CIVIL – PROGRESS & PLAN (As on 09.08.
2016)
SN Activity Date of Completion Revised D.O.C.
1 Topographic Survey Report 28 July Completed
2 Geotechnical Investigation 15 Aug Completed
3 Draft Horizontal Alignment 29 July Completed
4 First discussion with MD/CMRL 3rd to 6th Aug 1st to 3rd Aug
4a Second discussion with MD/CMRL -- 16th to 18th Aug
5 Vertical Profile 8th to 26th Aug 19th Aug - 09th Sept
6 Alignment Report 30th Aug 15th Sept
7 Utilities data collection 1st Aug - 20th Aug 19th Aug - 02nd Sept
8 Utilities Marking on Drawing 20th Aug - 26th Aug 05th Sept – 09th Sept
9 Land requirement 29th Aug – 02nd Sept 05th Sept – 14th Sept
10 Cost Estimate 29th Aug – 02nd Sept 16th Sept - 20th Sept
11 Chapter writing 02nd Sept – 15th Sept 30th Sept