Se Unit 5
Se Unit 5
- Introduction
- Risk identification
- Risk projection (estimation)
-Risk Refinement
- Risk mitigation, monitoring, and
management
Project Risks
What can go wrong?
What is the likelihood?
What will the damage be?
What can we do about it?
What Is Software Risk?
• Risk is an expectation of loss, a potential problem
that may or may not occur in the future.
• It is generally caused due to lack of information,
control or time.
• A possibility of suffering from loss in software
development process is called a software risk.
• Loss can be anything, increase in production cost,
development of poor quality software, not being
able to complete the project on time.
Types of software risks
• Software risk exists because the future is
uncertain and there are many known and
unknown things that cannot be incorporated
in the project plan.
• A software risk can be of two types
– (1) internal risks that are within the control of
the project manager and
– (2) external risks that are beyond the control of
project manager.
Definition of Risk
• A risk is a potential problem – it might happen, and it
might not
• Conceptual definition of risk
– Risk concerns future happenings
– Risk involves change in mind, opinion, actions, places,
etc.
– Risk involves choice and the uncertainty that choice
entails
• Two characteristics of risk
– Uncertainty – the risk may or may not happen; that is,
there are no 100% risks (those, instead, are called
constraints)
– Loss – the risk becomes a reality, and unwanted
consequences or losses occur
Risk Categorization – Approach #1
• Project risks
– They threaten the project plan
– If they become real, it is likely that the project schedule will slip and that
costs will increase
• Technical risks
– They threaten the quality and timeliness of the software to be produced
– If they become real, implementation may become difficult or impossible
• Business risks
– They threaten the viability of the software to be built
– If they become real, they jeopardize the project or the product
Reduce the
Reduce the probability
Identify the Risk
impact of or
risk monitoring
risk likelihood
of risk
Reactive vs. Proactive
Risk Strategies
3-Customer risks associated with sophistication of the customer and the developer's ability to
characteristics communicate with the customer in a timely manner
4-Process risks associated with the degree to which the software process has been defined and
definition is followed
5-Development risks associated with availability and quality of the tools to be used to build the
environment project
6-Technology to risks associated with complexity of the system to be built and the "newness" of the
be built technology in the system
7-Staff size and risks associated with overall technical and project experience of the software
experience engineers who will do the work
Recording Risk
Information
Project: Embedded software for XYZ system
Risk type: schedule risk
Priority (1 low ... 5 critical): 4
Risk factor: Project completion will depend on tests which
require
hardware component under development. Hardware component
delivery may be delayed
Probability: 60 %
Impact: Project completion will be delayed for each day that
hardware is unavailable for use in software testing
Monitoring approach:
Scheduled milestone reviews with hardware group
Contingency plan:
Modification of testing strategy to accommodate delay using
software simulation
Estimated resources: 6 additional person months beginning 7-1-
96
Questionnaire on Project Risk
(Questions are ordered by their relative importance to project success)
Take a forward-looking
view
Think about risks that may arise in the future; establish contingency plans
Encourage open
communication
Encourage all stakeholders and users to point out risks at any time
Integrate risk
management
Integrate the consideration of risk into the software process
Emphasize a
continuous process of Modify identified risks as more becomes known and add new risks as better
risk management insight is achieved
Develop a shared
product vision A shared vision by all stakeholders facilitates better risk identification and
assessment
Encourage teamwork
when managing risk Pool the skills and experience of all stakeholders when conducting risk
management activities
Summary
• Whenever much is riding on a software project, common sense dictates risk
analysis
– Yet, most project managers do it informally and superficially, if at all
• However, the time spent in risk management results in
– Less upheaval during the project
– A greater ability to track and control a project
– The confidence that comes with planning for problems before they occur
• Risk management can absorb a significant amount of the project planning
effort…but the effort is worth it
Software Configuration
Management
- Introduction
- SCM repository
- The SCM process
Software Configuration
• The Output from the software process makes up the software
configuration
– Computer programs (both source code files and executable files)
– Work products that describe the computer programs (documents targeted at
both technical practitioners and users)
– Data (contained within the programs themselves or in external files)
35
Origins of Software Change
• Errors detected in the software need to be corrected
• New business or market conditions dictate changes in product
requirements or business rules
• New customer needs demand modifications of data produced by
information systems, functionality delivered by products, or services
delivered by a computer-based system
• Reorganization or business growth/downsizing causes changes in
project priorities or software engineering team structure
• Budgetary or scheduling constraints cause a redefinition of the system
or product
36
Elements of a Configuration
Management System
• Configuration elements
– A set of tools coupled with a file management (e.g., database) system that
enables access to and management of each software configuration item
• Process elements
– A collection of procedures and tasks that define an effective approach to
change management for all participants
• Construction elements
– A set of tools that automate the construction of software by ensuring that
the proper set of valid components (i.e., the correct version) is assembled
• Human elements
– A set of tools and process features used by a software team to implement
effective SCM
37
What is Change Management
• Also called software configuration management (SCM)
• It is an umbrella activity that is applied throughout the software process
• It's goal is to maximize productivity by minimizing mistakes caused by
confusion when coordinating software development
• SCM identifies, organizes, and controls modifications to the software being
built by a software development team
• SCM activities are formulated to identify change, control change, ensure that
change is being properly implemented, and report changes to others who may
have an interest
39
Have you established a baseline yet?
40
Baseline
• An SCM concept that helps practitioners to control change without
seriously impeding justifiable change
• IEEE Definition: A specification or product that has been formally
reviewed and agreed upon, and that thereafter serves as the basis for
further development, and that can be changed only through formal
change control procedures
• It is a milestone in the development of software and is marked by the
delivery of one or more computer software configuration items
(CSCIs) that have been approved as a consequence of a formal
technical review
• A CSCI may be such work products as a document (as listed in MIL-
STD-498), a test suite, or a software component
41
Baselining Process
1) A series of software engineering tasks produces a CSCI
2) The CSCI is reviewed and possibly approved
3) The approved CSCI is given a new version number and placed in a
project database (i.e., software repository)
4) A copy of the CSCI is taken from the project database and
examined/modified by a software engineer
5) The baselining of the modified CSCI goes back to Step #2
42
The SCM Repository
Paper-based vs. Automated
Repositories
• Problems with paper-based repositories (i.e., file cabinet containing folders)
– Finding a configuration item when it was needed was often difficult
– Determining which items were changed, when and by whom was often
challenging
– Constructing a new version of an existing program was time consuming and
error prone
– Describing detailed or complex relationships between configuration items was
virtually impossible
• Today's automated SCM repository
– It is a set of mechanisms and data structures that allow a software team to
manage change in an effective manner
– It acts as the center for both accumulation and storage of software engineering
information
– Software engineers use tools integrated with the repository to interact with it
44
Automated SCM Repository
(Functions and Tools)
Requirements
Versioning
tracing
SCM Repository
Functions
Dependency Data integrity Configuration
tracking Information sharing management
Tool integration
Data integration
Methodology enforcement
Document standardization
Change Audit
management trails
47
Summary of CM Tools
• http://www.daveeaton.com/scm/CMTools.html
• http://www.laatuk.com/tools/SCM_tools.html
• http://www.snuffybear.com/ucmcentral_new_vendorlinks.htm
• http://www.google.com/Top/Computers/Software/Configuration_Management
/Tools/
• http://stason.org/TULARC/business/config-version-management-tools/69-CM
-Tools-With-World-Wide-Web-Sites.html
• http://www.cmcrossroads.com/cm-resources/tools/commercial-cm-tools
48
The SCM Process
Primary Objectives of the
SCM Process
• Identify all items that collectively define the software configuration
• Manage changes to one or more of these items
• Facilitate construction of different versions of an application
• Ensure the software quality is maintained as the configuration evolves
over time
• Provide information on changes that have occurred
50
SCM Questions
• How does a software team identify the discrete elements of a software
configuration?
• How does an organization manage the many existing versions of a program
(and its documentation) in a manner that will enable change to be
accommodated efficiently?
• How does an organization control changes before and after software is
released to a customer?
• Who has responsibility for approving and ranking changes?
• How can we ensure that changes have been made properly?
• What mechanism is used to appraise others of changes that are made?
51
SCM Tasks
Status reporting
Configuration auditing
Version control
Change control
Identification
CSCI CSCI
CSCI CSCI
53
Identification Task
• Identification separately names each CSCI and then organizes it in the
SCM repository using an object-oriented approach
• Objects start out as basic objects and are then grouped into aggregate
objects
• Each object has a set of distinct features that identify it
– A name that is unambiguous to all other objects
– A description that contains the CSCI type, a project identifier, and change
and/or version information
– List of resources needed by the object
– The object realization (i.e., the document, the file, the model, etc.)
54
Change Control Task
• Change control is a procedural activity that ensures quality and consistency as
changes are made to a configuration object
• A change request is submitted to a configuration control authority, which is
usually a change control board (CCB)
– The request is evaluated for technical merit, potential side effects, overall impact on
other configuration objects and system functions, and projected cost in terms of
money, time, and resources
• An engineering change order (ECO) is issued for each approved change
request
– Describes the change to be made, the constraints to follow, and the criteria for
review and audit
• The baselined CSCI is obtained from the SCM repository
– Access control governs which software engineers have the authority to access and
modify a particular configuration object
– Synchronization control helps to ensure that parallel changes performed by two
different people don't overwrite one another
55
Version Control Task
• Version control is a set of procedures and tools for managing the creation and use
of multiple occurrences of objects in the SCM repository
• Required version control capabilities
– An SCM repository that stores all relevant configuration objects
– A version management capability that stores all versions of a configuration object (or
enables any version to be constructed using differences from past versions)
– A make facility that enables the software engineer to collect all relevant configuration
objects and construct a specific version of the software
– Issues tracking (bug tracking) capability that enables the team to record and track the
status of all outstanding issues associated with each configuration object
• The SCM repository maintains a change set
– Serves as a collection of all changes made to a baseline configuration
– Used to create a specific version of the software
– Captures all changes to all files in the configuration along with the reason for changes
and details of who made the changes and when
56
Configuration Auditing Task
• Configuration auditing is an SQA activity that helps to ensure that quality is
maintained as changes are made
• It complements the formal technical review and is conducted by the SQA group
• It addresses the following questions
– Has the change specified in the ECO been made? Have any additional modifications
been incorporated?
– Has a formal technical review been conducted to assess technical correctness?
– Has the software process been followed, and have software engineering standards been
properly applied?
– Has the change been "highlighted" and "documented" in the CSCI? Have the change
data and change author been specified? Do the attributes of the configuration object
reflect the change?
– Have SCM procedures for noting the change, recording it, and reporting it been
followed?
– Have all related CSCIs been properly updated?
• A configuration audit ensures that
– The correct CSCIs (by version) have been incorporated into a specific build
– That all documentation is up-to-date and consistent with the version that has been built
57
Status Reporting Task
• Configuration status reporting (CSR) is also called status accounting
• Provides information about each change to those personnel in an organization
with a need to know
• Answers what happened, who did it, when did it happen, and what else will be
affected?
• Sources of entries for configuration status reporting
– Each time a CSCI is assigned new or updated information
– Each time a change is approved by the CCB and an ECO is issued
– Each time a configuration audit is conducted
• The configuration status report
– Placed in an on-line database or on a website for software developers and
maintainers to read
– Given to management and practitioners to keep them appraised of important
changes to the project CSCIs
58
Summary
• Introduction
• SCM Repository
• SCM Process
– Identification
– Change control
– Version control
– Configuration auditing
– Status reporting
59