MEP Work
Excavation Bedding Manhole (RCC and Brick work) Pipe laying Pipe jointing Encasing/Trust block Leak test Back filling
MEP Work Equipments
Loader Excavator Tipper Tanker Transit mixer Crane/Hydra Trailer Compactor
MEP Work
Materials
RCC pipe (Various size) Coarse & Fine aggregates Cement Steel Brick
Test
Material test (cement, steel, brick & aggregates) Pipe inspection Leak test
MEP Work
Work procedure
Study GFC drawing for level and alignment. Arrangement of co-ordinates and TBM. Record the original ground level. Excavation according to invert level of pipe Fill PCC (1:3:6) or granular material in case of excess excavation. Trimming manually at bottom level Compact all the loose materials Base concrete as per design and drawing Mark the layout of manhole for brick work Start brick work with CM & control the joints Fabrication of reinforcement, shuttering and concreting Curing as per the requirement
MEP Work
Work procedure
Check and requirement of bedding Laying of pipe line as per the alignment Check the alignment and fix Joint the pipe as per specification/requirement Leak test Haunch concrete/pipe encasing Back filling at both sides simultaneously/uniformly Continue filling up to top of the pipe and continue layer wise fill with compaction Back filling of manhole layer wise
MEP Work
Contract specification
Excess excavation should be filled with 1:3:6 concrete or granular fill CM mortar should measured