Installation Method Statement
                                                                     1 of 6
            Issue Date         Issued by                      Document No.
            Rev No.       0    Approved by
TITLE                            INSTALLATION METHOD STATEMENT
PROJECT                         Caustic Tower Modification Project
ITEM                             LT-01 – Caustic Tower
CUSTOMER                         Koch-Glitch / Kemya
CUSTOMER’S WO. NUMBER
ISSUED BY
DATE
                                                        Page
                     Installation Method Statement
                                                        2 of 6
               Issue Date         Issued by          Document No.
               Rev No.       0    Approved by
 CONTENT                                             PAGE
INTRODUCTION                                            3
SCOPE OF WORK                                           3
MAIN EQUIPMENT                                          3
MATERIAL STORAGE AND TRANSPORTATION                     3
LIFTING TO/FROM THE COLUMN                              4
WASTE DISPOSAL                                          4
VENTILLATION                                            5
INSTALLATION PROCEDURE                                  7
                                                                                Page
                            Installation Method Statement
                                                                                3 of 6
                    Issue Date             Issued by                        Document No.
                    Rev No.          0     Approved by
1.0       INTRODUCTION
 The following instructions aim to highlight the methodology of how the operations as listed
 on the installation method statement XXXXXXXXXX are to be performed. The procedure
 for which the work is to be completed as detailed in method statement XXXXXXXXXXXX
2.0       SCOPE OF WORK
 To carry out the Modification of Trays in Caustic Tower LT-01 of Dia. 4400 mm ID. As per
 the drawing reference attached.
 It must be stressed that all the works to be carried out with the importance on safety over
 and above all other considerations and is subject to the statutory and mandatory health
 and safety regulations pertaining thereto, together with the KG / KEMYA safety Policies.
 Prior to commencement, the column is to be fully isolated, washed / steamed through. All
 Column Manholes are to be opened and gas free. KG / KEMYA will give the entry to
 column after ensuring safe working condition.
        Entry will not be permitted until entry permit is obtained from KG / KEMYA.
 At all times when men are working inside the column, entry attendant (standby man) is
 required at manhole entry location.
3.0       MAIN EQUIPMENT
  No.    Description                                     Qty.       Comments
  1      Crane                                           1
  2      Forklift                                        1
  3      Welding Machines                                1
  4      Grinding M/C 110 V                              1
4.0       MATERIAL STORAGE AND TRANSPORTATION
 The Column internals shall be delivered on pallets or in closed wooden crates to the
 designated preparation area prior to shutdown. The packing cases will only be opened in
 the presence of a specialist from KG. Any transport damage has to be reported
 immediately to the responsible person. During the pre-shutdown period, all crates should
 be checked against packing lists and to be arranged in the sequence of installation.
 Missing items to be reported immediately.
 Prepared materials will be transported from the storage area to near the column area in
 readiness for installation as and when required.
 During transporting the material, the traffic regulations and plant procedure must be
 followed.
                                                                                       Page
                          Installation Method Statement
                                                                                       4 of 6
                    Issue Date               Issued by                          Document No.
                    Rev No.            0     Approved by
5.0     LIFTING TO / FROM THE COLUMN
 A crane, mechanical / pneumatic winches and chain blocks will be used to facilitate the
 removal of old and the installation of new internals and the new or old materials will be
 lowered or lifted by using material basket.
 The lifting basket will be tested and marked with its safe working load. An experienced
 supervisor / men will control all lifting and lowering activities either by radio contact or
 hand signals to the crane
 A clear working area is required at the point of lifting or lowering the materials.
  The lifting area will have a barrier to prohibit unauthorised entry and for
  safety precautions during lifting operations.
6.0     WASTE DISPOSAL
 Redundant internals will be removed from the column via the respective manholes and
 placed into a lifting basket, or slung with certified shackles and slings, then lowered to
 ground level using the crane / winch and will be deposited into a scrap.
 All the waste materials to be disposed in the designated area as per the instructions of KG
 / Kemya
7.0     VENTILATION & LIGHTING
 Air mover or exhaust to be fixed below the working level for better fresh air circulation. For
 vast hot work inside the column, localised fume extraction equipment to be provided.
 Personal respiratory systems will also be provided for the welder workforce during hot
 work activities if required.
 Only 24 V or explosion proof lighting must be used inside the confined space. For grinding
 purpose use pneumatic grinders are 110V grinders.
8.0     INSTALLATION PROCEDURE
 Entry into the column will only be carried out once column is gas freed and the entry
 permit issued. The following parameters are very important to confined space entry.
 Oxygen            19.5 to 23% vol. Max.
 LEL               0%
 It is Mandatory that full understanding of the requirements to all involved persons.
 Entry attendant should be located near the working manhole and entry into the column
 must be strictly controlled by use of signing-in system to check everyone in and out.
                                                                                    Page
                             Installation Method Statement
                                                                                    5 of 6
                    Issue Date               Issued by                           Document No.
                    Rev No.            0     Approved by
9.0       PRE-SHUTDOWN ACTIVITIES
           SITE ESTABLISHMENT
                   9.1.1     Complete safety orientation for all personnel.
                   9.1.2     Mobilise equipment and personnel to site.
                   9.1.3     Site office and store to be established
                   9.1.4     Complete Permit Requirement.
                   9.1.5     Meeting / Discussion with client.
                   9.1.6     Equipment inspection and necessary certification from client.
 All the materials and the new internals to be shifted to the designated area for material
 identification and segregation. The tray materials to be checked against approved
 drawings & packing list. Each one type of tray assembly to be done for easy
 understandings and fitment purpose. The loose materials like fasteners to be kept in
 stores.
10.0      SHUTDOWN ACTIVITIES
          10.1     Vessel Entry Check
       Sr. No                  Description                 Responsibility
       8.2.1      Positive isolation of columns.           KEMYA
       8.2.2      Chemical cleaning of Column              KEMYA
       8.2.3      Gas test                                 KEMYA/ ALMUZAIN
       8.2.4      Lighting arrangements                    KG/ ALMUZAIN
       8.2.5      Proper ventilation                       KG/
                                                           ALMUZAIN
       8.2.6      Standby person outside the column        ALMUZAIN
       8.2.7      Valid confined space entry permit        KG / KEMYA
          10.2     Column Details
  SL NO          SERVICE       DIAMETER       NO OF TRAYS           TYPE OF TRAYS
  8.2.1     Caustic Tower      4400 mm        5 – 16 (12 Trays)     Bubble Cap
          10.3     Job Details
                   Entry to be done through 1C manhole
                           ENTRY
                           INTERNAL MANWAYS OPENING
                           INSPECTION BY CLIENT
                                                       Page
              Installation Method Statement
                                                       6 of 6
        Issue Date             Issued by            Document No.
        Rev No.          0     Approved by
            REMOVAL OF TRAYS # 5 TO 16 - 12 TRAYS
            BY GRINDING
            INSTALLATION OF TRAYS WITH LEAKTEST
            NOZZLE MARKING, CUTTING, FIT-UP
            OUTSIDE
            BACKCHIPPING OF NOZZLE AND SEALING
            FROM INSIDE
            FIT-UP AND WELDING OF FALSE
            DOWNCOMER AND PWHT ( TWO
            NOZZLES AND F/DOWNCOMER AREA)
            HYDROTEST AND CUTTING OF
            TEMPORARY ATTACHMENTS)
            INSPECTION BY CLIENT
10.4   Drawing list for Caustic Tower – LT-01
                          DRAWING LIST