0% found this document useful (0 votes)
288 views2 pages

Plumbing, Sanitary

This document is an inspection checklist for plumbing and sanitary works at a construction site. It lists inspection criteria such as the type and sizes of pipes and fittings, routing of cold and hot water pipes, setting out and alignment, location of pipe sleeves, joints and connections, protection, testing, and functionality. The checklist is used to verify works at various stages of installation and post-installation and ensure any issues are rectified by the main contractor.

Uploaded by

kumarakash122392
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
288 views2 pages

Plumbing, Sanitary

This document is an inspection checklist for plumbing and sanitary works at a construction site. It lists inspection criteria such as the type and sizes of pipes and fittings, routing of cold and hot water pipes, setting out and alignment, location of pipe sleeves, joints and connections, protection, testing, and functionality. The checklist is used to verify works at various stages of installation and post-installation and ensure any issues are rectified by the main contractor.

Uploaded by

kumarakash122392
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Insp. Ref.

#: _____________
VENKATA PRANEETH DEVELOPERS PVT LTD.
Inspection Checklist - Plumbing & Sanitary Works

Site Name :

Main Contractor (MC) : Contractor Supervisor :


Site Engineer : Site Supervisor :
Villa No. :
Pipes & fittings: Type & sizes = spec/approved sample? Y ( ) N ( )
Inspection criteria Pre & During Installation Post-Installation

Routing of Cold & Hot Water

SE & QC Accepted Works


Positioning of pipe routing

SE & QC Re-Verification
Setting Out & Alignment

Pipe Sleeves Location

Bearers & Platform for

Pressure Test, Smoke

SE & QC Verification
Routing of PVC Pipe
SE & QC Approval to

Joints, Connection,

Functionality Test
Water Tank
proceed works
MC Rectification

MC Rectification
Fittings / Wares
Pipe

Protection
SE Verification

Location Remarks

Test
Pipe jointings

Level pegs

Brackets
Gradient
INTERNAL

EXTERNAL

1 Toilet -1

2 Toilet -2

3 Toilet -3

4 Kitchen

5 Wash area

Checked/Verified by: MC SE MC SE/QC SE/QC MC SE/QC MC SE/QC

Signature
&
Date

Plumbing Quality = Nos. of location accepted by SE & QC after Re-Verification @ Post-Inst. / Total locations x 100% =

Notes:
(1) Change the location in this checklist according to the product layout. For high-rise project, to attach a copy of the layout.

(2) See below for acceptance tolerance. MC to mark 'a' in respective location only if workmanship is acceptable (NA if not applicable), \

Inspection criteria Acceptance tolerance Tools used

Setting out & alignment Marking of plumbing & sanitary routing, soil pipe & sleeve location, & etc = layout. Routing to be horizontally or vertically aligned. visual
Avoid running along joint between structural element & brickwall
Pre & During Installation

Positioning of riser, …. Positioning of riser, water meter, manhole, gully, dropper, stop cock outlet, fitting = layout / Praneeth / Consultant visual +
M. tape

Joints of piping Approved pipe fittings & adhesive used. 100mm dia. underground pipe for kitchen sink waste pipe. No burning of pipes allowed visual

Manholes & gully Constructed = see below diagram / Consultant drawing / as suggested by resident engineer visual

1
Routing of cold water As per Shop Drawing. Vertically & horizontally aligned. Avoid running along joint between structural element & brickwall visual
pipe

Joints, connection & Correct adhesive used. Joints are properly sealed. Cement patching to hold pipes and elbow to brickwall. All outlets protected / visual
protection properly capped. No damages detected visually.

Gradient Gradient for inclined pipes: 80mm–1:40; 100mm-1:60; 150mm–1:100 visual +


M. tape

Brackets Secured with brackets at interval: 80mm - 1.5m; 100mm - 1.8m; 150mm - 2m or as recommended by manufacturer visual +
M. tape
Post Installation

Water tank Location, type & capacity = drawing/spec. Water tight. Clean visual

CPVC Pipe Pressure test Using with Hydrilic pressure Machine, Testing pressure - 6 kg /cm2 hold 6 hours. visual +
procedure pressure
gauge
PVC Pipe Pressure test Using with Hand Blower & Smoke, hold 1 hour. visual
procedure

Pressure test & Test twice for all pipe lines: 1) before tiling, 2) after connecting to water tank with water supply.Pipe line to be pressurize with visual +
Functionality Test water. Flushing to all sanitary fittings and wares.Test as per Consultant req. Attach test report. pressure
gauge
Fittings / Wares Firmly secured & joints properly sealed. Location = drawings (+/-25mm). Mounting height: see below table. Manhole & floor trap visual
covers = approved & securely fixed. Free from leakage, chokage, damages & stains. Flush test report attached

Sanitary Tap Fittings/Wares Height from the bottom of the fittings/wares to FFL (mm)

Wall tile size: 200s x 250h

Wash basin / table top / salad bowl 800 (from the top of wares)

Kitchen sink 830

Paper roll holder 600

Bib tap at bathrooms 600

Shower rose (fixed) 2000

Shower rose (with adjustable rod) 1250 (from the rod bottom)

Shower stop cock, Soap holder 1000

Tap for washing machine 1100

Stop cock for riser / down pipe 2000 (2200 if behind door)

Bath spout 800

Tap at garden 800

(3) SE/QC to mark 'a' if acceptable, 'x' if reject (& circle the respective item) or '-' if not check (not for Post-Installation). MC to rectify if any reject & SE/QC to
re-verify.

You might also like