Date: 15. 01. 2014 Time: 08.00 AM

This RFI requests an inspection to close out deficiencies for five POV systems on January 15th at 8 AM at the GTC-2 platform level. The contractor and consultant representatives must sign off on the inspection status of the work, which can be one of four statuses including work may proceed, work may proceed with changes, work must be revised and resubmitted, or inspection not required. Permission to proceed with the work does not constitute acceptance and does not relieve the contractor of contractual obligations.

Uploaded by

Aneesh Jose
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
436 views1 page

Date: 15. 01. 2014 Time: 08.00 AM

This RFI requests an inspection to close out deficiencies for five POV systems on January 15th at 8 AM at the GTC-2 platform level. The contractor and consultant representatives must sign off on the inspection status of the work, which can be one of four statuses including work may proceed, work may proceed with changes, work must be revised and resubmitted, or inspection not required. Permission to proceed with the work does not constitute acceptance and does not relieve the contractor of contractual obligations.

Uploaded by

Aneesh Jose
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Client:

Consultant:

Request for Inspection (RFI)

Contract No.: To: Cc: Issued by: ITP Ref:

503406-TK5941 Mr. Manoje

Contractor:

ALSTOM

RFI No.: Date: Time: Signature: Element No:

ALSTOM/D-213 14.01.2014

Mr.SylvainLepage, Mr. Siva Aneesh Jose 503406-TK5941-Q07-002

04:00 PM

Def Close Out

Work to be Inspected:

To Close Out Deficiencies as below POV SYSTEM: 225-GTC-30, 225-GTC-29, 225-GTC-26, 225-GTC-22, 225-GTC-23 Date of inspection

Date: 15. 01. 2014 Time: 08.00 AM


Drawing No: Not Applicable Location: GTC 2 Platform Level: Consultant / Inspector Comments:

Not Applicable

Inspected by: Date:

Signature: Time:

The above works have been inspected and the next operation may proceed subject to Inspection Status. Works rejected must be resubmitted for Inspection. RETURNED TO CONTRACTOR INSPECTION STATUS Status A: Work May Proceed B: Work May Proceed subject to incorporation of changes indicated C: Revise and Resubmit Work may not Proceed D: Inspection not required

Name: Signature: Date:

Contractors Representative

SLIIs Representative

IMPORTANT: Permission to proceed does not constitute acceptance or approval of the Work under inspection and does not relieve contractor from full compliance with contractual obligation.