0% found this document useful (0 votes)
320 views52 pages

Mohmand

The Mohmand Dam Hydropower Project in Pakistan will be a 213-meter tall roller compacted concrete dam with an 800 megawatt power generation capacity. Key objectives include flood protection, irrigation, water supply and power generation. Construction began in 2019 and involves complex engineering challenges like excavating two 1.7 kilometer long diversion tunnels through fractured rock and constructing high cut slopes. The project aims to benefit local communities through public welfare initiatives and job opportunities.

Uploaded by

M Tanvir Abbas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
320 views52 pages

Mohmand

The Mohmand Dam Hydropower Project in Pakistan will be a 213-meter tall roller compacted concrete dam with an 800 megawatt power generation capacity. Key objectives include flood protection, irrigation, water supply and power generation. Construction began in 2019 and involves complex engineering challenges like excavating two 1.7 kilometer long diversion tunnels through fractured rock and constructing high cut slopes. The project aims to benefit local communities through public welfare initiatives and job opportunities.

Uploaded by

M Tanvir Abbas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 52

MOHMAND DAM HYDROPOWER PROJECT

DT-2 Tunnel Shuttering


1
Project Background

2
PROJECT BACKGROUND

Reconnaissance Study 1969

Pre-Feasibility Study 1992

JICA Feasibility Study 2000

Tender Design & Tender Documents 2017

Construction Contract Award March 2019

3
Key Project Objectives

4
MULTI-PURPOSE DAM AND HYDROPOWER PROJECT

Power
Generation

Water Supply Development


to Peshawar of Irrigation
City Canals

Agriculture
Flood Development
Mitigation

5
KEY OBJECTIVES
FLOOD PROTECTION
Munda Headworks – 2010 Flood

Munda Headworks - reconstructed

6
PUBLIC WELFARE PROJECTS

Education Institutes Road Infrastructures


Health Institutes

Drinking Water Tree Plantation Employment Opportunities

Benefits to Local Communities and Stakeholders


7
Project Layout and Features

8
9
10
SALIENT FEATURES
Operation Peaking hydropower with re-regulation
Dam height/ Crest length 213 m high with a crest length of 718 m
Type of Dam Concrete Faced Rockfill Dam
Gross / Live Storage 1.293 / 0.676 MAF
Spillway Capacity 27,427 m3/s PMF
Diversion Tunnels 2 Nos. Each 1.7km long & 15m diameter
Power Generation Capacity 800MW from 4 x 200MW Francis Turbines
Cultivable Command Area 18,237 Acres
Right Bank Irrigation System 3.6 Km Tunnel + 11.7km Canal
Left Bank Irrigation System 4.8 Km Tunnel + 12.4 km Canal
11
CFRD DAM & SPILLWAY
Dam & Spillway – looking at
upstream

12
CFRD DAM & SPILLWAY

Dam & Spillway – view


looking downstream
13
Milestones Achieved

14
PROJECT INAUGURATION MAY 02, 2019

15
PROJECT – 1ST CONCRETE
Project Colony – February 2020

16
GROUND BREAKING FOR TUNNELLING WORKS
Main Access Tunnel - May 2020

17
MAIN DIVERSION TUNNEL EXCAVATION START
Diversion Tunnel 1 - August 2020

18
MAIN DIVERSION TUNNEL EXCAVATION START
Diversion Tunnel 2 - October 2020

19
10 BILLION TREE PLANTATION CAMPAIGN
August 2020 – ongoing….

20
The Project Site

21
CONTRACTOR’S FACILITIES

Contractor’s Camp and Office

Crushing Plant 22
PROJECT COLONY

Colony Mosque WAPDA Project Office

Senior Officers Hostel 23


DIVERSION TUNNELS INLETS

24
DIVERSION TUNNELS
Tunnel Excavation Works

25
DIVERSION TUNNELS OUTLETS

26
DIVERSION TUNNELS OUTLETS
Assembly of Tunnel Lining Mobile Shutters

27
DIVERSION TUNNEL OUTLET
Assembly of Tunnel Lining Formwork

28
DIVERSION TUNNEL LINING

First Concrete in Diversion Tunnel -2


February 2022

29
SPILLWAY

Lower Stilling
Basin

Upper Stilling
Basin

Spillway Crest looking 30


SPILLWAY

Spillway Crest Spillway – Lower Basin


180m cut slope
Upper Stilling
Basin

Lower Stilling
Basin

Flow
Spillway – looking upstream from the Right
31
POWER INTAKE

Power Intake – cut


slope with high capacity
post tensioned anchors
32
POWERHOUSE AREA

Switchyard Platform

Powerhouse cut slope

33
POWER INTAKE & DT INLET WORKS
View from Todobo Quarry

Power Intake Project Colony


Works

DT – Inlet
Works

Main Dam fill stockpile -


hardstanding

Haul Road Bailey Bridge 34


Project Challenges

35
PROJECT CHALLENGES
213 m CFRD DAM Situation:
 5th highest CFDR in the World at 213 m
 Seismic area
 17M m3 of rockfill required from local
source
Actions:
 Experienced designers and Contractor
 Detailed investigations and testing of rockfill
materials from local quarry

36
PROJECT CHALLENGES

SPILLWAY
Situation:
 PMF Flood capacity = 27,500 m3
 High head = 215m for PMF to Riverbed level
and 600m long
Actions:
 Double stilling basin arrangement
 Extensive hydraulic model testing

PMF

215m
high

600m long
37
PROJECT CHALLENGES
GEOLOGY
Situation:
 Across the Site – generally, tectonically
deformed Schist with foliations with weak
zones

Actions:
 Exacting site investigation to understand the
geology and geotechnical parameters for the
Project design
 Real-time feedback loop during tunnelling
and surface excavations works to designers

38
PROJECT CHALLENGES

DIVERSION TUNNELS
Situation:
 2 x 17.0m excavated diameter both 1.7km long
 Encountering weaker zones in foliated Schist
Actions:
 Prudent real time interpretation of tunnel face
conditions – with forward drilling to test rock
conditions
 Engineer and Contractor working together at
the tunnel face
Outcome:
 DT-1 header completed - breakthrough Dec
2021
 DT-2 header nearing completion 39
PROJECT CHALLENGES

HIGH CUT SLOPES


Situation:
 High cut slope:
 180m at the Spillway lower stilling basin,
 150m at the Powerhouse
 120m at the Power Intake
 Foliated Schist in seismic area
Actions:
 Heavy slope reinforcement with high capacity
ground anchors
 Real time geological interpretation of each
bench
 Engineer and Contractor working together at
each bench for detailed assessment of support
40
SITE HEALTH AND SAFETY

41
Public Welfare Projects

42
MEDICAL CAMPS

12
43
FREE COMMUNITY TRANSPORT

44
SOLARIZATION OF MOSQUES & SCHOOLS

45
COMMUNITY INFRASTRUCTURE
DEVELOPMENT

Uplift of local communities through construction of schools and rural


roads

46
SPORTS / YOUTH ENGAGEMENT

47
Collaborations of Experience and Capabilities
- Driving the delivery of the Mohmand Dam Hydropower Project

48
PROJECT CONSULTANTS GROUP

MDC
G
In Association with:

49
MOHMAND DAM CONTRACTOR

China Gezhouba Group Co., DESCON Engineering


Ltd, Ltd, Pakistan
China

50
Collaboration delivering the Project

51
Thank You

52

You might also like