4         Activity-Based Costing
Learning Objectives
            Discuss the difference between traditional costing and
       1
            activity-based costing.
       2    Apply activity-based costing to a manufacturer.
            Explain the benefits and limitations of activity-based
       3
            costing.
       4    Apply activity-based costing to service industries.
4-1
 LEARNING              Discuss the difference between traditional
                1
 OBJECTIVE             costing and activity-based costing.
      Traditional Costing Systems
          Allocates overhead using a
           predetermined rate.
           ►   Job order costing: direct labor
               cost may be the relevant activity
               base.
           ►   Process costing: machine hours
               may be the relevant activity base.
4-2                                                             LO 1
      Illustration of a Traditional Costing System
      Atlas Company produces two abdominal fitness products—the Ab
      Bench and the Ab Coaster. The direct materials cost per unit is $40 for
      the Ab Bench and $30 for the Ab Coaster. The direct labor cost is $12
      per unit for each product. Both products require one direct labor hour
      per unit, both products are allocated overhead cost of $30 per unit.
                                                               Illustration 4-3
                                                               Total unit costs—
                                                               traditional costing
4-3                                                                                  LO 1
      The Need for a New Approach
          Tremendous change in manufacturing and service
           industries.
          Decrease in amount of direct labor usage.
          Significant increase in total overhead costs.
          Inappropriate to use plantwide predetermined overhead
           rates when a lack of correlation exists.
          Complex manufacturing processes may require
           multiple allocation bases; this approach is called
           activity-based costing (ABC).
4-4                                                                LO 1
      Activity-Based Costing
      An approach for allocating overhead costs.
          Allocates overhead to multiple activity cost pools.
          Assigns the activity cost pools to products or services by
           means of cost drivers.
4-5                                                                     LO 1
      Activity-Based Costing (Four Steps)
      1. Identify and classify the activities involved in the
         manufacture of specific products and assign overhead to
         cost pools.
      2. Identify the cost driver that has a strong correlation to the
         costs accumulated in each cost pool.
      3. Compute the activity-based overhead rate for each cost
         pool.
      4. Allocate overhead costs to products using the overhead
         rates determined for each cost pool.
4-6                                                                      LO 1
      Activity-Based Costing
      ABC allocates overhead in a two-stage process:
          Stage 1: Overhead costs are assigned to activity cost
           pools (Step 1).
          Stage 2: Allocates overhead assigned to the activity cost
           pools to products, using cost drivers (Steps 2-4).
       The more complex a product’s manufacturing operation, the
       more activities and cost drivers are likely to be present.
4-7                                                                    LO 1
                                            Illustration 17-2
                                            Activities and related cost drivers
      Illustration 4-5
4-8   Activities and related cost drivers                                         LO 1
                         1         Costing Systems
      Indicate whether the following statements are true or false.
      1. A traditional costing system allocates overhead by means of multiple
         overhead rates.
      2. Activity-based costing allocates overhead costs in a two-stage process.
      3. Direct material and direct labor costs are easier to trace to products
         than overhead.
      4. As manufacturing processes have become more automated, more
         companies have chosen to allocate overhead on the basis of direct
         labor costs.
      5. In activity-based costing, an activity is any event, action, transaction, or
         work sequence that incurs cost when producing a product.
      Solution: 1. False.       2. True.      3. True.       4. False.     5. True.
4-9                                                                                 LO 1
 LEARNING               Apply activity-based costing to a
                  2
 OBJECTIVE              manufacturer.
       Activity-Based Costing
       Involves the following four steps.
        1. Identify and classify the activities involved in the manufacture
            of specific products and assign overhead to cost pools.
        2. Identify the cost driver that has a strong correlation to the
            costs accumulated in each cost pool.
        3. Compute the activity-based overhead rate for each cost pool.
        4. Allocate overhead costs to products, using the overhead
           rates determined for each cost pool.
4-10                                                                       LO 2
       Identify and Classify Activities and Allocate
       Overhead to Cost Pools (Step 1)
       Overhead costs are assigned directly to the appropriate activity
       cost pool.
                                                      Illustration 4-6
                                                      Activity cost pools and
                                                      estimated overhead
4-11                                                                            LO 2
       Identify Cost Drivers (Step 2)
       Cost driver must accurately measure the actual consumption
       of the activity by the various products.
       Illustration 4-6: Cost drivers that Atlas Company identifies and
       their total expected use per activity cost pool.
                                                               Illustration 4-7
4-12                                                                         LO 2
       Compute Activity-Based Overhead Rates
       (Step 3)
       Next, the company computes an activity-based overhead rate
       per cost driver.                                  Illustration 4-8
                                                                Illustration 4-9
4-13                                                                          LO 2
    Allocate Overhead Costs to Products (Step 4)
       In allocating overhead costs, it is necessary to know the
       expected use of cost drivers for each product. Because of its
       low volume and higher number of components, the Ab Coaster
       requires more setups and purchase orders than the Ab Bench.
                                                            Illustration 17-8
Illustration 4-10
Expected use of cost
drivers per product
4-14                                                                        LO 2
   Allocate Overhead Costs to Products (Step 4)
       To allocate overhead costs, Atlas multiplies the activity-based
       overhead rates per cost driver (Ill. 4-9) by the number of cost
       drivers expected to be used per product (Ill. 4-10).
                                                             Illustration 4-11
                                                             Allocation of
                                                             activity cost
                                                             pools
                                                             to products
4-15                                                                         LO 2
   Allocate Overhead Costs to Products (Step 4)
       To allocate overhead costs, Atlas multiplies the activity-based
       overhead rates per cost driver (Ill. 4-9) by the number of cost
       drivers expected to be used per product (Ill. 4-10).
                                                           Illustration 4-11
4-16                                                                           LO 2
       Comparing Unit Costs
                                                                       Illustration 17-10
                                                                       Illustration 4-12
   Likely consequence of differences in assigning overhead.            Comparison of unit
                                                                       product costs
          Overpricing the Ab Bench and possibly losing market
           share to competitors.
          Sacrificing profitability by underpricing the Ab Coaster.
4-17                                                                                    LO 2
                          2         Apply ABC to Manufacturer
       Casey Company has five activity cost pools and two products. It expects to
       produce 200,000 units of its automobile scissors jack and 80,000 units of
       its truck hydraulic jack. Having identified its activity cost pools and the cost
       drivers for each cost pool, Casey Company accumulated the following data
       relative to those activity cost pools and cost drivers.
4-18                                                                                 LO 2
                          2         Apply ABC to Manufacturer
       Casey Company has five activity cost pools and two products. It expects to
       produce 200,000 units of its automobile scissors jack and 80,000 units of
       its truck hydraulic jack. Having identified its activity cost pools and the cost
       drivers for each cost pool, Casey Company accumulated the following data
       relative to those activity cost pools and cost drivers.
       Using the data provided,
         a. Prepare a schedule showing the computations of the activity-based
            overhead rates per cost driver.
         b. Prepare a schedule assigning each activity’s overhead cost to the
            two products.
         c.   Compute the overhead cost per unit for each product.
         d. Comment on the comparative overhead cost per unit.
4-19                                                                                 LO 2
                           2           Apply ABC to Manufacturer
 a. Prepare a schedule showing the computations of the activity-based overhead rates per cost driver.
4-20                                                                                                LO 2
       2   b. Prepare a schedule assigning each activity’s
              overhead cost to the two products.
4-21                                                     LO 2
                        2        Apply ABC to Manufacturer
       c. Compute the overhead cost per unit for each product.
       d. Comment on the comparative overhead cost per unit.
         These data show that the total overhead assigned to 80,000 hydraulic
         jacks exceeds the overhead assigned to 200,000 scissors jacks. The
         overhead cost per hydraulic jack is $34.25. It is only $12.80 per
         scissors jack.
4-22                                                                            LO 2
 LEARNING             Explain the benefits and limitations of
                 3
 OBJECTIVE            activity-based costing.
       ABC has three primary benefits:
        1. More cost pools, therefore more accurate product costing.
        2. Enhanced control over overhead costs.
        3. Better management decisions.
4-23                                                                   LO 3
       The Advantage of Multiple Cost Pools
       Multiple cost pools
           Used instead of one plantwide pool and a single cost driver.
           Numerous activity cost pools with more relevant cost drivers.
             ►   Costs allocated on basis of cost drivers used to produce
                 each product.
4-24                                                                        LO 3
        The Advantage of Multiple Cost Pools
       Illustration 4-13
       A more detailed view of Atlas’s machining activities
4-25                                                          LO 3
       The Advantage of Multiple Cost Pools
       CLASSIFICATION OF ACTIVITY LEVELS
         Unit-           Batch-          Product-    Facility-
         level            level            level      level
           Performed for each unit of production.
             ►   Example: Assembly of cell phones
4-26                                                             LO 3
       The Advantage of Multiple Cost Pools
       CLASSIFICATION OF ACTIVITY LEVELS
         Unit-           Batch-         Product-       Facility-
         level            level           level         level
           Performed every time a company produces another
            batch of a product.
             ►   Example: Batch of ice cream
4-27                                                               LO 3
       The Advantage of Multiple Cost Pools
       CLASSIFICATION OF ACTIVITY LEVELS
         Unit-           Batch-          Product-         Facility-
         level            level            level           level
           Performed every time a company produces a new type
            of product.
             ►   Example: Time spent testing a new drug by a
                 pharmaceutical company
4-28                                                                  LO 3
       The Advantage of Multiple Cost Pools
       CLASSIFICATION OF ACTIVITY LEVELS
         Unit-           Batch-          Product-          Facility-
         level            level            level            level
           Required to support or sustain an entire production
            process.
             ►   Example: A hospital
4-29                                                                   LO 3
Illustration 4-14
Hierarchy of
activity levels
4-30                LO 3
   Advantage of Better Management Decisions
       Activity-based management (ABM), a management tool that
       focuses on reducing costs and improving processes and
       decision-making.
       Managers use ABC via ABM
           for both strategic and operational decisions or perspectives.
           to help managers evaluate employees, departments, and
            business units.
           to establish performance standards, as well as benchmark
            against other companies.
4-31                                                                        LO 3
   Limitations and Knowing When to use ABC
       Limitations
           Expensive to use.
           Arbitrary allocations remain.
       When to Use
        1. Product lines differ in volume and manufacturing complexity.
        2. Product lines are numerous and diverse.
        3. Overhead costs constitute a significant portion of total costs.
        4. Manufacturing process or the number of products has
           changed significantly.
        5. Production or marketing managers are ignoring data.
4-32                                                                         LO 3
                         3        Classify Activity Levels
       Morgan Toy Company manufactures six primary product lines in its
       Morganville plant. As a result of an activity analysis, the accounting
       department has identified eight activity cost pools. Each of the toy
       products is produced in large batches, with the whole plant devoted to one
       product at a time. Classify each of the following activities as either unit-
       level, batch-level, product-level, or facility-level:
       a.   Engineering design                      a.   Product-level
       b.   Machine setup                           b.   Batch-level
       c.   Toy design                              c.   Product-level
       d.   Interviews of prospective employees     d.   Facility-level
       e.   Inspections after each setup            e.   Batch-level
       f. Polishing parts                           f. Unit-level
       g. Assembling parts                          g. Unit-level
       h. Health and safety                         h. Facility-level
4-33                                                                             LO 3
                        4         Apply ABC to Service Company
  (a) Compute the activity-based overhead rates for each pool.
4-34                                                             LO 4
                        4        Apply ABC to Service Company
  (b) Determine the overhead allocated to Job A1027 which has 150 pieces, requires
      200 miles of driving, and 0.75 hours of logistics.
           (150 x $0.70) + (200 x $0.50) + (0.75 x $30) = $227.50
4-35                                                                                 LO 4
 LEARNING                 APPENDIX 4A: Explain just-in-time (JIT)
                    5
 OBJECTIVE                processing.
  . JIT manufacturing is dedicated to having the right amount of materials,
       parts, or products just as they are needed.             Illustration 4A-1
4-36                                                                               LO 5
 LEARNING               APPENDIX 4A: Explain just-in-time (JIT)
                  5
 OBJECTIVE              processing.
       Objective of JIT Processing
           To eliminate all manufacturing inventories.
       Elements of JIT Processing
           Dependable suppliers.
           Multiskilled work force.
           Total quality control system.
4-37                                                              LO 5
 LEARNING               APPENDIX 4A: Explain just-in-time (JIT)
                  5
 OBJECTIVE              processing.
       Benefits of JIT Processing
           Significant reduction or elimination of manufacturing
            inventories.
           Enhanced product quality.
           Reduction or elimination of rework costs and inventory
            storage costs.
           Production cost savings from the improved flow of goods
            through the processes.
4-38                                                                  LO 5
       Copyright
        Copyright © 2015 John Wiley & Sons, Inc. All rights reserved.
        Reproduction or translation of this work beyond that permitted in
        Section 117 of the 1976 United States Copyright Act without the
        express written permission of the copyright owner is unlawful.
        Request for further information should be addressed to the
        Permissions Department, John Wiley & Sons, Inc. The purchaser
        may make back-up copies for his/her own use only and not for
        distribution or resale. The Publisher assumes no responsibility for
        errors, omissions, or damages, caused by the use of these
        programs or from the use of the information contained herein.
4-39