C.31:4.1a - Filled ModularityVectorLite

ModularityVectorLite:
  describedHolonRef: ProductPlatform@FieldPumpFamily
  architectureQuestion: which structural repair would reduce field-replacement and certification burden?
  intendedArchitectureUse: choose the next modularity repair for field service and procurement
  claimScopeRef?: field-service and procurement architecture claims
  qualificationWindowRef?: 2026Q2
  architectureClaimRef?: ArchitectureClaim@PumpControllerPlatform
  selectedStructureRefs: PumpControllerModuleInterfaceStructure, PumpControllerEvidencePackageStructure
  structureKindRefs: ModuleInterfaceStructure, EvidencePackageStructure
  liveCharacteristics:
    - characteristicRef: InterfaceStandardizationShare
      currentCue: three field variants need different wiring adapters behind ports with the same API name.
      repairDirection: identify the electrical differences the adapters accommodate and which variants must remain in service before changing the shared interface.
      claimUseClass: local repair cue
      forbiddenOverread: the public API label is not substitutability or procurement suitability.
    - characteristicRef: SubstitutabilityWidth
      currentCue: both candidate boards fit the connector and passed a bench signal test. A is qualified for the required signal, rate and wiring throughout this enclosure's operating temperature range. B's rating excludes the required maximum.
      repairDirection: admit A and exclude B from this pair for the specified enclosure. Establish the operating range for another enclosure before carrying the judgement there.
      claimUseClass: eligibility of the two boards for this signal and wiring throughout the specified operating range
      forbiddenOverread: the alternate-board count is not a selection result.
    - characteristicRef: EvidenceReuseShare
      currentCue: the electrical result covers A in this wiring and operating range. A different enclosure can expose the board to a higher temperature.
      repairDirection: use the electrical result within its qualification. Compare the field enclosure against the qualified thermal conditions before commissioning any further test.
      claimUseClass: local repair cue with possible evidence-package use
      forbiddenOverread: reused evidence is not assurance sufficiency.
  observedProblem: the team says the platform is modular because interfaces are public and evidence is reusable, but field replacement and certification still create variant-specific work.
  relatedClaimPatternLocatorsIfClaimed: A.6.M for the module-interface relation; C.31.RSA if report-only share becomes reusable-structure accounting; A.10 or B.3 only if an evidence-use or assurance-use assertion is being made.
  stopCondition: the service engineer can use A for the stated fit, signal and temperature requirements. Assess other procurement requirements or a proposed platform change when the decision calls for them.

The engineer can now name the eligible board among the two examined. To decide whether an interface change would reduce the cost of field service, compare the adapter and qualification work for the installed variants with the migration and service work after the change. An increased standardization share can coexist with higher service cost.