This thesis examines causes of delays in public building construction projects in Dessie City, Ethiopia. The study aims to identify major delay factors and their impacts. Data was collected through questionnaires distributed to 50 industry professionals, including clients, consultants, and contractors. Preliminary findings show respondents have varying levels of education and experience. Further analysis will assess the magnitude of delays and critical delay factors affecting construction project performance and costs in Dessie City.

Uploaded by

yassin eshetu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
195 views36 pages

For THESIS

This thesis examines causes of delays in public building construction projects in Dessie City, Ethiopia. The study aims to identify major delay factors and their impacts. Data was collected through questionnaires distributed to 50 industry professionals, including clients, consultants, and contractors. Preliminary findings show respondents have varying levels of education and experience. Further analysis will assess the magnitude of delays and critical delay factors affecting construction project performance and costs in Dessie City.

Uploaded by

yassin eshetu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 36

TOSSA College of Economic Development

MSC in Project planning and


Management (PPM)
MSc. THESIS

ASSESMENT OF PUBLIC BUILDING


CONSTRACTION PROJECT WORKS AND DELAYS
IN DESSIES CITY,ETHIOPIA
PREPARED BY :Yassin Eshetu
ADVISOR: Tefera E. (PhD)
Assessment of public building construction project works and delays in dessie city, Ethiopia

Outline
 Introduction
 STATEMENT OF PROBLEME
 OBJECTIVES
 METHODOLOGY
 SCOPE OF THE STUDY
 SIGNIFICANT OF THE STUDY
 Findings
 Conclusion and
 Recommendation
Assessment of public building construction project works and delays in dessie city, Ethiopia

Introduction
• BACK GROUND
 A construction project is commonly acknowledged as
successful, when it is completed on
schedule,
within budget and within the agreed quality, in compliance to
the specifications and to stakeholders
Assessment of public building construction
project works and delays in dessie city, Ethiopia
Con….
 In Ethiopia, the construction industry is the highest recipient of
government budget in terms of government development programs
Consequently, public construction projects consume an average
annual rate of nearly 60% of the government’s capital budget
(MoWUD, 2006).
 In construction, delay could be defined as the time overrun either
beyond completion date specified in a contract, or beyond the date
that the parties agreed upon for delivery of a project.
Assessment of public building construction project works
and delays in dessie city, Ethiopia
RESEARCH AREA
 This study will be conducted in Dessie town.
The road traverse mainly through rolling terrain with above 90% inaccessible
section.
 weinaDega climatic zone , The mean monthly annual rainfall varies from 12mm
to 299mm in the project area.
The main rainy season in the area is from July to October and its average annual
rainfall ranges from 500mm to 1000mm.
the monthly maximum temperature ranges between 23 oC to 30 oC, and the
minimum between 8 oC to 14 oC.
 Currently in this town different construction activities are carried out both
building and road construction.…
Assessment of public building construction
project works and delays in dessie city, Ethiopia
Cont…

Dessie Town
Assessment of public building construction project
works and delays in dessie city, Ethiopia
STATEMENT OF PROBLEME
 Why does this research be conducted
 A construction project is commonly acknowledged as successful, when it is
completed on schedule and within the agreed budget, with the highest quality
and in the safest manner, in accordance with the specifications and to
stakeholders’ satisfaction.
 Construction delay defined as “time over run either beyond completion date
specified in a contract or beyond the date that parties agree upon for delivery of a
project.”
 This research examined the factors that cause delays to building construction project
and determine how critical delay causes are most influential in project performance.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
OBJECTIVES
General objective
 To assess the magnitude of building construction project delay
and its associated factors among construction projects in
Dessie Town, Amhara, Ethiopia,2023
Specific objective
 To assess the magnitude of construction delay of projects at

Dessie town, 2023


• To identify factors associated with construction projects delay in
Assessment of public building construction project
works and delays in dessie city, Ethiopia
METHODOLOGY
Literatures about Constriction delays and Relative Importance Index (RII)
will be reviewed.
 The data were analyzed using descriptive statistics.
The relative importance indices were calculated for each question within
the form using the statistical techniquesthe collected DCP data for the
analysis will substitute into the existing correlations to find the estimated
CBR values.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Cont…
 Study participants consist of 50 individuals from Dessie town
different construction project. From these total study participants 21 of
them were clients and consultants and contractors were 15 and 14
respectively.
 The main aim of choosing this type of population is to be able to get
current and past information from engineers who have participated in
the implementation of construction projects.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
SCOPE OF THE STUDY
 This research focus on the assessment of public building
construction projects works and delay in Dessie town.
 using a combination of quantitative and qualitative methods.
 It was conducted in two stages.
 The first stage was conducted using a quantitative method
through a questionnaire survey
 The second stage of the study was conducted using the
qualitative method using semi-structured interviews.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
SIGNIFICANT OF THE STUDY

 To understand the delays and factors of building social and economic

 To provide how to minimize the delay of projects, overrun cost

 Generally, the result of this study will be provide to achieved the project by
own budget and time without overrun cost or additional time and cost.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Questions and/or Hypothesis
this research will be mainly focused on responding to the
following questions:
• What is the magnitude of construction project delay in Dessie town?
• What are the major causes of construction project delay?
• How much construction projects are affected by overrun cost from delay?
• What are the most critical delay factors in construction?
• What are the impacts of delayed projects?
• What measurements the have used to prevent delay?
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Materials , Methods and Procedures
• Research methods
Reconnaissance of the Area
Sampling and Data Collection
The data were analyzed using descriptive statistics.
 Study participants consist of 50 individuals from Dessie
town different construction project. From these total study
participants 21 of them were clients and consultants and
contractors were 15 and 14 respectively.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• logical steps (procedures)
Literature review
Reconnaissance of the area
Sampling
 distribution of questioner pepper
Collecting sample data
Developing relative equation
Developing thesis pepper
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Findings
• collect relevant data from targeted contractors, Clients/owner,
and consultants through designed questionnaire.
•The questionnaire used in this study has Sixty-one set of questions
which are related to;
cause of delay,
effects of delay and
Mechanisms to minimize delay.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Respondents Characteristics
Questionnaire Collected (#)

Respondent Questionnaire Invalid/No Filled Complete/ Response


Distributed (#) Questionnaire Valid from Total
Response (%)

Clients 21 4 17 28%

Consultant 18 3 15 28%

Contractor 20 2 18 36 %

Total 59 9 50 92%
Assessment of public building construction project
works and delays in dessie city, Ethiopia

Respondents by Educational Background


client

Diploma consultant

contractor

client

First degree consultant

contractor

client

Masters consultant

contractor

0 5 10 15 20
percent
Assessment of public building construction project works
and delays in dessie city, Ethiopia

Work Experience
Work experience Frequency Percent Valid percent

Up to three years 12 24.0 24.0

3-5 years 23 46.0 46.0

Above three years 15 30.0 30.0

Total 50 100.0 100.0


Assessment of public building construction project works
and delays in dessie city, Ethiopia

Respondents by Job Designation


Job Designation

Count Project Quality Project Site Total


Manager Manager Office Engineer Surveyor Supervisor
Engineer

Oganization Owner 0 0 4 0 0 13 17

Contractor 1 1 8 3 3 3 19

Consultant 0 0 7 0 0 6 13

Total 1 1 19 3 3 9 36
Assessment of public building construction project works
and delays in dessie city, Ethiopia

Respondents by Gender
Description Organization Total
Owner Contractor Consultant

Gender Male 4 15 16 35
Female 2 6 7 15
Total 6 21 23 50

male female
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Cause of building projects delay in Ethiopian
Construction Works Corporation
This part of the paper consists of results and discussion of causes
of project delay in building construction project
Each delay causes are assessed from the viewpoint of

Client
Consultants and
Contractors
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Owners related Delay
 Delays in revising and approving design document
 Change orders by owner during construction.
 Delays in approving shop drawing and sample materials
 Slowness decision-making process.
 Poor communication and coordination.
 Conflict between joint- ownership of the project
 Delay to furnish and deliver the site.
 Delay in progress payment.
 Suspension of work by owner.
NB; Delays in revising and approving design document”
identified as the most important causes of delay among all the listed delays
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Consultant Related Delays
Delays in approving major changes in the scope of work.
Unclear and inadequate details in drawings.
Delay in producing design document
Insufficient data collection and survey before design.
Delay in approval of submittals, design drawings, and sample materials,
etc.
Delay in performing inspection and testing
In adequate experience of consultants.
Assessment of public building construction project works
and delays in dessie city, Ethiopia
• Contractors Related Delays
Poor communication and Coordination
Delay in sub - contractor work
Inadequate contractors experience.
Deficiency in planning and scheduling of project
Poor safety conditions on site
Delays due to material delivery
Shortage of equipment
Rework due to errors during construction
Conflicts between contractor and other parties.
Difficulties in financing project
Poor qualification of contractor's staff
Low productivity of labor
Shortage of labors
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Ranking of group causes
No Owner Contractor Consultant Average
Group Cause

Mean RII Rank Mean RII Rank Mean RII Rank Mean RII Rank

1 Owners related Delay 2.77 0.48 7 2.74` 0.38 7 3.10 0.51 7 2.87 0.46
2 Consultant Related Delays 4.13 0.75 2 3.82 0.65 1 4.03 0.73 1 4.00 0.71 1
3 Contractors Related Delays 4.03 0.76 1 3.62 0.58 3 3.74 0.66 5 3.80 0.67 3
4 External Related Delays 3.67 0.65 5 3.31 0.48 3.29 0.54 6 3.41 0.56 6

Grand Mean 3.77 0.66 3.39 0.55 3.65 0.64 3.60 0.62

NB; owner’s group of causes are the most contributing factors to project delay
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Mechanisms to minimize delays in building projects
Managing ineffective planning and scheduling Tools
Managing delay in progress payment by client Tools
Managing change order during construction Tools
Managing poor Qualification, skill and experience of the
contractors’ staff
NB; “Managing ineffective planning and scheduling”is appeared to
have very high impact on minimizing delays in building construction
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• CONCLUSION
From overall results it was found client related delay
that ;
delays in revising and approving design document,
change order by owner during construction
 slowness decision making process
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Cont..
The analysis also resulted top three delay factors which are caused by
consultants which are ;

delay in approval of submittals design


drawing and sample materials
insufficient data collection and survey before design
Assessment of public building construction project
works and delays in dessie city, Ethiopia
Cont…
considered as major delay causes that were caused by
contractors
Rework due to errors during construction
conflicts between contractor and other parties
delay due to material delivery
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Recommendation
Delays are a part of the construction projects, however, they can be
avoided or minimized when their causes are effectively identified and
analyzed
the following points can be recommended as ways to minimize and
control delay in building construction projects.
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• Client Related Recommendations

Engaging closely with both consultants and contractors

All change order demands must be evaluated

Approving any payment issues in time


Assessment of public building construction project
works and delays in dessie city, Ethiopia

•Consultant Related Recommendations


Ensuring proper site investigation
Implementing all design changes
Assessment of public building construction project
works and delays in dessie city, Ethiopia

•Contractor Related Recommendations


Having adequate experience for a required assignment
employ appropriate construction methods
Hiring a qualified and responsible subcontractor
Having a good site manager
Good communication channel
Assessment of public building construction project
works and delays in dessie city, Ethiopia
• External Related Recommendations
Collaborating with all project stakeholders
By doing a proper planning in the design and
execution time
Thank you !!!