Ehtcl 001 1

This document is an inspection checklist for receiving, storing, and handling electrical heat tracing system materials. It lists acceptance criteria and references for reviewing documentation and material condition. Materials must be new, undamaged, and traceable. Storage procedures must follow specifications, manufacturer recommendations, and standards to prevent damage from water, dust, temperature extremes, improper stacking, and protect cable ends.

Uploaded by

arockiyathass
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
454 views1 page

Ehtcl 001 1

This document is an inspection checklist for receiving, storing, and handling electrical heat tracing system materials. It lists acceptance criteria and references for reviewing documentation and material condition. Materials must be new, undamaged, and traceable. Storage procedures must follow specifications, manufacturer recommendations, and standards to prevent damage from water, dust, temperature extremes, improper stacking, and protect cable ends.

Uploaded by

arockiyathass
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

INSPECTION CHECKLIST

Electrical Heat Tracing System Material Receiving, Storage, Handling and Preservation
PROJECT TITLE

REV 0 CHECKLIST NUMBER

DATE APPROVED

CR NUMBER

EHTCL-0001
BI / JO NUMBER

ELECTCONTRACTOR / SUBCONTRACTOR

EQUIPMENT ID NUMBER(S) LAYOUT DRAWING NUMBER SCHEDULED INSPECTION DATE & TIME ITP NUMBER CLIENT INSPECTION LEVEL

EQUIPMENT DESCRIPTION REV. NO. PURCHASE ORDER NUMBER LOCATION

PLANT NO.

ACTUAL INSPECTION DATE & TIME ITP ACTIVITY NUMBER CONTRACTOR INSPECTION LEVEL

WORK PERMIT REQUIRED?

ITEM No. A. A1 A2 B. B1 B2 Document Review

ACCEPTANCE CRITERIA

REFERENCE

PASS

FAIL

N/A

RE-INSP DATE

Review documents for Material Receiving. Identification procedure reviewed and implemented. General Requirements Materials shall be new and unused. Documentation for traceability reviewed and implemented. As Designed -Electrical materials shall be in accordance with the Saudi Aramco-approved project-specific design drawings, diagrams, schedules, lists, databases, and associated documents. Verify that the contractor or it's Saudi Aramco approved third party inspector performed the quality activities at the supplier and sub-supplier locations as required by the inspection level assigned for the materials and equipment identified in SAER-1972 Inspection Requirements. Free of Damage - Electrical materials shall be free of damage. All Incoming material shall be visually inspected for damage and conformance to all applicable Material Storage, Handling, and Preservation The CONTRACTOR shall include procedures for handling, storage, and preservation of material as specified in all applicable specifications, manufacturer recommendations and SAUDI Aramco's standards. Store material in a clean, dry location at temperatures between -40F and 140F (-40C and 60C).

Schedule Q Att. IV Sec.3 Schedule Q Att. IV Sec. 4

Schedule Q Sec. 2 Schedule Q Att. IV Sec. 4 Schedule Q Sec. 4

B3

B4

Schedule Q Att. III Sec. 1.2

B5

Schedule Q Att. IV Sec. 7.1

C.

C1

Schedule Q Att. IV, Sec.5 NECA-202 Sec 4.1.3 a & Vendor Manual NECA-202 Sec 4.1.3 a & Vendor Manual NECA-202 Sec 4.1.3 a & Vendor Manual NECA-202 Sec 4.1.3 b & Vendor Manual NECA-202 Sec 4.1.3 c & Vendor Manual NECA-202 Sec 4.1.3 d & Vendor Manual NECA-202 Sec 4.1.3 e & Vendor Manual

C2

C3

Avoid areas where water accumulate or where significant airborne dust or dirt is present.

C4

Store heat tracing material in raise above floor and possible water levels, and warp in protective plastic sheet.

C5

Store heat tracing material carefully to prevent damages. Observe warning and stacking instructions on packing or shipping materials.

C6

Heat tracing materials do not stack boxes that are partially crushed, even if the products are intact.

C7

Verify that any event occur, such as a water leak, which could damage stored heat tracing material, immediately re inspect it and obtain replacements for damaged good.

C8

Verify the protection of heat tracing cable, it should be provide for the ends of all heat tracing cables to preclude water entrance and migration in the heat tracing cables.