MOHMAND DAM HYDROPOWER PROJECT
DT-2 Tunnel Shuttering
1
Project Background
2
PROJECT BACKGROUND
Reconnaissance Study 1969
Pre-Feasibility Study 1992
JICA Feasibility Study 2000
Tender Design & Tender Documents 2017
Construction Contract Award March 2019
3
Key Project Objectives
4
MULTI-PURPOSE DAM AND HYDROPOWER PROJECT
Power
Generation
Water Supply Development
to Peshawar of Irrigation
City Canals
Agriculture
Flood Development
Mitigation
5
KEY OBJECTIVES
FLOOD PROTECTION
Munda Headworks – 2010 Flood
Munda Headworks - reconstructed
6
PUBLIC WELFARE PROJECTS
Education Institutes Road Infrastructures
Health Institutes
Drinking Water Tree Plantation Employment Opportunities
Benefits to Local Communities and Stakeholders
7
Project Layout and Features
8
9
10
SALIENT FEATURES
Operation Peaking hydropower with re-regulation
Dam height/ Crest length 213 m high with a crest length of 718 m
Type of Dam Concrete Faced Rockfill Dam
Gross / Live Storage 1.293 / 0.676 MAF
Spillway Capacity 27,427 m3/s PMF
Diversion Tunnels 2 Nos. Each 1.7km long & 15m diameter
Power Generation Capacity 800MW from 4 x 200MW Francis Turbines
Cultivable Command Area 18,237 Acres
Right Bank Irrigation System 3.6 Km Tunnel + 11.7km Canal
Left Bank Irrigation System 4.8 Km Tunnel + 12.4 km Canal
11
CFRD DAM & SPILLWAY
Dam & Spillway – looking at
upstream
12
CFRD DAM & SPILLWAY
Dam & Spillway – view
looking downstream
13
Milestones Achieved
14
PROJECT INAUGURATION MAY 02, 2019
15
PROJECT – 1ST CONCRETE
Project Colony – February 2020
16
GROUND BREAKING FOR TUNNELLING WORKS
Main Access Tunnel - May 2020
17
MAIN DIVERSION TUNNEL EXCAVATION START
Diversion Tunnel 1 - August 2020
18
MAIN DIVERSION TUNNEL EXCAVATION START
Diversion Tunnel 2 - October 2020
19
10 BILLION TREE PLANTATION CAMPAIGN
August 2020 – ongoing….
20
The Project Site
21
CONTRACTOR’S FACILITIES
Contractor’s Camp and Office
Crushing Plant 22
PROJECT COLONY
Colony Mosque WAPDA Project Office
Senior Officers Hostel 23
DIVERSION TUNNELS INLETS
24
DIVERSION TUNNELS
Tunnel Excavation Works
25
DIVERSION TUNNELS OUTLETS
26
DIVERSION TUNNELS OUTLETS
Assembly of Tunnel Lining Mobile Shutters
27
DIVERSION TUNNEL OUTLET
Assembly of Tunnel Lining Formwork
28
DIVERSION TUNNEL LINING
First Concrete in Diversion Tunnel -2
February 2022
29
SPILLWAY
Lower Stilling
Basin
Upper Stilling
Basin
Spillway Crest looking 30
SPILLWAY
Spillway Crest Spillway – Lower Basin
180m cut slope
Upper Stilling
Basin
Lower Stilling
Basin
Flow
Spillway – looking upstream from the Right
31
POWER INTAKE
Power Intake – cut
slope with high capacity
post tensioned anchors
32
POWERHOUSE AREA
Switchyard Platform
Powerhouse cut slope
33
POWER INTAKE & DT INLET WORKS
View from Todobo Quarry
Power Intake Project Colony
Works
DT – Inlet
Works
Main Dam fill stockpile -
hardstanding
Haul Road Bailey Bridge 34
Project Challenges
35
PROJECT CHALLENGES
213 m CFRD DAM Situation:
5th highest CFDR in the World at 213 m
Seismic area
17M m3 of rockfill required from local
source
Actions:
Experienced designers and Contractor
Detailed investigations and testing of rockfill
materials from local quarry
36
PROJECT CHALLENGES
SPILLWAY
Situation:
PMF Flood capacity = 27,500 m3
High head = 215m for PMF to Riverbed level
and 600m long
Actions:
Double stilling basin arrangement
Extensive hydraulic model testing
PMF
215m
high
600m long
37
PROJECT CHALLENGES
GEOLOGY
Situation:
Across the Site – generally, tectonically
deformed Schist with foliations with weak
zones
Actions:
Exacting site investigation to understand the
geology and geotechnical parameters for the
Project design
Real-time feedback loop during tunnelling
and surface excavations works to designers
38
PROJECT CHALLENGES
DIVERSION TUNNELS
Situation:
2 x 17.0m excavated diameter both 1.7km long
Encountering weaker zones in foliated Schist
Actions:
Prudent real time interpretation of tunnel face
conditions – with forward drilling to test rock
conditions
Engineer and Contractor working together at
the tunnel face
Outcome:
DT-1 header completed - breakthrough Dec
2021
DT-2 header nearing completion 39
PROJECT CHALLENGES
HIGH CUT SLOPES
Situation:
High cut slope:
180m at the Spillway lower stilling basin,
150m at the Powerhouse
120m at the Power Intake
Foliated Schist in seismic area
Actions:
Heavy slope reinforcement with high capacity
ground anchors
Real time geological interpretation of each
bench
Engineer and Contractor working together at
each bench for detailed assessment of support
40
SITE HEALTH AND SAFETY
41
Public Welfare Projects
42
MEDICAL CAMPS
12
43
FREE COMMUNITY TRANSPORT
44
SOLARIZATION OF MOSQUES & SCHOOLS
45
COMMUNITY INFRASTRUCTURE
DEVELOPMENT
Uplift of local communities through construction of schools and rural
roads
46
SPORTS / YOUTH ENGAGEMENT
47
Collaborations of Experience and Capabilities
- Driving the delivery of the Mohmand Dam Hydropower Project
48
PROJECT CONSULTANTS GROUP
MDC
G
In Association with:
49
MOHMAND DAM CONTRACTOR
China Gezhouba Group Co., DESCON Engineering
Ltd, Ltd, Pakistan
China
50
Collaboration delivering the Project
51
Thank You