SLDC-Gujarat: Draft Procedure
GRID CONNECTION TO INTRA
            STATE NETWORK
                                      DRAFT
                PROCEDURE FOR GRID
                   CONNECTION
                      (TO BE FOLLOWED BY NEW GRID USER
                                     AND
                              EXISTING GRID USER
                                     AND
                            GRID CONNECTION AFTER
                    SUBSEQUENT MODIFICATION/EXPANSION)
                      STATE LOAD DISPATCH CENTRE
             GUJARAT ENERGY TRANSMISSION CORPORATION LTD.
                     PREPARED BY COMMERCE DEPARTMENT
                           SLDC, GOTRI, VADODARA
                          Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
                           GRID CONNECTION PROCEDURE
   1.   PREAMBLE:
   1.1 This procedure provides guidelines for grid connection to intra state network
       applicable to long term open access users including generating &
       Distribution Company before commencement of long term open access.
   1.2 The procedure prepare for providing grid connection to intra state network
       as per prevailing regulation issued by GERC i.e. provision 10(iii) of “Open
       Access in Intra-state Transmission and Distribution regulation 2005’ and
       provision 3 of “Levy and Collection of Fees and Charges by SLDC
       Regulations, 2005”
   1.3 This procedure is prepared in order to facilitate implementation of
       regulation issued by Gujarat Electricity Regulatory Commission (as
       mentioned in above para) exercising powers conferred to State Load
       Dispatch Centre under IE Act’2003.
   1.4 An interpretation/meaning of any words, statements and expressions
       hereunder this procedure shall have a same meaning as stipulated in
       regulation. Any dispute, therefore, arise due to incorrect interpretation shall
       be resolved as per meaning of regulation.
   2.   INTRODUCTION
   2.1 All long term open access users or users running in parallel with system are
       obtaining approval for connectivity to intra state network under connectivity
       condition of State Grid Code or prevailing regulation from State
       Transmission Utility.
   2.2 An intending grid user has supposed to compliance all terms and condition
       mentioned there under in approval given by STU and obtained certificate for
       confirmation from respective STU.
   2.3 The user who have obtained approval for connectivity to intra state network
       and complied all conditions of approval as per connectivity procedure
       stipulated in State Grid Code are eligible for connection to grid. The
       procedure followed thereafter, from application to grid by intending user
       and releasing grid connection, shall be exercised by SLDC.
   2.4 Such application filed by intending grid users is to be processed by SLDC as
       per prevailing regulation of GERC. Regulation applicable are reproduced as
       under :
        ■ Provision 3 of “Levy and Collection of Fees and Charges by SLDC
          Regulations, 2005’ is reproduced as under:
                          Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
         “3. Application for connection to Grid
         (i)    Generating companies and licensees requiring long term access to the
                grid shall submit an application to the SLDC in the specified format at
                least one month before the proposed date of connection to the State grid,
                along with fee of Rs. 10,000.00 ( Rupees ten thousands only). The
                existing licensees and generating companies shall register themselves
                with SLDC by filing an application along with above mentioned fees.
         (ii)   The SLDC, after scrutinizing the application and after being satisfied of
                the completeness and correctness of the information furnished in the
                application, shall register the application in SLDC records duly intimating
                the applicant regarding the acceptance of the same.
         ■ Provision 10(iii) of “Open Access in Intra-state Transmission and
           Distribution regulation 2005’ is reproduced as under:
         “10. Bulk Capacity Agreement
         (i)    A long term open access user shall entire into Bulk Power
                Transmission/Distribution       capacity       agreement  with       the
                transmission/distribution licensee. An open access user shall enter into
                commercial agreements with the transmission and distribution licensees,
                for use of their transmission and distribution systems.
         (ii)   The agreement shall provide, amongst other things for the eventuality of
                premature termination of agreement and its consequences on the
                contracting parties.
         (iii) After agreements have been entered into and copies furnished to State
               Load Dispatch Centre, the State Load Dispatch Centre shall inform the
               open access user the date from which open access will be available
               which will not be later than 3 days from the date of furnishing of
               agreements.”
   2.5     Procedure of grid connection can be applicable case to case base
           depending on complexity involved. Though it is not generic, SLDC has
           attempted to generalize procedure in order to diffuse complexity involved
           and to maintain smooth implementation.
   2.6     If the grid connection is terminated or renewed due to expiry of agreement,
           shall also have to obtained grid connection as per procedure stipulated
           hereunder. The any loss or damage occur due to power exchange takes
           place without approval of grid connection is to be reported to appropriate
           commission and shall be treated under breach of regulation.
   2.7     In case there is a change in status of network, which was existed during
           permission granted for grid connection by SLDC, shall also be updated to
           SLDC and obtain fresh permission for grid connection.
                            Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
   2.8    Application of grid connection, not in conformity with procedure stipulated
          here shall not be processed. Any delay arises due to incomplete or
          incorrect information to SLDC shall be on account of applicant only.
   2.9    SLDC may change, modify procedure for providing grid connection. SLDC
          shall inform such changes in procedure to GERC for conformity and
          circulated to all users and published on our website.
   3.    PROCEDURE FOR REGISTRATION OF APPLICATION:
   The forthcoming generating companies and distribution licensees as well as
   existing generating companies shall have to get registration as per procedure
   described as under:
   3.1    Generating companies and licensees intend to commence grid connection
          after obtaining necessary approval from STU shall submit application to
          SLDC in advance along with necessary fees. The application should be
          made in specified format as per Annexure I to III duly filled in two copies.
   3.2    The application shall contain non refundable application fee of Rs.10,
          000.00 (Rupees ten thousands only) in the favor of Chief Engineer, SLDC,
          GETCO, Gotri as a grid connection fees. The application received date
          shall be consider from date of payments of application fee. Any delay due
          to postal or clearance in bank etc. for which SLDC shall not be
          responsible.
   3.3    SLDC shall scrutinize the application, verify completeness and correction
          of information as above, shall register application and give
          acknowledgement of application.
    4.   SUBMISSION / PROCESSING OF GRID APPLICATION:
   4.1    The relevant documents and details as per prescribed check list is to be
          made available to SLDC along with application. The check list provides
          generalized documents but there may be exception based on case to case
          for which SLDC may require additional information. Applicant has to
          provide such information in reasonable time period.
   4.2    Generating Companies has to furnished details and copies of bulk Power
          Purchase Agreement (PPA) duly signed by its beneficiaries as per clause 10
          of GERC regulation 13 of 2005. Based on BPPA, generating companies
          shall derived allocation in percentage to its beneficiaries ( up to 4 digit
          accuracy after decimal point ), single figure for entire day without
          discriminating peak or off peak etc.
   4.3    After allocation of capacity as per BPPA, if there is surplus capacity
          available with generating station, may please be specified in application
          with probable mode of utilization of such capacity like sale through STOA
          or pending LTOA etc.
                          Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
   4.4    Licensee and Generating companies intend to get grid connection has to
          furnished details and copies of Bulk power transmission agreement (BPTA)
          to SLDC along with relevant transmission scheme approved by appropriate
          commission irrespective of dedicated lines or system strengthening
          scheme.
   4.5    Generating companies or licensee shall arrange to carry out system study
          with connectivity of adjoining network clearly specifying period for which
          study carried out with underlying assumption. Such system study is
          provided by STU (GETCO) or respective RLDC on payment basis. It is
          crucial for SLDC to ascertain deviation in assumption consider during
          system study and real time parameters, in order to determine suitable
          period/date for providing grid connection, after ensuring reliable and
          secure operation. Copy of system study carried out is to be submitted
          along with application.
   4.6    Intending grid user, Generating companies or licensee, has to arrange data
          communication facility to SLDC for real time monitoring and controlling as
          per requirement of SLDC well in advance as per State Grid Code. The data
          communication to SLDC is important for system operation, and same shall
          be tested and obtain satisfactory certificate from SLDC in one month
          advance before application of grid connection. Same is to be submitted
          with application.
   4.7    Generating companies & licensees has to approach SLDC with Stage wise
          planning of non commercial and commercial operation, schematic network
          with clear demarcation of interface points for deciding scheduling,
          metering and energy accounting scheme. Single line diagram for each
          stage wise planning to be submitted along with application.
   4.8    As per para (ix), concerned generating companies & licensees shall
          complete this exercise well in advance and obtain confirmation of
          scheduling, metering and accounting scheme from SLDC which is to be
          jointly agreed by all stakeholders. Meters are to be installed by respective
          agencies as per metering scheme prepared by SLDC. In Gujarat, Hon’ble
          commission has directed GETCO to provide meter, hence metering scheme
          finalized shall be installed by generating companies or distribution
          licensee in consultation with GETCO. Joint Minutes indicating
          confirmation of each concerned parties is to be submitted along with
          application.
   4.9    Distribution licensee has to submit detail of load to be connected category
          wise, and approved planning for load management within respective
          control area, network diagram and important places like airport, railway
          station, hospital etc.
                          Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
   4.10 Distribution licensee has to set up their independent control centre for
        exercising their role of grid user, with real time data availability for taking
        necessary action in maintaining grid, demand side management and for
        single point communication with SLDC.
   4.11 The purchase agreement is to be submitted by distribution licensee with
        summarize statement showing each supplier, contract capacity along with
        deficit and surplus for next one year.
   4.12 The Co generating Plant has to apply for grid connection as per procedure
        mentioned for generating station. However they have to indicate allocation
        to their own company, mentioning at same place (without injecting grid)
        and quantum of MW to be injected into network.
   4.13    Any dedicated lines or parallel operation of co-generating plant or any
          other plant shall has to follow same procedure during grid connection.
   5.     PROCESSING OF GRID CONNECTION:
   5.1    SLDC will study impact on system due to interconnection of new
          generating stations & associated network with prevailing system
          conditions and provide date from which open access to grid available.
   5.2    SLDC shall ensure the metering accounting, conduct meeting if necessary
          with concerned stakeholders for role to play by each individual and verify
          application, verify completeness and correction of information as above,
          shall register application and give confirmation of acceptance to associated
          parties.
   5.3    The evacuation network will be studied by SLDC and ensure that it is as
          per approved planning. In case deviation from planning, during incomplete
          network or partial installation, SLDC has to ensure availability of adequate
          transmission capacity with necessary margin.
   5.4    Based on current system behavior, SLDC will determine probable date for
          commencement of grid connection looking to the system reliability
          conditions after fulfillment of all requirement of SLDC. The date of
          commencement for open access to be adhered by respective users and
          change their planning accordingly.
   5.5    SLDC will finally issue a commencement order for grid connection suitably
          along with suitable notes as applicable to respective grid connection.
                          Gujarat Energy Transmission Corporation Ltd.
SLDC-Gujarat: Draft Procedure
   6.     APPLICABILITY OF PROCEDURE:
   6.1    While connection of one or more element of transmission element to grid or
          part of distribution licensee or generating companies after every
          modification or upgrdation or expansion, the treatment of such connection
          is not specified in regulation.
   6.2    If such expansion or modification affects the capacity of generating station,
          flow of transmission network and addition of new area of supply in
          distribution licensee which is electrified first time shall affect grid
          performance and operational planning of State Load Dispatch Centre.
   6.3    In view of above consideration, procedure mentioned hereunder is to be
          follow for such medication and expansion of network and addition of
          generating capacity.
   6.4    Licensee or generating companies has to register such up gradation or
          modification and obtain approval for connection to grid. Application fee for
          such up gradation and modification not mentioned in regulation.
   6.5    In such type of grid connection, part of information and procedure would be
          covered while earlier connection to grid, SLDC will have to provide grid
          connection for additional network or capacity only.
   6.6    Therefore, every modification/expansion in generating station or existing
          network shall be treated as revised grid connection and accordingly revised
          grid connection application to be filed. Application fee shall be applicable as
          mentioned in regulation for grid connection.
7 TIME LIMIT
   7.1    All existing grid users have to register with SLDC before 1st April’2009.
   7.2    All New grid users have to register 45 days in advance before
          commencement.
                          Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
                                          FORMAT 1
                    APPLICATION FORMAT FOR GRID CONNECTION
                            FOR GENERATING COMPANIES
                       (To be applicable for Generating Station )
Name of Generating Company :
Registered Address of Generating Company :
Name of Generating Station:
Location of Generating Station :
Category of Generating Station(IPP/CPP/MPP) :
Approval obtained from various Statutory
agencies
                             (Name /Reference)
                             (Name /Reference)
Legal/Regulatory     cases     pending    with
generating station
       (Name/ Case No/Description of Subject)
       (Name/ Case No/Description of Subject)
Proposed date of connection with grid
(A) Details of Generating Station
Total Generating Capacity ( in MW)
Capacity of each          COD of each Rating            MVAR         Terminal      Rated Aux
Unit                          Units    in               Capabili     Voltage       Req.
                                       (MW)             ty
Unit 1(Make :          )
Unit 2(Make :          )
Unit 3(Make :          )
Unit 4(Make :          )
Unit 5(Make :          )
Details of Generating Transformer      Type             Rating       Ratio HV/LV   Voltage
                                                        (MVA)                      Var. limit
GT of Unit 1
GT of Unit 2
GT of Unit 3
GT of Unit 4
GT of Unit 5
(B) Type of Fuel
                                           Type of      Rated consumption
                                           Fuel
Gas Bas station
Thermal Station
Cogenerations plant
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(C) Bulk Power Purchase Agreement (BPPA)
                           Period   of     Quantum      Beneficiar   Injection   Drawal
                           Agreement                    y/Buyer      point       point
For supply to Licensee
     Transaction 1(Route)
     Transaction 2(Route)
     Transaction 3(Route)
For supply to Licensee
    Transaction 1(Route)
    Transaction 2(Route)
    Transaction 3(Route)
For supply to Licensee
     Transaction 1(Route)
     Transaction 2(Route)
     Transaction 3(Route)
(D) Bulk Power Transmission Agreement (BPTA)
                          Period   Quantum             Connection Points
I. Intra -State Agency                       Interface points          Voltage
                                             1.
                                             2
                                             3.
                                             4.
II. Inter-State Agency                       1.
                                             2
                                             3.
                                             4.
(E) Parallel Connectivity Approval
      STU(Intra State)    Quantum   Date      Period       Ref No/Date
      CTU( Inter State)
(F) Long Term Open Access
      STU (Intra State)    Quantum Period    Injecting     Drawee      Remarks
                                             Point         Point
   CTU (Inter State)         Quantum       Period       Injecting       Drawee   Remarks
                                                        Point           Point
(G) Operating Parameters
   i)  Ramp-up rate (MW/Minute)
         Hot Start up
         Warm Start up
         Cold Start up
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
         ii)     Ramp-down rate (MW/Minute)
            Hot Start up
            Warm Start up
            Cold Start up
iii) Time required for synchronizing generating station
            Hot Start up
            Warm Start up
            Cold Start up
iv) Minimum Notice required from desynchronization to
synchronized unit
v) Technical Minimum load required in open cycle by
regulating fuel consumption
vi) Technical Minimum load required in combine cycle by
regulating fuel consumption
vii) Technical Minimum load required in open cycle by
with oil support
viii) Technical Minimum load required in combine cycle
with oil support
ix) Minimum MVAR injection without loss of active power
x) Minimum time required for switching from open cycle
to combine cycle mode
xi) Minimum Time required for synchronizing units one
after another (only GT units).
(H) Metering Arrangement
(i) Metering Scheme finalized by SLDC (Ref/Date)
(ii) No of Meter Assessed (Category    Assessed              Installed      Pending
wise )
      Main Meters
      Check Meters
      Stand by Meters
(ii) Submission of Schematic diagram        (Enclosed herewith)
showing meter number at each
location to be furnished to SLDC
(iv) Joint Testing of meters (         Date/ ( Record Notes enclosed h/w)
Testing date and record notes duly
signed)
(v) Scheduling & Accounting Scheme
finalized by SLDC(Ref/Date)
(I) Communication Scheme
(i) Communication Scheme
confirmed by SLDC (Ref/Date)
(ii) Details of data communication
      No of RTU
      No of Transducers /Sensors
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
       No of points taped
       Data communication
        redundancy
      Date of Testing
      Acceptance confirmation of
        SLDC
(iii) Details of voice communication
      Mode of communication               (PLCC/any other)
      Type of communication               (Dedicated/Interdependent)
        channel
      Alternate Communication             Channel1                  Channel2   Channel3
        channel
(J) Islanding & Restoration Scheme
(i) Proposed Islanding Scheme
      Frequency Variation
      Demand Variation
      Voltage Variation
(ii)Proposed Restoration procedure
      Availability of Synchronization facility
      Possible sources of black start power
      Availability of independent Black Start power
(iii) Mock trial of Islanding Scheme
      Date of Trial
      Hours system withstand in island mode
      Stability Measurement
(iv) Proposed planning date for Mock trial of Islanding
Scheme ( Not more than four weeks or 30 days after
commercial operation of generating station)
(v) Coordinator /Responsible officer for operating
islanding scheme & restoration procedure (Min Two)
Name :
Address :
Contact No.(RTC) :
(K) List of Attachment
      Schematic diagram
      Power Purchase Agreement
      Power Transmission Agreement
      Registration fee receipt
      Metering details including CT/PT
      Switch yard diagram (Approved by EI)
      Actual data as per Annexure A.2.1 of State Grid Code
      Any other supporting documents
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
                                            FORMAT 2
            APPLICATION FORMAT FOR GRID CONNECTION WITH SLDC
                         FOR DISTRIBUTION LICENSEE
                    (To be applicable for Distribution Licensee)
General :
Name of Distribution Licensee :
Registered Address of Distribution Licensee :
Area of Supply of Distribution Licensee:
Approval obtained from various agencies
                               (Name /Reference)
                               (Name /Reference)
Legal/Regulatory cases related with approval
of distribution licensee
        (Name/ Case No/Description of Subject)
        (Name/ Case No/Description of Subject)
Proposed date of grid connection :
(A) Details of Distribution licensee
1. Details of connected load            Category of consumers
                                        1           2                       3       4
Total Number
Connected Load (MW)
2. Details of Interface points          Voltage Wise
( Voltage wise list to be attached )*   400KV       220KV                   132KV   66KV
3. Details of EHV lines                    Voltage Wise
                                           400KV      220KV                 132KV   66KV
Number of lines
Length of lines
4. Details of EHV Substations              Voltage Wise
                                           400KV      220KV                 132KV   66KV
Number of Substations
Capacity of Substations
(B) Details of Transmission licensee with contract made & Capacity
Name of Transmission Licensee         Capacity   Period      Seller                 Buyer
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(C) Details of Long Term Open Access in Transmission Network
Category           Period             Capacity Interface   Injecting                    Drawee
(in STU/CTU)       (From -------- To) Reserved Periphery   Point                        Point
(D) Details of Long Term Open Access Consumers
Name of Open       Period           Capacity Interface                      Injecting   Drawee
access consumer (From -------- To)  Reserved Periphery                      Point       Point
(E) Name of generating stations supplied power to distribution licensee
Name of Generating Station           Capacity   Contract      Percentage
                                     (in MW)    Quantity          (Share)
1.
2.
3.
(F) Communication Scheme
(i) Communication Scheme
confirmed by SLDC (Ref/Date)
(ii) Details of data communication
      No of RTU(Substation wise
        list to be attached)
      No of Transducers /Sensors
      No of points taped
      Data communication
        redundancy
      Date of Testing
      Acceptance confirmation of
        SLDC
(iii) Details of voice communication
      Mode of communication          (PLCC/any other)
      Type of communication          (Dedicated/Interdependent)
        channel
      Alternate Communication channel
                            Channel 1
                            Channel 2
                           Channel 3
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(G) Planning for load management
                    Number of group Load 3Ph Load 1Ph       Peak Load     Min Load
                                  A
                                  B
                                  C
                                  D
                                  E
                                  F
                                  G
                                  H
(H) Details of Important Customers (Like Military Camp/Airport/Hospital etc.)
                  Name of Customers Location    Feeding S/S Feeding Lines Remarks
(I) Metering Arrangement
(i) Metering Scheme finalized by SLDC (Ref/Date)
(ii) No of Meter Assessed (Category    Assessed Installed        Pending
wise )
      Main Meters
      Check Meters
      Stand by Meters
(ii) Submission of Schematic diagram (To be enclosed herewith)
showing meter number at each
location to be furnished to SLDC
(iv) Joint Testing of meters (         Date/ ( Record Notes enclosed h/w)
Testing date and record notes duly
signed)
(v) Scheduling & Accounting Scheme Ref No/Date
finalized by SLDC(Ref/Date)
(J) Information of Control Centre of Distribution licensee
(i) Name of Control Centre:
(ii) Address of Control Centre:
(iii) Infrastructure Details:
On line data for Monitoring system:
Communication Channel:
Any other :
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(iv) Name and Designation of person responsible for grid operation
             Name
            Designation
            Office Address:
            Permanent Address:
(K) List of Attachment
          o Schematic diagram
          o Power Purchase Agreement
          o Power Transmission Agreement
          o Registration fee receipt
          o Metering details including CT/PT
          o Actual data as per Annexure A.2.1 of State Grid Code
          o Any other supporting documents
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
                                            FORMAT 3
                    APPLICATION FORMAT FOR GRID CONNECTION
                            FOR TRANSMISSION LICENSEE
                       (To be applicable for Transmission Licensee)
General :
Name of Transmission Licensee :
Registered Address of Transmission Licensee :
Area of Supply of Transmission Licensee:
Approval obtained from various agencies
                               (Name /Reference)
                               (Name /Reference)
Legal/Regulatory cases related with approval
of distribution licensee
        (Name/ Case No/Description of Subject)
        (Name/ Case No/Description of Subject)
Proposed date of grid connection :
(A) Details of Transmission licensee
1. Details of Reactors Installed        Voltage Wise
( Voltage wise list to be attached )*   400KV      220KV                    132KV       66KV
3. Details of EHV lines                 Voltage Wise
(List to be attached)                   400KV      220KV      132KV                     66KV
                      Number of lines
                        Length of lines
4. Details of EHV Substations           Voltage Wise
                                        400KV      220KV      132KV                     66KV
Number of Substations
Capacity of Substations
(B) Details of Distribution Licensee with contract made & Capacity
Name of Distribution Licensee           Capacity   Period     Seller                    Buyer
(C) Details of Long Term Open Access Consumers
Name of Open       Period           Capacity Interface                      Injecting   Drawee
access consumer (From -------- To)  Reserved Periphery                      Point       Point
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(D) Name of generating stations connected with Transmission licensee
Name of Generating Station          Capacity   Contract     Percentage
                                    (in MW)    Quantity        (Share)
1.
2.
3.
(F) Communication Scheme
(i) Communication Scheme
confirmed by SLDC (Ref/Date)
(ii) Details of data communication
      No of RTU(Substation wise
        list to be attached)
      No of Transducers /Sensors
      No of points taped
      Data communication
        redundancy
      Date of Testing
      Acceptance confirmation of
        SLDC
(iii) Details of voice communication
      Mode of communication          (PLCC/any other)
      Type of communication          (Dedicated/Interdependent)
        channel
      Alternate Communication channel
                            Channel 1
                            Channel 2
                           Channel 3
(G) Metering Arrangement
(i) Metering Scheme finalized by SLDC (Ref/Date)
(ii) No of Meter Assessed (Category    Assessed Installed        Pending
wise )
      Main Meters
      Check Meters
      Stand by Meters
(ii) Submission of Schematic diagram (To be enclosed herewith)
showing meter number at each
location to be furnished to SLDC
(iv) Joint Testing of meters (         Date/ ( Record Notes enclosed h/w)
Testing date and record notes duly
signed)
(v) Scheduling & Accounting Scheme Ref No/Date
finalized by SLDC(Ref/Date)
                             Gujarat Energy Transmission Corporation Ltd.
   SLDC-Gujarat: Draft Procedure
(H) Information of Grid Substations
(i) Name of Grid Substation:
(ii) Address of Grid substation :
(iii) Infrastructure Details:
On line data for Monitoring system:
Communication Channel:
Any other :
(iv) Name and Designation of person responsible for grid operation
             Name
            Designation
            Office Address:
(I) List of Attachment
          o Schematic diagram
          o Power Transmission Agreement
          o Registration fee receipt
          o Metering details including CT/PT
          o Actual data as per Annexure A.2.1 of State Grid Code
          o Any other supporting documents
                                   -----------x------------x---------------
                             Gujarat Energy Transmission Corporation Ltd.