Detail Engineering Desain Jalan Tol Kertosono - Kediri Ringkasan Harga Dasar Biaya Peralatan

The document provides a summary of baseline costs for equipment for the Kertosono - Kediri Toll Road construction project. It includes the hourly fixed costs and operational costs for 20 pieces of construction equipment like bulldozers, excavators, rollers, trucks, and cranes. For example, the hourly fixed cost for a 100-150 HP bulldozer is Rp 220,369.71 and the hourly operational cost is Rp 458,100.

Uploaded by

Diki Firmansah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views47 pages

Detail Engineering Desain Jalan Tol Kertosono - Kediri Ringkasan Harga Dasar Biaya Peralatan

The document provides a summary of baseline costs for equipment for the Kertosono - Kediri Toll Road construction project. It includes the hourly fixed costs and operational costs for 20 pieces of construction equipment like bulldozers, excavators, rollers, trucks, and cranes. For example, the hourly fixed cost for a 100-150 HP bulldozer is Rp 220,369.71 and the hourly operational cost is Rp 458,100.

Uploaded by

Diki Firmansah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 47

DETAIL ENGINEERING DESAIN

JALAN TOL KERTOSONO - KEDIRI


RINGKASAN HARGA DASAR BIAYA PERALATAN
No. BIAYA PASTI OPRASIONAL Total
Kode Jenis Peralatan Satuan Ket
Urut (Rp) (Rp) (Rp)
1 2 3 4 5 6

1 E01 Asphalt Mixing Plant Jam 734,565.68 950,900.00 1,685,465.68 #N/A


2 E02 Asphalt Finisher Jam 172,360.59 950,900.00 1,123,260.59 #N/A
3 E03 Asphalt Sprayer Jam 7,417.38 202,911.25 210,328.63 #N/A
4 E04 Bulldozer 100-150 Hp Jam 220,369.71 458,100.00 678,469.71 #N/A
5 E05 Compressor 4000-6500 L/M Jam 50,370.22 120,945.00 171,315.22 #N/A
6 E06 Concrete Mixer 0.3-0.6 M3 Jam 2,909.23 60,945.48 63,854.71 #N/A
7 E07 Crane 25 - 50 ton Ton Jam 440,739.41 429,875.00 870,614.41 #N/A
8 E08 Dump Truck 3-4 M3 Jam 80,277.54 144,434.38 224,711.91 #N/A
9 E09 Dump Truck 10-14 M3 Jam 160,555.07 288,868.75 449,423.82 #N/A
10 E10 Excavator 100-160 Hp Jam 188,888.32 373,835.00 562,723.32 #N/A
11 E11 Flat Bed Truck 3-4 M3 w/Crane 4 Ton Jam 62,962.77 225,800.00 288,762.77 #N/A
12 E12 Generator Set 250 KVA Jam 114,592.25 383,450.00 498,042.25 #N/A
13 E13 Motor Grader >100 Hp Jam 188,888.32 316,760.00 505,648.32 #N/A
14 E14 Track Loader 75-100 Hp Jam 129,388.50 243,172.50 372,561.00 #N/A
15 E15 Wheel Loader 1.0-1.6 M3 Jam 138,518.10 323,505.00 462,023.10 #N/A
16 E16 Three Wheel Roller 6-8 T Jam 94,684.70 276,086.15 370,770.86 #N/A
17 E17 Tandem Roller 6-8 T. Jam 94,684.70 276,086.15 370,770.86 #N/A
18 E18 Tire Roller 8-10 T. Jam 137,311.68 263,370.00 400,681.68 #N/A
19 E19 Vibratory Roller 5-8 T. Jam 125,925.55 274,665.00 400,590.55 #N/A
20 E20 Concrete Vibrator Jam 9,096.47 35,710.00 44,806.47 #N/A
22 E22 Water Pump 70-100 Mm Jam 2,380.95 45,000.00 47,380.95 #N/A
23 E23 Water Tanker 3000-4500 L. Jam 56,666.50 202,407.00 259,073.50 #N/A
25 E25 Padfoot Roller / Baby roller, Jam 183,021.52 234,889.87 417,911.39 #N/A
26 E26 Jack Hammer Jam 40,424.73 151,358.60 191,783.33 #N/A
28 E28 Concrete Pump Jam 440,739.41 448,200.00 888,939.41 #N/A
29 E29 Trailer 45 Ton / Boogie truck Jam 124,666.29 343,030.00 467,696.29 #N/A
30 E30 Pile Driver + Hammer Jam 503,702.18 557,320.00 1,061,022.18 #N/A
31 E31 Crane On Track 35 Ton Jam 440,739.41 429,875.00 870,614.41 #N/A
32 E32 Welding Set Jam 7,564.63 119,242.00 126,806.63 #N/A

413898533.xls Alat 1
DETAIL ENGINEERING DESAIN
JALAN TOL KERTOSONO - KEDIRI
RINGKASAN HARGA DASAR BIAYA PERALATAN
No. BIAYA PASTI OPRASIONAL Total
Kode Jenis Peralatan Satuan Ket
Urut (Rp) (Rp) (Rp)
1 2 3 4 5 6

33 E33 Bore Pile Machine Jam 315,418.31 591,452.40 906,870.71 #N/A


35 E35 Trailler 15 Ton Jam 166,221.72 457,373.33 623,595.05 #N/A
37 E37 Asphalt/Concrete Cutter Jam 4,548.24 37,671.25 42,219.49 #N/A
38 E38 Concrete Mixing Plant Jam 314,813.86 444,275.00 759,088.86 #N/A
39 E39 Truck Mixers Jam 152,495.84 219,841.00 372,336.84 #N/A
40 E40 Concrete Paver Finisher Jam 1,511,106.55 1,552,900.00 3,064,006.55 300M3/7 Jam
42 E42 Crane 120 Ton Jam 944,441.59 762,800.00 1,707,241.59 Sewa Alat
46 E46 Hydraulic Jack 150 Ton Jam 40,424.73 151,358.60 191,783.33 Sewa Alat
52 E52 Launching Girder Jam 2,048,388.88 1,442,895.00 3,491,283.88 Sewa Alat
53 E53 Alat Pancang Mini Pile Jam 44,073.94 129,120.00 173,193.94 Sewa Alat

413898533.xls Alat 1
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan BULLDOZER 100-150 HP
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 1.50 M3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,750,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,575,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 175,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
^
( 1+i) A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 218,794.71 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,575.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 220,369.71 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 288,750.00 Rupiah 0.165

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 23,400.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 110,250.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 458,100.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 678,469.71 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 19,000.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 16,700.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan DUMP TRUCK 20 TON
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 6.00 Ton
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,275,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,147,500,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 127,500,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 159,407.57 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,147.50 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 160,555.07 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 176,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 71,718.75 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 14,300.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 288,868.75 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 449,423.82 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 14,300.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Water Tanker 3000-4500 L.
2 Tenaga Pw 97.00 HP
3 Kapasitas Cp 5,000.00 Ltr
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 450,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 405,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 45,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 56,261.50 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 405.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 56,666.50 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 133,375.00 Rupiah 0.125

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,132.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 28,350.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 14,300.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 202,407.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 259,073.50 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 14,300.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan EXCAVATOR 100-160 HP
2 Tenaga Pw 160.00 HP
3 Kapasitas Cp 0.90 M3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,350,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 150,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 187,538.32 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,350.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 188,888.32 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 228,800.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 24,960.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 84,375.00 Rupiah 12.5%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 373,835.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 562,723.32 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 19,000.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 16,700.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan MOTOR GRADER >100 HP
2 Tenaga Pw 110.00 HP
3 Kapasitas Cp 1.50 M3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,350,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 150,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 187,538.32 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,350.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 188,888.32 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 169,400.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 17,160.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 94,500.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 316,760.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 505,648.32 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 19,000.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 16,700.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan WHEEL LOADER 1-1.6 M3
2 Tenaga Pw 105.00 HP
3 Kapasitas Cp 1.50 M3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,100,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 990,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 110,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 137,528.10 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 990.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 138,518.10 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 202,125.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 16,380.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 69,300.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 323,505.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 462,023.10 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 19,000.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 16,700.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan TRACK LOADER 75 - 100 HP
2 Tenaga Pw 90.00 HP
3 Kapasitas Cp 1.50 M3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,027,500,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 924,750,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 102,750,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 128,463.75 Rupiah

b. asuransi, dll F 924.75 Rupiah

BIAYA PASTI PER JAM =(E + F) G 129,388.50 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 128,700.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 14,040.00 Rupiah 0.012

3 Perawatan dan perbaikan K 64,732.50 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 243,172.50 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 372,561.00 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 19,000.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 16,700.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan GENERATOR SET
2 Tenaga Pw 145.00 HP
3 Kapasitas Cp 500.00 KVA
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 910,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 819,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 91,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B ' −C )×D E 113,773.25 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 819.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 114,592.25 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 279,125.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 22,620.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 57,330.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 383,450.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 498,042.25 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan VIBRATORY ROLLER 8-20 T
2 Tenaga Pw 90.00 HP
3 Kapasitas Cp - m3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,000,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 900,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 100,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 125,025.55 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 900.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 125,925.55 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 173,250.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 14,040.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 63,000.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 274,665.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 400,590.55 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Sheepfoot Vibr. Roller 5-8 T.
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp - m3
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,453,410,615.89 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,308,069,554.30 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 145,341,061.59 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 181,713.46 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,308.07 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 183,021.52 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 107,250.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 11,700.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 91,564.87 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 234,889.87 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 417,911.39 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Crawler Crane 50 Ton
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 50.00 Ton
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 3,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 3,150,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 350,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 437,589.41 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 3,150.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 440,739.41 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 165,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan (12 . 5 −17 .5 )×B ' K 196,875.00 Rupiah 14%
=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(2 Orang/jam) x U2 M 33,400.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 429,875.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 870,614.41 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Crawler Crane 150 Ton
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 18.00 Ton
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 7,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 6,750,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 750,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 937,691.59 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 6,750.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 944,441.59 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 214,500.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 23,400.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 472,500.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(2 Orang/jam) x U2 M 33,400.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 762,800.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 1,707,241.59 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan STAMPER
2 Tenaga Pw 5.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,000.00 Jam
c. Harga alat B 18,482,223.74 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,000.00 Jam 90%
c. Harga alat B' 16,634,001.37 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 1,848,222.37 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 4,621.50 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 33.27 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 4,654.77 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 7,150.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 780.00 Rupiah 0.012

3 Perawatan dan perbaikan (12 . 5 −17 .5 )×B ' K 2,328.76 Rupiah 14%
=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 45,958.76 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 50,613.53 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Concrete Mixer 0.3-0.6 M3
2 Tenaga Pw 15.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,600.00 Jam
c. Harga alat B 18,482,223.74 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,600.00 Jam 90%
c. Harga alat B' 16,634,001.37 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 1,848,222.37 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 2,888.44 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 20.79 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 2,909.23 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 21,450.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 2,340.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 1,455.48 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 60,945.48 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 63,854.71 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Concrete Vibrator
2 Tenaga Pw 10.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 3.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 50,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 3.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 45,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 5,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.45 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 9,051.47 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 45.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 9,096.47 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 14,300.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 1,560.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 3,150.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L - Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 35,710.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 44,806.47 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Concrete Cutter
2 Tenaga Pw 13.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 3.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 25,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 3.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 22,500,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 2,500,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.45 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 4,525.74 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 22.50 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 4,548.24 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 17,875.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 1,690.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 1,406.25 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L - Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 37,671.25 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 42,219.49 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Concrete paver
2 Tenaga Pw 170.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 12,000,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 10,800,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 1,200,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 1,500,306.55 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 10,800.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 1,511,106.55 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 280,500.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 221,000.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 756,000.00 Rupiah 14%


=
W'
4 Operator =(5 Orang/jam) x U1 L 95,000.00 Rupiah
5 Pembantu operator =(12 Orang/jam) x U2 M 200,400.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 1,552,900.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 3,064,006.55 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Barrier paver
2 Tenaga Pw 120.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 5,000,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 4,500,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 500,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 625,127.73 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 4,500.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 629,627.73 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 165,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 393,750.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(4 Orang/jam) x U2 M 66,800.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 660,150.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 1,289,777.73 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Flat bad truck
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 450,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 50,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 62,512.77 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 450.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 62,962.77 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 143,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan (12 . 5 −17 .5 )×B ' K 31,500.00 Rupiah 14%
=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 225,800.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 288,762.77 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Bar cutter
2 Tenaga Pw 13.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 3.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 70,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 3.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 800.00 Jam 90%
c. Harga alat B' 63,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 7,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.45 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 31,680.16 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 157.50 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 31,837.66 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 18,590.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 2,028.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 11,025.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L - Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 48,343.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 80,180.66 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Bar bending
2 Tenaga Pw 13.00 HP
3 Kapasitas Cp 5.00
4 Alat Baru a. Umur ekonomis A 3.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 70,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 3.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 800.00 Jam 90%
c. Harga alat B' 63,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 7,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.45 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 31,680.16 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 157.50 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 31,837.66 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 18,590.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 2,028.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 11,025.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L - Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 48,343.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 80,180.66 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Trailer 30T
2 Tenaga Pw 160.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 990,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 891,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 99,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 123,775.29 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 891.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 124,666.29 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 220,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 24,960.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 62,370.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 343,030.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 467,696.29 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Pile Driver hammer
2 Tenaga Pw 170.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,000.00 Jam
c. Harga alat B 2,000,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,000.00 Jam 90%
c. Harga alat B' 1,800,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 200,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 500,102.18 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 3,600.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 503,702.18 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 243,100.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 26,520.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 252,000.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 557,320.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 1,061,022.18 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Alat pancang mini pile
2 Tenaga Pw 45.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,000.00 Jam
c. Harga alat B 175,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,000.00 Jam 90%
c. Harga alat B' 157,500,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 17,500,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 43,758.94 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 315.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 44,073.94 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 64,350.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 7,020.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 22,050.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 129,120.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 173,193.94 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Flat Bed Truck w/ Crane 4 m3 / 4 Ton
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 450,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 50,000,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 62,512.77 Rupiah

b. asuransi, dll F 450.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 62,962.77 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 143,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan K 31,500.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 225,800.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 288,762.77 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Batching plant
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 2,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 2,250,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 250,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal E 312,563.86 Rupiah

b. asuransi, dll =
0 . 002× B '
W '
F 2,250.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 314,813.86 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H - Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 23,400.00 Rupiah 0.012


( 1 2. 5 − 1 7 . 5 ) × B '

3 Perawatan dan perbaikan K 196,875.00 Rupiah 14%


=
W '

4 Operator =(3 Orang/jam) x U1 L 57,000.00 Rupiah


5 Pembantu operator =(10 Orang/jam) x U2 M 167,000.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 444,275.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 759,088.86 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Truk mixer
2 Tenaga Pw 68.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,211,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,089,900,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 121,100,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 151,405.94 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,089.90 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 152,495.84 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 97,240.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 10,608.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 76,293.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 219,841.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 372,336.84 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Concrete pump
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 3,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 3,150,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 350,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 437,589.41 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 3,150.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 440,739.41 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 143,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 220,500.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(3 Orang/jam) x U2 M 50,100.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 448,200.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 888,939.41 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Launching Set
2 Tenaga Pw 120.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,200.00 Jam
c. Harga alat B 9,760,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,200.00 Jam 90%
c. Harga alat B' 8,784,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 976,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 2,033,748.88 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 14,640.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 2,048,388.88 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 165,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 18,720.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 1,024,800.00 Rupiah 14%


=
W'
4 Operator =(5 Orang/jam) x U1 L 65,625.00 Rupiah
5 Pembantu operator =(15 Orang/jam) x U2 M 168,750.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 1,442,895.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 3,491,283.88 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Wielding Set
2 Tenaga Pw 50.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 6.00 Tahun
b. Jam kerja dalam 1 tahun W 1,500.00 Jam
c. Harga alat B 50,500,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 6.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,500.00 Jam 90%
c. Harga alat B' 45,450,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 5,050,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.28 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 7,504.03 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 60.60 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 7,564.63 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 71,500.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 7,800.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 4,242.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 119,242.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 126,806.63 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Drilling machine
2 Tenaga Pw 40.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 179,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 161,100,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 17,900,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 22,379.57 Rupiah

b. asuransi, dll F 161.10 Rupiah

BIAYA PASTI PER JAM =(E + F) G 22,540.67 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 57,200.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 6,240.00 Rupiah 0.012

3 Perawatan dan perbaikan K 11,277.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 99,092.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 121,632.67 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Drilling pump
2 Tenaga Pw 30.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 150,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 135,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 15,000,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 18,753.83 Rupiah

b. asuransi, dll F 135.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 18,888.83 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 42,900.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 4,680.00 Rupiah 0.012

3 Perawatan dan perbaikan K 9,450.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 81,405.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 100,293.83 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan

DETAIL ENGINEERING DETAIL


PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Grouting mixer
2 Tenaga Pw 30.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 200,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 180,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 20,000,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 25,005.11 Rupiah

b. asuransi, dll F 180.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 25,185.11 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 42,900.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 4,680.00 Rupiah 0.012

3 Perawatan dan perbaikan K 12,600.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 84,555.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 109,740.11 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Grouting pump
2 Tenaga Pw 30.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 167,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 150,300,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 16,700,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 20,879.27 Rupiah

b. asuransi, dll F 150.30 Rupiah

BIAYA PASTI PER JAM =(E + F) G 21,029.57 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 42,900.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 4,680.00 Rupiah 0.012

3 Perawatan dan perbaikan K 10,521.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 82,476.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 103,505.57 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Shotcrete Equipment
2 Tenaga Pw 25.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 280,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 252,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 28,000,000.00 Rupiah
2 Faktor angsuran modal D 0.31 -

3 Biaya pasti per jam:


a. biaya pengembalian modal E 35,007.15 Rupiah

b. asuransi, dll F 252.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 35,259.15 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 35,750.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 3,900.00 Rupiah 0.012

3 Perawatan dan perbaikan K 17,640.00 Rupiah 14%

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 81,665.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 116,924.15 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Air Compressor
2 Tenaga Pw 45.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,600.00 Jam
c. Harga alat B 320,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,600.00 Jam 90%
c. Harga alat B' 288,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 32,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal E 50,010.22 Rupiah

b. asuransi, dll =
0 . 002× B '
W '
F 360.00 Rupiah

BIAYA PASTI PER JAM =(E + F) G 50,370.22 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 64,350.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 7,020.00 Rupiah 0.012


12 . 5 17 . 5 B '

3 Perawatan dan perbaikan


( − ) ×

K 25,200.00 Rupiah 14%


=
W '

4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah


5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 120,945.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 171,315.22 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Pompa Air
2 Tenaga Pw 5.00 HP
3 Kapasitas Cp 40.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,600.00 Jam
c. Harga alat B 60,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,600.00 Jam 90%
c. Harga alat B' 54,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 6,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 9,376.92 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 67.50 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 9,444.42 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 7,150.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 650.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 4,725.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 13,125.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 11,250.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 36,900.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 46,344.42 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Alat pancang PVD
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 18.00
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 1,504,900,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 1,354,410,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 150,490,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 188,150.94 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,354.41 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 189,505.35 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 143,000.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 15,600.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 94,808.70 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 289,108.70 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 478,614.05 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Asphalt Sprayer
2 Tenaga Pw 6.00 HP
3 Kapasitas Cp 800.00
4 Alat Baru a. Umur ekonomis A 6.00 Tahun
b. Jam kerja dalam 1 tahun W 1,000.00 Jam
c. Harga alat B 29,451,447.79 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,000.00 Jam 90%
c. Harga alat B' 26,506,303.01 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 2,945,144.78 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 7,364.37 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 53.01 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 7,417.38 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 8,580.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 936.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 3,710.88 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L - Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 29,926.88 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 37,344.26 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Asphalt Mixing Plant 60 Ton
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 60.00
4 Alat Baru a. Umur ekonomis A 10.00 Tahun
b. Jam kerja dalam 1 tahun W 1,200.00 Jam
c. Harga alat B 3,500,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,200.00 Jam 90%
c. Harga alat B' 3,150,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 350,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 729,315.68 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 5,250.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 734,565.68 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 214,500.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 23,400.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 367,500.00 Rupiah 14%


=
W'
4 Operator =(5 Orang/jam) x U1 L 95,000.00 Rupiah
5 Pembantu operator =(15 Orang/jam) x U2 M 250,500.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 950,900.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 1,685,465.68 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Asphalt Finisher 60 Ton
2 Tenaga Pw 30.00 HP
3 Kapasitas Cp
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 1,600.00 Jam
c. Harga alat B 1,095,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,600.00 Jam 90%
c. Harga alat B' 985,500,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 109,500,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A ' −1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 171,128.72 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,231.88 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 172,360.59 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 42,900.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 4,680.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 86,231.25 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(3 Orang/jam) x U2 M 50,100.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 202,911.25 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 375,271.84 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Tandem Roller 8 Ton
2 Tenaga Pw 90.00 HP
3 Kapasitas Cp
4 Alat Baru a. Umur ekonomis A 6.00 Tahun
b. Jam kerja dalam 1 tahun W 1,800.00 Jam
c. Harga alat B 758,516,491.85 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 6.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,800.00 Jam 90%
c. Harga alat B' 682,664,842.66 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 75,851,649.18 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.28 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 93,926.19 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 758.52 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 94,684.70 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 173,250.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 14,040.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 53,096.15 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 276,086.15 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 370,770.86 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Pneumatic Tire Roller 10 Ton
2 Tenaga Pw 95.00 HP
3 Kapasitas Cp
4 Alat Baru a. Umur ekonomis A 6.00 Tahun
b. Jam kerja dalam 1 tahun W 1,800.00 Jam
c. Harga alat B 1,100,000,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 6.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 1,800.00 Jam 90%
c. Harga alat B' 990,000,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 110,000,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.28 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 136,211.68 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 1,100.00 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 137,311.68 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 135,850.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 14,820.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 77,000.00 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 19,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 16,700.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 263,370.00 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 400,681.68 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Bore Pile Machine
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp
4 Alat Baru a. Umur ekonomis A 5.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 2,504,800,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 5.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 2,254,320,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 250,480,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.31 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 313,163.99 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 2,254.32 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 315,418.31 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 288,750.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 23,400.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 157,802.40 Rupiah 14%


=
W'
4 Operator =(2 Orang/jam) x U1 L 38,000.00 Rupiah
5 Pembantu operator =(5 Orang/jam) x U2 M 83,500.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 591,452.40 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 906,870.71 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan
DETAIL ENGINEERING DETAIL
PEMBANGUNAN JALAN TOLL KEDIRI - KERTOSONO

URAIAN ANALISA ALAT

No Uraian Kode Koef. Satuan Ket.

A. URAIAN PERALATAN
1 Jenis peralatan Jack Hydrolic
2 Tenaga Pw 10.00 HP
3 Kapasitas Cp
4 Alat Baru a. Umur ekonomis A 3.00 Tahun
b. Jam kerja dalam 1 tahun W 2,000.00 Jam
c. Harga alat B 222,200,000.00 Rupiah
5 Alat yang dipakai a. Umur ekonomis A' 3.00 Tahun 90%
b. Jam kerja dalam 1 tahun W' 2,000.00 Jam 90%
c. Harga alat B' 199,980,000.00 Rupiah 90%

B. BIAYA PASTI PER JAM KERJA ALAT


1 Nilai sisa alat = 10% X B C 22,220,000.00 Rupiah
2 Faktor angsuran modal i×( 1+i ) ^
A' D 0.45 -
=
( 1+i) ^
A '−1
3 Biaya pasti per jam:
a. biaya pengembalian modal ( B '−C )×D E 40,224.75 Rupiah
=
W'
b. asuransi, dll 0 . 002×B ' F 199.98 Rupiah
=
W'
BIAYA PASTI PER JAM =(E + F) G 40,424.73 Rupiah

C BIAYA OPERASI PER JAM KERJA


1 Bahan bakar =0.125-0.175 (Lt/HP/Jam) x Pw x Ms H 14,300.00 Rupiah 0.13

2 Pelumas =0.01-0.0.012 (Lt/HP/Jam) x Pw x Mp I 1,560.00 Rupiah 0.012

3 Perawatan dan perbaikan ( 12 . 5 −17 .5 )×B ' K 13,998.60 Rupiah 14%


=
W'
4 Operator =(1 Orang/jam) x U1 L 38,000.00 Rupiah
5 Pembantu operator =(1 Orang/jam) x U2 M 83,500.00 Rupiah

BIAYA OPERASI PER JAM = (H+I+K+L+M) P 151,358.60 Rupiah

D TOTAL BIAYA SEWA ALAT / JAM =(G + P ) S 191,783.33 Rupiah

E LAIN-LAIN
1 Tingkat suku bunga i 17.0% % / tahun
2 Upah operator / supir U1 13,125.00 Rp. / Jam
3 Upah pembantu operator / Pmb. Sopir U2 11,250.00 Rp. / Jam
4 Bahan bakar bensin Mb 11,000.00 Liter
5 Bahan bakar solar Ms 11,000.00 Liter
6 Minyak pelumas Mp 13,000.00 Liter
7 PPN diperhitungkan pada lembar rekapitulasi biaya pekerjaan