &
MS,CRH & HRH line drains valves in open condition
Prepare the system for Turbine reset
When MS Pressure >35 Bar & Temp above 3000C
RESET the Turbine for Opening of HP&IP stop valves.
(Ensure minimum Superheat of 500C)
Confirm of HP&IP stop valves opening at local
Ensure no speed rising on operation of Stop valves
Open LP Heaters & Deaerator steam extraction valves
(MOVs & Extn. NRVs)
Ensure Condensate to LP Heaters are made through
Ensure LP Heaters drain condensate valves are in
Auto
Raise the MST Pressure gradually to 45 Bar
Ensure the Steam temp is not dropping below
3200C
Check for HP & IP stop valves metal temp
pickup
Keep the Pegging Steam to Deaerator in Auto
(AST & CRH)
Turbine Rolling Parameters
1. MST Pressure = 45/50 Bar
2. MST Temperature = 3700C
3. HRH Pressure = 7 Bar
4. HRH Temperature = 3500C
Ensure HRH Temp is always less than MST
Temp by 200C
Ensure Turbine Drain valves open
(Choke MS line drain by 50%)
Record Rolling parameters, Turbine metal Temps and
supervisory readings
Switch ON Turbine RSE
Start Turbine Rolling (Target Speed 501 rpm &
Acceleration 5%)
Ensure Turning Gear got disengaged on Rolling
Check the Turbine supervisory readings and observe
HP & LP De, Axial Shift, Shaft vibration & Bearing
metal Temp
At 500 rpm warm up the Turbine for 30 min (Turbine
soaking for 30 min)
Keep steam parameters steady
Check for HP&IP starting probe temp pick up
Start further Speed rising of Turbine (Target
speed 3000 rpm & Acceleration 5%)
Check the Turbine supervisory readings and
observe HP & LP DE, Axial Shift, Shaft
Vibration & Bearing metal temp
Record Maximum vibration during speed rising
(In the critical speed range, Auto acceleration is
10%)
Check for Opening of LP Exhaust hood spray
at 1500 rpm
Check the Lube Oil Temp (about 450C)
Observe Turbine Stress Margin
Observe HP Turbine exhaust temp & should
not exceed 4500C
Ensure stoppage of Auxiliary Oil Pump and
jacking Oil Pump at 2700 rpm & observe the
Lube Oil header pressure
Ensure Turbine RSE is ON & Enabled
On Synchronizing check the control valve open
demand rises by 5% for initial load pick up &
check for the load rising
Close MS line drain valves fully
Slowly raise the load till HP & LP Bypass valve
closure
If HP/LP Turbine stress margin is dropping, DO
NOT raise the load (Take care of Drum Level)
Hold 10/20 min. at this load depending on
Turbine Stress Margin
Ensure Closing of LP exhaust hood spray at
10% load
Ensure closure of Turbine drain valves, HRH &
CRH drain valves at 15% Load on Auto (Close
the GV of MOV if necessary)
Ensure turbine Follow Mode is selected
automatically on full closing of HP & LP Bypass
valves and ensure HP Bypass pressure set on
full Auto
Slowly close the Pilot Ejector steam valve
Close Deaerator Start up vents
Close steam trap bypass valve in the seal
steam header drain line
Check Turbine Stress Margin for Parameter
raising (Margin must always be above 1%)
Observe HP & LP DE for any abnormality
Rate of parameter raising.
Load :1.5 MW/min
MS pressure : 0.2 bar/min (up to 70 bar)
MS pressure : 1.2 bar/min. (above 70bar)
MS Temp : 1 0C/min. (Up to 490 0C)
MS Temp : 1.5 0C/min. (above 490 0C)
(Take care of Turbine thermal stress)
Ensure take over of Turbine self-sealing and
open CRH steam to seal header MOV
Charge CRH to AST PRDS
Raise MS pressure gradually depending upon the
Steam Purity and Silica value (MS & Condensate
silica must be less than 20 ppb)
Load the Turbine slowly on observing HP & LP
DE and Stress margin
LOAD : 70 MW
MS pressure : 60 70 bar.
MS & HRH Temp : 450 OC.
(*** Ensure the Turbine control valves not opening full,
while raising the load ***)
Start charging of HP heaters on steam side at a
load of 70 MW (Ensure FW to HP Heaters are made
through)
Start one LP drain pump at a load of 90-100 MW
Start second BFP
Commission CRH to AST PRDS and set the
pressure at 15bar.Reduce MS to AST PRDS set
to 14 bar and ensure take over of CRH to AST
PRDS
LOAD : 90 MW
MS pressure : 70 80 bar.
MS & HRH Temp : 480 0C.
(If the silica value is high DONOT raise the load &
the pressure)
LOAD : 110 MW
MS pressure : 90 100 bar.
MS & HRH Temp : 500 0C.
LOAD : 140 MW
MS pressure : 110 120 bar
MS & HRH Temp : 520 0C
LOAD : 160 170 MW
MS pressure : 130 bar
MS & HRH Temp : 535 0C
LOAD : 210 MW
MS pressure : 146bar
MS & HRH Temp : 535 0C
Put CMC mode into service& enable Frequency
influence.
TURBINE START UP PARAMETER
ESV & ISV Warm Up
HPT – Turbine Rolling Min Load
for 10 min
Sl. RSE after
No Probe SH3 O/L RH2 O/L Acc Holding synchronize
MS Pr & HRH Pr
Temp Pr & Pr & Rate Time at & Hold Time
Temp & Temp
Temp Temp % 500 rpm
Below 30 Bar 7 Bar 45-50 Bar 7 Bar 20 MW
1 5 30 min
1500C 3000C 2500C 3700C 3500C 10 min
1500C 40 Bar 7 Bar 20 MW
7 Bar 50-60 Bar
2 to 325 - 350 - 7 20 min
3000C 4000C 10 min
2500C 3500C 3750C
2500C 60-70 Bar 7 Bar 70-80 Bar 7 Bar 20 MW
3 to 375 - 350 - 400 - 350 - 10 10 min
3500C 4500C 4250C 4500C 4250C 10 min
3500C 80 Bar 7 Bar 80-100 Bar 7 Bar
30 MW
4 to 450 - 400 - 450 - 450 - 10 5 min
5 min
4500C 4800C 4800C 5000C 5000C
4500C 100 Bar 7 Bar 40 MW
100 Bar 7 Bar Direct
5 and 500 - 500 - 10
5000C 5000C 3000 rpm 5 min
above 5200C 5200C
Start Up Limiting Factors
Thermal Stress
Non steady state operation such as start up,
shutdown & load changes give rise to Thermal
Stresses
Vibration
Excessive vibration affecting a machine can be
originated by improperly balanced or bowed Rotor
Differential Expansion
Sudden loading & Unloading can give raise to
excessive temp differences between Rotor &
Casing. This is due to differences existing between
Mass & Surface area of the parts concerned
Turning Gear Operation
Its very important that Turbine shaft is turned by
the turning gear for a sufficient period of time
before a start-up is initiated, even if the turbo-
group is in cold condition.
Turning Gear times are:
Shaft Stand still Min. Turning Gear Time
Less than 1 day 2 Hours
Up to 7 days 6 Hours
From 7 to 30 days 12 Hours
Over 30 days 24 Hours
Critical Speed Range
Speed up must never be stopped when in
the range of following critical speeds
Critical speed range:
0800 – 0900 RPM
1560 – 1700 RPM
2000 – 2450 RPM
Differential Expansion
Differential Expansion should be watched
during load increase as well as load
decrease
Positive Expansion (+ve) mean the Rotor
Shaft is longer than Cylinder Body (During
Loading)
Negative Expansion (-ve) mean the Rotor
Shaft is shorter than Cylinder Body
(During Unloading)
Temperature at the HP Steam Exhaust
The HP exhaust steam temp limiter provides for
limiting the exhaust steam temp by acting on
both MST & RH control valves
Moreover during a load rise when coming fron
no-load or low load condition, care shall be
exercised that no allowable cooling down
gradients occur at the HP exhaust steam outlet
Allowable values given below:
Sudden Temp change :500C
Temperature gradient :1.30C/min
Under normal condition this is governed by the
HP cooling down limiter
LPT Ventilation Safety
On No-Load/Low Load operation for a certain
time length & concurrent bad vacuum he
turbine temp can become to high through the
ventilation
Values for Spray Water Exhaust Hood system
>750C : Opening Spray valve
Boundary value for LP blading temp
>1800C : Alarm
>2000C : Tripping
THANK YOU