RRU 5516 Modernization

The document outlines the responsibilities and processes for the modernization of Dual Band RRU5516, detailing key tasks such as verification, dismantling, quality control, and equipment management. It includes three scenarios for RRU modernization, specifying the steps for replacing existing RRUs with new models, managing cables, and ensuring quality control. The document emphasizes the importance of proper planning and execution to ensure a smooth project flow.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views7 pages

RRU 5516 Modernization

The document outlines the responsibilities and processes for the modernization of Dual Band RRU5516, detailing key tasks such as verification, dismantling, quality control, and equipment management. It includes three scenarios for RRU modernization, specifying the steps for replacing existing RRUs with new models, managing cables, and ensuring quality control. The document emphasizes the importance of proper planning and execution to ensure a smooth project flow.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Dual Band RRU5516 Modernization

Department name: Delivery Management Department

Date: 18-Apr-25

Security Level:
Contents
1. Key Responsibilities
2. Process Flow
3. 3 Scenarios of RRU Modernization
Key Responsibilities

1. Pre-Activity Verification: Supplier to verify Purchase Order (PO) and Purchase Request (PR) before
planning the activity.
2. Dismantling and Packing: Supplier to dismantle and pack RRUs with care, ensuring no damage
during transportation and inform if any thing missing or damaged before dismantling. RRU Power
connector , SFPs , Assembly will be packed along with RRU in same box .
3. Quality Control: Supplier to perform Dis-QC (Dismantling Quality Control) and upload item/serial
numbers with model pictures along with packing short video on site
4. Verification and Go-Ahead: IMs (Installation Managers) to verify existing RRU condition and ECRF
Activation status before giving the go-ahead to the supplier.
5. Power Cable Management: Power cables for RRU5916 will be reused, while others will be replaced.
For sites with existing RRUs in GL MODE, the same configuration will be followed for RRU MOD.

3 Huawei Proprietary - Restricted Distribution


Process Flow
• 1. Supplier verifies PO/PR and plans the activity.
• 2. IMs verify RRU condition and provide the go-ahead.
• 3. Supplier dismantles and packs RRUs, performing Dis-QC.
• 4. Supplier will dismantled jumpers from Antenna end and cut from RRU end .
• 4. Supplier shares Advanced Shipping Notification (ASN) within 24 hours with concerned IM.
• 5. Equipment is submitted to customer warehouses after approval.

• if any Mismatch Between ASN and MMAF


• Note : Supplier RT PO Line accepting will be Hold and deduction shall be imposed equivalent to
loss/damage.

This scope of work outlines the responsibilities and processes for the supplier to ensure a smooth and
efficient project execution.

4 Huawei Proprietary - Restricted Distribution


3 Scenarios of RRU Modernization

• For Case 01 where only 1800 is available


1. Existing RRUs(4T4R) Will be Replaced with new RRU5516 .
2. New Jumpers will be installed .
3. Existing RRU Power cable will be Re-used.
4. Existing Multimode CPRI will be replaced with Single Mode CPRI and OLD will be dismantled .
5. SFP will be replaced and OLD SFP will be dismantled and Packed with RRU .
6. Standard Breaker will be added by supplier Min 100 A if Required .
7. Existing DCDU 16-D will Re-Used .

5 Huawei Proprietary - Restricted Distribution


• For Case 02 where 2* 2T2R RRU are available(L1800 ).
1. Existing 2* 2T2R RRUs will be replaced with new RRU5516 .
2. New Jumpers will be installed .
3. New power cable will be installed and OLD will be dismantled as per MMAF .
4. Existing Multimode CPRI will be replaced with Single Mode CPRI and OLD will be dismantled.
5. SFP will be replaced and OLD SFP will be dismantled and Packed with RRU .
6. Standard Breaker will be added by supplier Min 100 A if Required .
7. New DCDU 16-D will be processed and installed on site .

• For Case 03 where 2* 2T2R L1800 & 1*2T2R L2100 RRU replaced with RRU5516 .

1. Existing 3* 2T2R RRUs(L1800 & L2100 both) will be replaced with new RRU5516 .
2. New Jumpers will be installed .
3. New power cable will be installed and OLD will be dismantled as per MMAF .
4. Existing Multimode CPRI will be replaced with Single Mode CPRI, OLD will be dismantled.
5. SFP will be replaced and OLD SFP will be dismantled and Packed with RRU .
6. Standard Breaker will be added by supplier Min 100 A if Required .
7. New DCDU 16-D will be processed and installed on site .

6 Huawei Proprietary - Restricted Distribution


Thank you. Bring digital to every person, home and
organization for a fully connected,
intelligent world.

Copyright©2018 Huawei Technologies Co., Ltd.


All Rights Reserved.

The information in this document may contain predictive


statements including, without limitation, statements regarding
the future financial and operating results, future product
portfolio, new technology, etc. There are a number of factors that
could cause actual results and developments to differ materially
from those expressed or implied in the predictive statements.
Therefore, such information is provided for reference purpose
only and constitutes neither an offer nor an acceptance. Huawei
may change the information at any time without notice.