ANED P & C Training
ANED P & C Training
Relay Configuration,
Brief Introduction to 1 Coordination and Calibration
Protection
3
3
AGENDA
Time Activities Remarks
LEARNING STYLE 14.00-16.00hrs 5. Protection Schemes in Distribution – 1.5hrs Case study, Simulation
and Demonstration
Virtual Learning via Zoom or Google Meet 6. Relay Configuration, Coordination and
methods
Calibration – 0.5hrs
synchronous platforms.
N
IO
S T
LA
T
EL L
U
V AU
LC
LE F
A
C
5
Did you Know that a detailed fault study Can;
a v e y ou
S of
li o n s
mil
o l la rs?
D
Prevent accident
at work place?
2.
Identify the causes of faults in the
distribution Network
1. 3.
Identify and describe the Perform Fault Calculation
various types of fault in the for different types of faults
distribution network
03
01
Characteristics of faults
Introduction
Causes of Fault,
Effect of fault.
04
02
Necessity of fault calculation
Types of
faults
05
Case study on fault
current calculation
with simulations on
Powerfactory
8
Introduction
.
Distribution substations as a target of study, consists of some elements
like Lines, Bus Bars, Transformers, Outgoing Feeders, and Bus Couplers.
Regardless of the design and the systematic preventive maintenance
procedures instituted, failures due to abnormal or fault conditions do
occur.
Therefore, the system must be protected against flow of heavy short
circuit currents, which can cause permanent damage to major equipment,
by disconnecting the faulty section of system by means of circuit breaker
and protective relaying.
Hence, the need for a reliable detailed fault studies and calculations to
enable proper choice and selection of the protective switchgears.
9
Introduction: Causes of Power System Faults
• Healthy insulation in the equipment is subjected to either
transient over voltages of small time duration due to
switching and lightning strokes, direct or indirect. Failure of
Overvoltages insulation may happen, resulting in very high fault current.
This current may be more than 10 times the rated or nominal
current of the equipment.
Source: EC&M
Broad Categorization of Faults Types
Symmetrical or Asymmetrical or
balanced faults unbalanced
and faults
5. Electricity
Promotion
Markets
15
Per Unit Impedance system
Power system quantities such as voltage, current and impedance are often expressed in
per unit or percent of specified values.
Per unit quantities are calculated as: Actual Value
Per Unit Value
Base Value
S I V Z
Per Unit Values S pu I pu Vpu Z pu
S base I base Vbase Z base
Usually, the nominal apparent power (S) and nominal voltage (V) are taken as the base
values; for power (Sbase) and voltage (Vbase).
The base values for the current (Ibase) and impedance (Zbase) can be calculated based on the
first two base values expressed in percentage
Z actual
Z% 100%..(3)
Z base
Example: Given that a synchronous generator has its nominal voltage as 13.8 kV , instead of
saying the actual voltage is 12.42 kV, we say the voltage is 0.9 p.u. or 90% of the nominal
value. 17
Per unit system 3Ø Circuit
Usually, the 3-phase SB or MVAB and line-to-line VB or kVB are selected
IB and ZB dependent on SB and VB
SB 3VB I B , VB 3I B Z B
IB
SB
, ZB
VB / 3
VB
2
3VB IB SB
Change of Base
When pieces of equipment with
various different ratings are
connected to a system, it is 2
MVAbase ( new) KVbase ( old )
necessary to convert their Z pu ( new) Z pu ( old ) * * 2
..(4)
impedances to a per unit value MVAbase ( old ) KVbase ( new)
expressed on the same base 18
PROCEDURE FOR CALCULATING MAXIMUM
FAULT CURRENT (SHORT CIRCUIT CACULATIONS)
20
Key Formulas for Per Unit System
4 Source Impedance Zp.u when given short-circuit MVA
6 Fault Current
21
Case Study 1: Fault Calculation
Consider the distribution network shown in figure 1.0, meant to service a community in New Town, through a 240mm2,11kV
ACSR three lines conductor with the following parameters:
22
Case Study 1: Fault level Calculation Solution(Case1)
23
Case Study 1: Fault level Calculation Solution(1)
24
Case Study 1: Fault level Calculation Solution(Case2)
25
Case Study 1: Fault level Calculation Solution(2) Power Factory
26
Summary
• Power Distribution networks are subject to failures arising from fault
which cannot be prevented.
• Power system faults tends to damage network equipment
• Fault level studies is necessary in order to determine the magnitude
of fault current for appropriate choice of protection equipment.
27
28
NATIONAL POWER TRAINING INSTITUTE OF NIGERIA
Power System Protection Workshop for Distribution Companies Executives
Instrument Transformers
29
………………….power trainer with a difference
Course Content
1
Introduction
3
Current Transformers
4 Voltage Transformer
30
Introduction .
Current Transformer
3p
Ste
32
32
OPTICAL CURRENT AND VOLTAGE TRANSDUCERS
These are non-Conventional Instrument Transformers
(NCIT) now being used by some utilities in different
parts of the world.
There are multiple parts roughly divided into
conventional and low power instrument transformers.
Benefits :
• Reduced cabling
• Reduced engineering time
• Reduced commissioning time
• Increased reliability
Figure 2.0: Integrated switchgear showing conventional and non-conventional instrument
• Improved safety transformers 33
Current Transformer
The main tasks of current transformers are:
1. To transform currents,
from a high value to a value
easy to handle for relays and
instruments,
2. To insulate the metering
circuit from the primary high
voltage,
3. To provide possibilities of
a standardizing rated
currents of meters and
relays
. 34
Classification Of Current Transformer
Current
Transformers
(CTs)
Electromagnetic Opto-electronic
Rogowski Coil Metering CTs Protective CTs Indoor CTs Outdoor CTs
CTs CTs
35
Classification of CTs(Based On Application)
Protection/Disturbance
Measuring CTs
recording CTS
37
PROTECTIVE CURRENT TRANSFORMERS AS PER IEC
IEC61869-2
Defining a Current Transformers to meet the Composite Error Requirements of a Short Circuit Current under Symmetrical
Steady State Conditions:
These are Protective current transformers without remnant flux limit for which the saturation behaviour in
Class P: the case of asymmetrical short circuit is specified. The standard accuracy limit factors (ALF) are: 5-10-15-
20-30. 5P and 10P are commonly used.
These are Protective current transformers with remnant flux limit for which the saturation behaviour in
Class PR: the case of a symmetrical short circuit is specified.
Defining a Current Transformers by Specifying its Magnetization Characteristic:
These are Protective current transformers of low leakage reactance without remnant flux limit for which
Class PX: knowledge of the excitation characteristic and of the secondary winding resistance, secondary burden
resistance and turns ratio is sufficient to assess its performance in relation to the protective relay system
with which it is to be used.
These are Protective current transformers with remnant flux limit for which knowledge of the excitation
Class PXR: characteristic and of the secondary winding resistance, secondary burden resistance and turns ratio, is
sufficient to assess its performance in relation to the protective relay system with which it is to be used.
38
PROTECTIVE CURRENT TRANSFORMERS AS PER INDIAN
STANDARDS IS 2705
Class PS: The class PS current transformers are of low reactance and their performance is specified in terms of the
Turns ratio, Minimum Knee point voltage (VK) and Maximum Exciting Current.
Vk= K.IS(Rct + Rb )
High-voltage CTs are the oil-filled type. At a system voltage of 400 KV and above
there is a severe insulation problem. CTs for this range of system voltage become extremely expensive.
Their performance is also limited due to the large dimensional separation of the secondary winding from
the primary winding. These problems are overcome using SF6(gas) and clophen (liquid) as insulation, thus
reducing the size and cost of CTs
A new trend is to use opto-electronic CTs and Rogowski coil current sensors to tackle this problem occurring in
Extra High Voltage (EHV) and Ultra High Voltage (UHV) systems. A Rogowski coil and a linear coupler encircle the
EHV conductor.
A signal proportional to the secondary current is generated and transmitted via the communication channel. Light
beem, laser beam and radio frequency are being used to transmit this signal.
40
SELECTION OF CT CORES
Some general guidelines for selecting current transformer cores, for metering and protection purposes, are
given below.
42
Case Study On CT Sizing
43
Case Study On CT Sizing (Solution)
44
Case Study On CT Sizing (Solution)
Note: The performance of a protection function will depend on the quality of the measured current signal.
The protection IEDs normally are designed to permit heavy CT saturation with maintained correct operation.
45
Voltage Transformer .
46
Types Of Voltage Transformers
4p
Ste
47
47
VT Errors
The voltage transformer is normally loaded by an impedance consisting of relays, instruments and, perhaps
most important, the cables.
The induced emf required to achieve the secondary current through the total burden, requires a magnetizing
current which is taken from theprimary side voltage. This magnetizing current introduces errors in the
voltage transformer.
Ratio Error (Voltage Error)
Phase Angle Error The phase difference between the primary voltage and the reversed secondary phasors.
In order to keep the overall error within the specified limits of accuracy, the winding must be
designed to have:
(i) the internal resistance and reactance to an appropriate magnitude, and
(ii) mininum magnetizing and loss components of the exciting current required by the core.
48
SELECTION OF VTs
Some general guidelines for selecting Voltage transformer cores, for metering and protection purposes, are
given according to IEC 61869-3
Accuracy Class
Rated Output Accuracy Class (Protection)
(Metering)
• With the exception of
• The standard values of rated • The standard accuracy class residual voltage windings,
output at a power factor of for single-phase inductive PVTs shall be assigned same
0.8 lagging are: measuring VT are: measuring accuracy class.
• 10, 25, 50, 100VA 0.1,0.2,0.5, 1.0,3.0 • The standard accuracy
classes for protective voltage
transformers are 3P and 6P.
• The accuracy class for a
Limits of voltage error and phase displacement for measuring voltage transformers residual voltage winding shall
be 6P or better
Limits of voltage error and phase displacement for protective voltage transformers
49
SELECTION OF CVTs
Some general guidelines for selecting Voltage transformer cores, for metering and protection purposes, are
given according to IEC 61869-3
Accuracy Class
Rated Output Accuracy Class (Protection)
• The standard values of rated
(Metering)
• With the exception of
output at a power factor of • The standard accuracy class residual voltage windings,
0.8 lagging are: for single-phase inductive PVTs shall be assigned same
• 10, 25, 50, 100VA measuring VT are: 0.2,0.5, measuring accuracy class.
• Where accuracy is specified 1.0,3.0 • The standard accuracy
from 25% to 100% of rated classes for protective voltage
burden. transformers are 3P and 6P.
• The accuracy class for a
residual voltage winding shall
Limits of voltage error and phase displacement for measuring capacitive voltage transformers
be 3P or 6P
50
VOLTAGE TRANSFORMERS WITH SEVERAL
SECONDARY WINDINGS
Where the transformer has two or more separate secondary windings, one of measurement
and the others for protection, having the same or different transformation ratios, they shall
respectively comply requirements as laid out for respective type of voltage transformer in the
standard.
52
FERRO-RESONANCE
53
54
Basic Protection Scheme In distribution Network
55
Distribution System .
56
Types of
Feeders Radial Parallel
Ring Main
A loop formation
for power supply
and most reliable
.
57
Protection Schemes in Distribution Network
1 Fuse Protection
Differential Protection
4
5 Over-volatge Protection
58
Fuse Protection
.
Fuses
Semi-enclosed Totally
Drop-out
or rewireable Enclosed or
Fuse
type Cartridge type
60
Important Terms
• Is the nominal rated current in Amps
marked on the fuse body that the fuse
Current rating will carry continuously without
deteriorating
The approximate value for fusing current of a round wire is given as:
where : I = k √d3
I = fusing current
k = Preece constant depending upon the material of the wire(K for copper is 10244)
d = diameter of the wire in inches.
62
Important Terms
For semi enclosed or rewire-able fuse which employs copper wire as the fuse element, fusing
factor is equal to 1.9 - 2.0
For the standard duty cartridge fuses, the fusing factor is equal to 1.2 -1.45.
Breaking capacity: the breaking capacity is the maximum current that can be safely
interrupted by the fuse. Some fuse are designated as high rupture capacity (HRC).
Voltage rating: this indicates the maximum circuit voltage in which the fuse can be used.
63
Case Study
Q1. What will be the fuse rating if a 500KVA, 11/0.415KV transformer is to be fused with HRC fuse & D-fuse respectively?
64
Case Study(Solution)
65
Case Study 2
66
67
Overcurrent Protection with Relays
.
68
TIME-CURRENT CHARACTERISTICS
A definite-time overcurrent relay operates
Definite-time Overcurrent after a predetermined time when the current
Relay(51) exceeds its pick-up value.
The operating time is constant, irrespective of
the magnitude of the current above the pick-
up value. See Figure 4a.
Instantaneous Overcurrent An instantaneous relay operates in a definite Figure 4a.: Definite time characteristics
Relay(50) time when the current exceeds its pick-up
value.
The operating time is constant, irrespective of
the magnitude of the current.
There is no intentional time-delay. It operates
in less than 0.1s. See figure 4b.
69
Figure 4b.: Instanteneous time characteristics
TIME-CURRENT CHARACTERISTICS
An inverse-time overcurrent relay operates
Inverse-time Over-current when the current exceeds its pick-up value.
Relay(51) The operating time depends on the magnitude
of the operating current.
The operating time decreases as the current
increases. See figure 4c.
Figure 4c.: inverse time characteristics
70
Important Terms In Relay Setting
Current Setting • The current above which an overcurrent relay should operate.
• The plug-setting (current-setting) can either be given directly in amperes or
(Plug setting) indirectly as percentages of the rated current.
Plug setting • The actual r.m.s. current flowing in the relay expressed as a multiple of the
setting current (pickup current)
Multiplier(PSM)
setting(TMS)
71
Non-directional and Directional Application of OC Relays
Radial Feeder
Radial feeders are easily protected from overcurrent fault by non-directional definite time relays or inverse time relays.
Time grading is used such that the relay nearest to the end of the line has the minimum time setting while the time setting
of other relays increases successively toward the source has shown in the figure 5.0
Parallel Feeder
In an event of a fault on a parallel feeder, only the faulted feeder is isolated leaving the healthy feeder. This is achieved with
directional over current relay(67) with a grading of the time setting for selective tripping.
Unlike non-directional OC relays, directional OC relays requires a voltage input for polarization.
Clockwise: B – P- A coordinated
Anti-clockwise: A- Q-B coordinated
Clockwise: A – B – C – D- A
Anti-Clockwise: A – D – C – B - A
50/51ABC-N
C IA=IF
IA T
A A
IB
B B
IC IB=0
C C
IN IC=0
In Ia
50/51 N C B A
(Low Impedance)
5. 4. The effect of
6.
The possible occurrence magnetizing inrush during
CT saturation initial energization
of overfluxing.
7. Tap-changing. CT polarity
79
Percentage Differential Relay
To avoid unwanted relays operation under the above conditions a
"Percentage Bias" differential relays is used.
Percentage differential relay has an operating coil (No) and two
restraining coil (Nr).
In the scheme, the relay operates when the magnitude of the
secondary operate current, ĪOP = Ī1 + Ī2, is larger than a given
proportion of the secondary restraint current, IRT.
For this particular scheme, the restraint current is chosen to be k.IRT
= k.(|Ī1| + |Ī2|)/2.
The proportionality constant, k (sometimes called the slope), may
be adjustable and have typical values from 0.1 to 0.8 (or 10 percent
to 80 percent).
Bias is a fixed "percentage“ of the ratio of the differential
operating current to the average restraining current
In other words, % bias can be define as the ratio between the
number of turns of the restrain coil (Nr) to the number of turns of
the operating coil (NO) (i.e. %bias = Nr/No = K)
80
Operating Characteristic of a Percentage Differential
relay
Differential
Current
81
Operating Characteristic of a Percentage Differential
relay(Cont’d)
The normal maximum setting for slope 1 is the cumulative rated error of the CTs. For instance, if two
CTs have a maximum error of 10% each, the slope would be set at 20%.
Any value below the 20% slope, is in the restraint region while any value above the 20% slope, is in
the operating region.
To provide greater stability under large external fault conditions, differential element utilizes a steeper
slope beyond the breakpoint, resulting in a dual slope percentage differential characteristic.
However, if the fault current will generate a voltage that is less than or equal to half of the knee point
voltage of the CTs, the common practice is to reduce the CTs rated error by half.
Therefore, the CT maximum error would be 5% each for a 10% rated error CTs and the slope setting
will now be 10%. This practice provides greater sensitivity for low-level faults.
The K1 slope setting is further complicated by the existence of On-load tap changer of the power
transformer which creates an imbalance in the secondary outputs of the differential zone CTs. 82
Operating Characteristic of a Percentage Differential
relay(Cont’d)
This imbalance that can occur from tap changer operation needs to be determined for maximum
stability of the differential scheme.
Thus, since CT ratios are fixed and there is known CT error, the spill current which will be equivalent
to the maximum current on the HV side can be determined.
Therefore, the ratio of maximum spill current to the restraint current for the maximum tap changer
deviation gives the required slope setting. K1 = 20% slope of CT error
K2 = 80 - 100% slope of CT saturation
Differential
Differential
Current
Current
K2
I1 - I 2
I1 - I 2 20% slope of CT error
K1 Breakpoint
Consequently, there are two (2) options or methods that can be used to set K1 slope of a
% differential protection:
1. Cumulative maximum error method.
2. The ratio of maximum spill current to the restraint current for the maximum tap
changer deviation.
84
Case Study
A 30/40MVA, 132/33KV transformer in Benin T/S has the following data available on the name plate:
VHV = 112200V @ tap 17
CTRHV = 200/1; 5P20
CTRLV = 1200/1; 5P20
Determine the expected K1 and K2 settings of your slope for the %bias differential protection of the transformer ?
Solution Where :
Given parameters VMax = Maximum voltage @ HV side of the transformer
Vmax = 112200V @tap 17 VNom = Nominal voltage @ LV side of the transformer
Vnom = 33000V @ nominal tap of LV side CTRHV = CT Ratio @ HV side of the transformer
CTRHV = 200/1A; 5P20 CTRLV = CT Ratio @ LV side of the transformer
CTRLV = 1200/1; 5P20 CTeHV = CT error @ HV side of the transformer
CTeHV = 5% CTeLV = CT error @ LV side of the transformer
CTeLV = 5% IeHV = Spill current @ HV side of the transformer
IOp = Operating current
IeLV = Spill current @ LV side of the transformer
85
IRes = Restraint current
Case Study Cont’d
86
Overvoltage Relay Protection(59)
This is a protection against system Over-voltages on the feeder, lines ,Transformer and generators.
This might be as a result of sudden load throw off, AVR malfunctioning, Power transformer tap failure,
lightning strike etc.
It will have 2 stages:
Stage-I:
Setting: 110%
Time delay: 5 Sec.
Stage –II
Setting: 140%
Time delay: Instantaneous.
87
IMPORTANT TRENDS IN PROTECTION SYSTEMS
• Many manufacturers of numerical protection relays have provided the
ability to implement different relay settings on the same relay and to be
selected by remote means.
Use of Nested Settings • This functionality is little used and yet provides the ability to re-protect the
affected network after a circuit reconfiguration or in different operating
and Custom Curves conditions of distributed Energy sources (DERs) like wind speed or solar
insolation.
• This involves the use of real-time adaptive protection curves that could
adapt to different network conditions. E.g. to manage wind farms in a
micro-grid application.
Adaptive Protection • To keep generation connected even during a fault condition would require
protection to “hold-off” while fault-ride through and other network
actions are tried before disconnection of the generation.
88
IMPORTANT TRENDS IN PROTECTION SYSTEMS
• This involves the use of real time thermal rating of transmission lines
to avoid unnecessary costly network reinforcement and add extra
capacity to the DER project especially during installation of a new
Dynamic Thermal DER .
• The line thermal rating can be calculated dynamically in real time from
Protection the local weather measurements such as wind speed and ambient
temperature to co-ordinate allowed generation automatically.
89
DC AUXILIARY SUPPLY SYSTEMS
All protection schemes designed to prevent or (Tripping Units)
minimize damage to equipment requires an
actuating signal. This signal can be an alternating
current(A.C) or a direct current (D.C.) signal.
Battery bank with a matching charger (rectifier) are
the inseparable pair which are installed for a
healthy d.c. system performance.
The charger provides d.c. to the standing load and
at the same time provides trickle charge or boost
charge to the battery bank depending on the state-
of-charge of the batteries in the bank.
The battery bank supplies the load during
emergency or loss of output from the charger.
It is safer to shut down the station if the battery
bank output is not available because without d.c.
there is no protection for the bulk of the
equipment/apparatus in service in the station.
90
DC AUXILIARY SUPPLY SYSTEMS
(Tripping Units)
Auxiliary D.C. supply has standard voltage ratings of 24V, 30V, 36V, 48V, 50V, 60V, 72V, 110V, 220V and
250V.
The ampere ratings of the charges are usually 3A, 6A, 10A, 20A, 30A, 40A , 50A etc.
In most 11KV, 33KV and 132KV substations, voltage rating of 110V DC (2.2V per cell) are installed and is
used for:
Tripping and closing coil of circuit breakers
Station Control Board (SCB). e.g. the Relay master tripping board.
A ground fault relay is installed to protect the D. C. circuits from ground fault, which usually flags whenever there is a ground
fault within any of the poles of the D.C circuits.
91
Factors To Consider in Sizing of DC Supply unit
92
Battery Capacity
The capacity (Cn ) of a battery refers to the amount of amperage that can be drawn until the battery is fully
discharged for a given period of time at a giving initial cell temperature while maintaining voltage above a given
minimum level. The unit is ampere-hour(Ah)
93
THE CHARGER
Battery chargers in use at all distribution stations convert AC to
DC at a suitable voltage for battery charging.
Station batteries primarily have a stand-by function. They are
“floated” across the battery charger which will supply the
normal dc load. The battery must supply all of the load
whenever the charger is out of service.
The dc output of the Charger, the battery and the load are all
connected in parallel.
The charger should maintain a voltage of 2.037 volts per cell,
for example 110 volts in the case of 54 cell battery
94
TYPES OF CHARGER
Automatic constant
Two-rate charger
Potential Charger
This is the type of charger that is The simplest type is a trickle charger
practically specified for all substation with two rates (low and high rates).
It has a built-in control circuit which A series resistor is partially shorted out
detects any variation in the charging to switch from the low rate to higher
voltage due to varying load rate
Supplies substantially constant voltage The transfer from high to low rate is
to the battery for maximum cell life usually controlled by a voltage relay
95
TYPES OF BATTERY CHARGE
96
Classification of Batteries(Based on Technology)
97
Case Study Battery Sizing
A switchboard consists of 20 circuit breakers. Each circuit breaker has two indicator lamps each taking 1 amp
continuously, a tripping solenoid taking 5 amps for one second, and a spring charging motor for reclosing
which takes 3 amps for 30 seconds. The battery needs to supply current for 4 hours when a mains failure
occurs.
Solution
98
Case Study Battery Sizing Solution
Charger
99
CHARGER MAINTENANCE
The following maintenance procedures are to be carried out on a D.C unit (i.e. the charger):
1. Periodic check of d.c. voltage output;
2. Panel cleaning and removal of dirt/cobwebs;
3. Check for Charge retention ability;
4. Replace ruptured fuses.
100
SPECIFIC GRAVITY & SOC OF A BATTERY
Specific Gravity Values
The specific gravity of the electrolyte to a large extent
determines the status of the cells.
The values of the specific gravity when the cell is fully
charged is 1.22± 0.1 at a temperature of 77 F and
State-of –Charge Values
1.18 when discharged.
The specific gravity is measured with a hydrometer.
During charging, the density of the electrolyte
increases due to evaporation of water.
101
FACTORS AFFECTING BATTERY LIFE
• Gas formation which will tend to scrub the active materials from the
plates
OVERCHARGING • lower the water level
Leads to: • plate buckling and warping which may result in damage to the
separators
• Corrosion of the positive plates
102
Maintenance of Battery Bank
Checks of battery casing for cracks.
The most important aspect of battery maintenance is the addition of distilled water to correct electrolyte
level.
Scheduled checks(daily) of electrolyte’s specific gravity, voltage levels, cell voltage, etc. should be noted and
recorded in the battery maintenance report sheet.
Battery cleaning(with sand paper), greasing of terminals and connections should be done every month.
Battery room should always be kept clean and properly ventilated.
Bring old batteries to recycling; never dispose of them with normal waste or by leaving them outside
(in nature).
103
104
NATIONAL POWER TRAINING INSTITUTE OF NIGERIA
………………….power trainer with a difference
Power System Protection Workshop for Distribution Companies Executives
Relay Coordination
105
What Can relay coordination do for you?
106
Learning Outcomes
By the end of this workshop, you should be able to:
CONCEPT
1. 2. 3.
Explain relay coordination Design and Implement relay
PROPOSAL
Coordination
1 2 3
Procedure of
Why relay Types of Relay relay
Coordination? Coordination Coordination
4 5
108
Relay Coordination
Power Transformer
Figure 1.0 Relay co-ordination network
109
Why co-ordination?
110
When is Coordination Required?
Relay setting Coordination is require under the following Circumstances:
111
3. A combination
2. Time graded of time and
protection current grading
protection.
4. Time in
relation to
1.Current graded
thermal
protection
Relay Co- capability of the
equipment.
ordination
Methods
112
Current Graded Systems 630A
600A
(E q uiva le nt
H V C urre nts )
F a ult M a x . 1 3 1 0 0 A 8800A 2900A 1200A
c urre nt M in. 6 8 5 0 A 5400A 2400A 1100A E
MV
630A (Equivalent L o a d
This principle is based on the fact R e la y a t 'A ' s e t to Fault Max. 13100A
F1
8800A
F2
2900A 1200A 600A HV
F
Currents)
o p e ra te fo r m a x . fa ult 8 8 0 0 A
that the fault current varies with c urre nt a t re m o te ecurrent
nd Min. 6850A 5400A 2400A 1100A E
MV
the position of the fault because of A R A D IA L
Relay at 'A' setDtoIS T R IB U T IO N
BF1 C D Load
F2 F
the difference in impedance values operate for m ax. fault
current at rem ote end
SYST EM
8800A
towards the source. C urrents F1 and F2 m ay be sim ilar - loss of discrim ination
For m inim um infeed A - B m ay be unprotected
This current grading is achieved by N O TEFigure 2a,2 b.0 Current grading method D C B A
: M ax.AIM
fault- Protection
at S /S tn.co-ordinated to ensure
E < m in. fault minimum
current betwunfaulted
een D -E load is t
Amps
disconnected
high set instanteneous over current
Challenge: F1 and F2 may have the same
relays. Unreliable Scheme
valueCurrents
leading toF2loss
F1 and ofsimilar
may be discrimination
- loss of discrimination
Since their selectivity is based solely For minimum infeed A - B may be unprotected
on the magnitude of the current,
NOTE: Max. fault at S/Stn. E < min. fault current between D-E
there must be a substantial Amps
114
Time and Current Graded Systems
In this relays the time of operation
is inversely proportional to the fault
Operating Time
current level and the actual T i m e M u l ti p l i e r = 1 .0
characteristics is a function of both
time and current settings.
The most widely used is the IDMT 10s
115
Inverse Definite Minimum Time Characteristics
0.14
t 0.02
T .M .S
PSM I
1
IS
116
Co-ordination Procedure
• A single line diagram of the power system,
• The impedance of transformers, feeders, motors etc.
in ohms, or in p.u. or % ohms,
• The maximum peak load current in feeders and full
load current of transformers etc, with permissible
Information required overloads,
to achieve proper co-
ordination are: • The maximum and minimum values of short circuit
currents that are expected to flow,
• The type and rating of the protective devices and
their associated protective transformers,
• Performance curves or characteristic curves of relays
and associated protective transformers.
117
Protection Co-ordination Principles
1. Whenever and wherever possible, use relays with the same
characteristics in series with each other.
2. Set the relay farthest from the source at the minimum current settings.
3. For succeeding relays approaching the source, increase the current setting or retain
the same current setting. (i.e that is the primary current required to operate the relay
in front is always equal to or less than the primary current required to operate the relay
behind it. )
4.Instantaneous units should be set so they do not trip for fault
levels equal or lower to those at busbars or elements protected by
downstream instantaneous relays.
Decrease in the level of short circuit • Oversizing the inverter of the PV system to increase the fault current
current resulting from Integration of • Performing network studies and reconfiguration of relays on the
variable renewable energy sources network.
120
Case Study 1.0: Relay Coordination
Question
The figure 5.0 above is a network having indiscriminate tripping at different stations. As a protection Engineer,
design a coordination scheme for the network;
1. Determine the relay settings at various stations. Assume standard inverse characteristics of IDMT numerical
relays with coordination time interval of 0.4s.
2. Validate your results using DigSilent Power Factory PSAT software 121
Case Study 1.0: Relay Coordination(Solution)
122
Case Study 1.0: Relay Coordination(Solution)
123
Case Study 1.0: Relay Coordination(Solution)
124
Case Study 1.0: Relay Coordination(Solution)
125
Case Study 1.0: Relay Coordination(Solution)
126
Case Study 1.0: Relay Coordination(Solution PF)
Table 1.1: Bus Data of the six power system network Table 1.2: External Grid data
Bus name Bus Voltage (KV) System Type Phase Technology Description Voltage(KV Bus Type Active Voltage set-point in p.u
Bus SL 33 AC ABC ) Power(MW)
Bus A 11 AC ABC External Grid 33 PV 2 1.0
Bus B 11 AC ABC
Bus C 11 AC ABC Table 1.3: Transformer Data
Bus D 11 AC ABC Description Voltage(KV Short circuit Copper losses(kW) Rated Power(MVA)
Bus F 0.415 AC ABC ) Voltage(%)
Transformer 1 33/11 7 7.5 10
Transformer 2 33/11 7 7.5 10
Table 1.4a Transmission Line Data Transformer 3 11/0.4 4 3 1
Description Rated Rated Line Type Resistance(2 Reactance
voltage(k Current length(km) 0o) (20o) Table 1.5 load Data
V) (kA) (ohms/km) Description Voltage Technology Reactive Power Mvar Power Factor
(ohms/km) (pu)
Line 1 11 0.37 10 OHL 0.3621 0.471 General load 1.0 3PH-PH-E 0.7 0.9
Line 2 11 0.37 10 OHL 0.3621 0.471 Table 1.6: instrument transformer settings of the six bus power system
Line 3 11 0.37 10 OHL 0.3621 0.471 Protection Location Branch Manufacturer Model CT Slot Ratio
Device [pri.A/sec.A]
Table 1.4b Transmission Line Data(same for line 1 to 3)
Descriptio Susceptance Susceptan Conductor Maximum
n B uS/km ce B0 B Material Operating 1 Relay A Bus A Line 1 Areva P12x CT1 Ct-3P 400A/5A
uS/km Temp. deg C Ct-
Line 1 0.3621 1.817 3.582 1.324 Aluminium 80 CT1 E/N 400A/5A
2 Relay B Bus B Line2 Areva P12x CT2 Ct-3P 300A/5A
Ct-
CT2 E/N 300A/5A
3 Relay C Bus C Line3 Areva P12x CT3 Ct-3P 200A/5A
Ct-
CT3 E/N 200A/5A
4 Relay D Bus D TF3 Areva P12x CT4 Ct-3P 100A/5A
Ct- 127
CT4 E/N 100A/5A
Table 1.7: The Micom Areva overcurrent relay settings of the six bus power system(P123)
Protection Location Branch Manu Model Stage Current Current Current Time Charac Direc
Device facturer (Phase) [pri.A] [sec.A] [p.u.] teristic tional
IEC Standard
2 Relay A Bus A Line 1 Areva P12x I> 390.40 4.88 4.88 0.17 Inverse None
Definite time
I>> 1600.00 20.00 20.00 0.03 (51) None
IEC Standard
3 Relay B Bus B Line2 Areva P12x I> 225.00 3.75 3.75 0.17 Inverse None
Definite time
I>> 900.00 15.00 15.00 0.03 (51) None
IEC Standard
4 Relay C Bus C Line3 Areva P12x I> 130.00 3.25 3.25 0.22 Inverse None
Definite time
I>> 520.00 13.00 13.00 0.03 (51) None
IEC Standard
5 Relay D Bus D TF3 Areva P12x I> 50.00 2.50 2.50 0.35 Inverse None
Definite time
I>> 200.00 10.00 10.00 0.03 (51) None
3-phase Min., Fault Fuse Relay Tripping Time(s)
balanced Current(A) Tripping
fault Time(s)
location
Tripping Times F1(t) RD (t>)/(t>>) RC(t>)/(t>>) RB(t>)/(t>>) RA(t>)/(t>>)
obtained
Bus F 7330 1.352 1.439/0.035 2.177/9999 7.224/9999 9999/9999
128
Bus D 320 99999 9999/9999 1.732/9999 3.465/9999 9999/9999
Time overcurrent Plot
129
130
References
1. Instruction Manual for Schweitzer SEL-787-0 “Current Differential and Overcurrent Relay” (Manual P/N: SEL-
787-0 dated 20050919).
2. ANSI / IEEEC37.91, “Guide for Protective Relay Applications for Power Transformers”
3. Tracy Toups and Prashanna Bhattarai, “Microprocessor Based Differential Relaying ” Lab procedure, 2014.
4. Chapman, S. J. (2012). “Electric Machine Fundamentals Fifth Edition”. New York, NY: McGraw Hill.
5. Edmund O. Schweitzer, I. a. (2010). “Modern Solutions for Protection, Control, and Monitoring of Electric Power
Systems”. Pullman, WA 99163: Schweitzer Engineering Laboratories, INC.
6. Turan Gonen, “Electrical Power Distribution System Engineering”, (Second Edition), CRC Press, Taylor & Francis
Group, Boca Raton, FL, 2008.
7. Central Board of IrrIgatIon & Power research report(2018). Manual on Power System Protection. Malcha Marg,
Chanakyapuri, New Delhi – 110021
131