Request For Inspection: Saudi Aramco Project Inspection Division Inspection Department

This document is a request form for an inspection of offshore maintenance facilities at Dammam Port by Saudi Aramco's Inspection Department. It requests details of the inspection such as date, time, type of inspection needed, facility location, and names of requested inspector and contractor representative. The bottom section is for inspectors to provide findings and sign off once the inspection is complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views1 page

Request For Inspection: Saudi Aramco Project Inspection Division Inspection Department

This document is a request form for an inspection of offshore maintenance facilities at Dammam Port by Saudi Aramco's Inspection Department. It requests details of the inspection such as date, time, type of inspection needed, facility location, and names of requested inspector and contractor representative. The bottom section is for inspectors to provide findings and sign off once the inspection is complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Reset Print

SAUDI ARAMCO
INSPECTION DEPARTMENT
PROJECT INSPECTION DIVISION
DAMMAM PORT
OFFSHORE MAINTAIN POTENTIAL FACILITIES (LTA)
REQUEST FOR INSPECTION
Request Number : Submittal Date:

BI - JO : Request Type Urgent Normal


Inspection Request for: Mechanical Electrical Instrumentation Coating Others

Inspection Date: Inspection Time :


Work Permit Require Yes No Company Inspection Witness point Hold point

Job Description Prior to : Contractor Inspection Witness point Hold point

Facility / Location : DWG No./Rev.:

Inspection and Test Plan ITP Activity No.:


Requested By * SAPMT Use Only **
Name: Name

Signature Signature

Date: Date

Inspection Use Only

Inspector Name: QC Supervisor

Signature Signature

Phone No.: Phone No.:

Findings:

Rescheduled to: / / . Accepted Rejected Cancelled


/ / .
Assigned Inspector SAIR

Name Name
Signature Signature
Date Date

*contractor has verified that the work to be inspected is completed with following specification.
** SAPMT representative has verified that the work is ready for inspection and conforms to the project requirements.