ST/SC DEVELOPMENT DEPARTMENT
ODISHA
             INTEGRATED TRIBAL DEVELOPMENT AGENCY,
                          NILAGIRI.
                       TENDER    SCHEDULE
Tender document
For the work         :- Const. of Two storied 300 seated Boy’s Hostel
                        Building at Banabhuin High School .
   D.T.C,N      :- No. 936 /2011-12
CONTRACTOR                            PROJECT ADMINISTRATOR
                         GOVERNMENT OF ODISHA
           OFFICE OF THE PROJECT ADMINISTRATOR, ITDA,NILAGIRI
                          DETAILED TENDR CALL NOTICE
1.   Sealed tenders are invited from registered Contractor of P.W.D. / Irrigation / P.H.D. of
     class…”A” & “Special class” Contractors in prescribed form to be eventually drawn
     in P.W.D. Form F-2 and will be received by the Project Administrator, ITDA, Nilagiri
     upto 3.00P.M. on date 19.12.2011 . for the work Construction of Two storied 300
     seated Boy’s Hostel Building at Banabhuin High School with an estimated
      cost Rs. 1,50,00000/- .
     ( Rupees one crore fifty lakhs only. ) .
2.    The prescribed form along with the documents is obtained from the office of the
     undersigned on payment of Rs10000/- + 4% Only per each set. This amount is not
     refundable. Department will not be responsible if there is any delay in respect of
     tender documents by the intending Contractors sent by the department through
     registered post or speed post / courier service . not reach the undersigned office
     by the last date and time as mentioned in D.T.C.N, , their offers will not be
     considered on any account even if, the tender documents were despatched by the
     tenderers before the due date.
3.   No tenderers should furnish their tender in their own manuscript papers.
4.   The work is to be completed in all respect within 10(ten) calendar months from the
     date of issue of the work order. Tenders whose tender is accepted must submit
     programme of works immediately after issue of work order for approval of Engineer-
     in-Charge.
5.   Bid documents consisting of plans, specifications, the schedule of quantities
     and   the term         and conditions of contract and other necessary
     document can be seen in office of under signed during office hours
     everyday except on Sundays and Public holidays till last date of sale of tender
     papers .Interested bidders may obtain further informations at the said
     address can down loaded from website address “www.baleswore.nic.in”.
CONTRACTOR                                     PROJECT ADMINISTRATOR
6.             Bid document is obtainable from O/O-P.A,I.T.D.A, Nilagiri and must be
      accompanied by EMD amount mentioned above payable at any Nationalized
      Bank, at Nilagiri as per DTCN             and drawn in favour of         Project
      Administrator, I.T.D.A, Nilagiri. The E.M.D. should be in form of KVP/T.D/
      Bank Draft/NSC/PassBook etc.
7..   The sale of the Bid documents shall start from 13.12.2011 and close
      on17.12.2011 at 5.00 P.M . Bids shall be received in office of under signed only
      till 3.00 P.M hours on 19.12.2011 along with duly attested, Xerox copies of
      (a) valid contract license ,(b) Pan card, (c)Vat clearance in form NO-612.
      Alongwith original No relation certificate and Affidavit of Authenticity of
      documents. However labour license shall have to be submitted at the
      time of Agreement .
8.      Bids must be send through Regisrered post / speed post having
       identification NO- 02/2011—12 . P.A.,I.T.D.A,Nilagiri .
.
9.    Bidding documents requested by mail will be despatched by Regd/speed post
      on payment of an extra amount of Rs.500/- over the cost of tender paper.
      The authority will not be held responsible for the postal delay if any or non -
      receipt of same.
10.    Bidding documents downloaded from website will have to pay Rs10,000/-
      (Rupees Ten thousands only) towords cost of tender paper should be in form
      of KVP/T.D/ Bank Draft/NSC/PassBook etc payable at any Nationalized
      Bank, at Nilagiri as per DTCN          and drawn in favour of           Project
      Administrator, I.T.D.A, Nilagiri. .
11.   The Bid documents will be opened on 19.12.2011 at 4.00 P.M hours in the
      office of undersigned in the presence of bidder or his authorized
      representative.
12.   The bids quoting less than 10% of the estimated cost will have to deposit
      differential amount of 90% of amount put to tender and tendered value in
      shape of bank draft . However, the bids has to be attached with analysis of
      quoted rates against each item .
13.   The SC/ST bidders shall have to furnish XEROX COPY OF CASTE
      CERTIFICATE and an Affidavit mentioning he has not availed any such
      preference within last three months at the time of submission of document.
14.   The      Engineer     bidders seeking exemption of            EMD must submit
.     their original license at the time of opening of tender papers,
      With the no. of work awarded to them in same financial year .
15.      Transfer or adjustment of EMD & ISD amount with other works
      will not be entertained .
16.   Incase the quoted amount is less than 10 % of the tender call amount then
      bidder      has to submit item wise analysis without which the tender will be
      liable for rejection.
17.   By submission of a tender for the work, a tenderer will be
      deemed to have satisfied himself by actual inspection of the site and locality
      of the work, about the quality and availability of the required quantity of
      materials . The tendered Rates will be adequate to complete the work as per
      specification with quantity. He has to bear all difficulties if encountered during
      progress of work. No extra charges or payments will be entertained for any
      reason thereof, in case Contractor Claims later on to have misjudged as
      regards to availability of materials, labour, and other factors.
CONTRACTOR                                   PROJECT ADMINISTRATOR
18.      The contractor after receiving of work-order, has to furnish a
.      work programme with a view to complete the work in stipulated
       Time, any deviation to this will be heavily penalized .
19.    The E.M.D will be forfeited if the contractor failed to sign the
       agreement after acceptance of tender with the stipulated
       period . Incomplete tender/ tenders will be rejected.
20.    The authority reserves the right to reject any/all tenders
       without assigning any reason thereof.
21       ll the tenders received will remain valid for a period of Ninety days from the
.       date of issue of receipt of tenders. Validity of tender can also be extended
        if agree to by the tenders and the dept
    22 The rates should be written in both words and figures and in decimal coinage, and
       the units in words. In case of discrepancy in rates between words and figures the
       amount in words will prevail. The tender should also show the total of each item and
       the grant total of whole tender. The tender shall be written legibly & free from using
       erasures, overwriting or converse of figures corrections where unavoidable should be
        made by crossing out initiating, dating rewriting.
    23.      The tenderers carefully study the drawing and specification, liable to contract
    and all the documents which form parts of the agreement to be entered into the
    accounted tenders and detailed specifications of Orissa and other relevant specifications
    and drawing which are not available for sale. Complaints at future date, the plans and
    specifications have not seen cannot be entertained.
    24 . the time of submitting the tender samples of stones metal and chips to be used to be
       deposited in settled baos duly labeled, nothing the made of quarry dated initial by the
       tenders in the office of the undersigned.
25     It must be definitely understood that the Govt. accepted any responsibility for the
        correctness and completeness of the trial borings shown in the Cross Sections.
26     Each tenderers must pay an earnest money of Rs 1,15,000.00 along with the form of
        State Govt. Loan bonds or National Saving Certificates, Postal Pass Books pledge to
        the Project Administrators, ITDA, Nilagiri in no other form.
27     The tender will not be considered unless the tenderers enclosed a true copy of the
        Income Tax Clerance Certificate , valid       labour   license and Vat     Clearance
        Certificate along with the tender and Original Certificates are produced before the
        Officer concerned at the time of opening of the tender.
28     The tenderer may at his, option quote reasonable rate for each items of work carefully
        so that the rate for one should be un-workable low and for other too high.
29     The tender containing extraneous conditions not concerned by the tender notice are
        liable for rejection and quotations should be strictly in accordance with the items
        mentioned in the call notice. An change in the wording will not be accepted.
CONTRACTOR                                       PROJECT ADMINISTRATOR
30   Letters etc. found in the tender raising or Lowering the rates of detailing with the
      points in connection with the tender will not be considered.
31   A schedule of quantity accompanies the tender notice. It shall be definitely
     understood the Govt. does not accept any responsibility for the corrections of this
     schedule and that this schedule is liable for alteration or omissions deductions or
     additions as set forth in the condition of contractor. Such omissions, deductions
     additions or alterations shall in no way in all date the contract and no extra monetary
      compensation will be countersigned.
32   The earnest money will be retained in the case of successful tenders and will be dealt
     with as provided in the contract form. The earnest money will be refunded to the
     unsuccessful tenders in application after intimation is sent on rejection of their
      tender.
33   The tenders whose tender is selected for acceptance and who has not fixed deposit
     with the Govt. of Orissa, shall within a period of seven days upon written instruction
     being given to him for acceptance of his tender, make an initial security deposit in
     the form of State Govt. Loan bonds of the Orissa State or National Saving
     Certificates and in no other form which including the amount already deposit as
     earnest money shall be 2% of the value of the tenders amount and sign the
     Agreement in the P.W.D. Form No. F-2 Schedule LLV No. CL fulfillment of the
     contract in the office of the undersigned as directed. This security deposit together
     with the earnest money and the amount withheld according to the provision of F-2
     Agreement shall be retained as security for the due fulfillment of the of this
      agreement.
34   Failure to enter into the required agreement and to make the security deposit as
     above shall enter for forfeitere of the earnest money. No tender shall be finally
     accepted until the required amount of security money deposited. The written
     Agreement to be executed in        between the contractor and the Govt. so         the
     Contractor shall be deemed to be unaccepted until the Agreement first sign by the
     Contractor and then by the proper officer unlessotherwise mentioned. The
     Government security will be refunded six months after completion of the work and
      payment of the final bill.
35   The contractor should be liable to fully identify the department for      payment of
     compensation Workman Compensation Act VIII of 123 on account of workman
     employed by the contractor and full amount of compensation paid will be received
     from the Contractor.
CONTRACTOR                                    PROJECT ADMINISTRATOR
36   Tenderers as they are registered labour license holders are           required to abide
      by the fair wages clause labour Department Letter No. GA-VIIIR 18/5225 dt. 25.2.85
      and No. 11M/56.62/28842(5) dt. 27.9.81. and all enacted labour rules alongwith
      enhanced labour rates .
37   The tenderer shall bear cost of various incidental sundries and contingencies
      necessitated by the work fall within the following work similar categories.
      a) Rent, Royalties and other charges of materials, Octroi/ vat duty all other taxes
         including sales taxes, ferry tools, Conveyance, Charge and other costs on
         account of land and building including temporary buildings required by the tender
         of the collection of materials storage, housing of staff other purpose for the work
         no rent will however by payable to Government for temporary occupation of land
         owned by the Government at the site of work.
      b) Labour camp or huts necessary to a suitable sale including conservancy and
         sanitary arrangements therein to the satisfaction of the local Health Authorities.
      c) Fees and dues levies by Municipal canal or water supply whenever available for
         the staff and labour as well as for the.
      d) Fees and dues levied by Municipal or water supply authorities.
      e) Suitable equipments and warning apparatus for the labour engaged for the risky
         operation.
      f) Suitable fencing barriers, signals, including paraffin and electric signals where
         necessary at works and approach in order to protect the public employees from
         accident.
      g) Compensation including cost of any suit for injuring to persons or property due to
         neglect or any major precaution also of which become payable due to operation
         of the Workman Compensation Act.
      h) The contractor has to arrange adequate lighting arrangement for night works
        over necessary at his own cost.
38   No payment will be made for bench marks, levels pillar profiles and benching and
     leveling the ground if required. The rates to be quoted should be for finished items of
     work inclusive of carriage of a materials and all incidental items of work.
39   After the work is finished all surplus, materials should be removed from the site work
     Preliminary works such as vatsmixing platforms etc. should be dismantled and all
     materials removed from the site and premises left neat and clean and this should be
     inclusive in the rates.
40    It should be understood clearly that no claims whatsoever will be entertained in
     regards extra items of works extra quantity of any items, besides estimated amount. A
     written order must be obtained from the undersigned officer and rates settled before
     the extra items of works or extra quantity of any item of work is taken up.
CONTRACTOR                                      PROJECT ADMINISTRATOR
41   The tender shall have to abide by the C.P.W.D. safety code rules introduced by the
     Govt. of India Ministry of Work Housing and supply in their standing order No. 44 to 55
     dated 25.11.57 which can be seen in the office of the undersigned on working days.
42   No part of the contract shall be subject without written permission of the Project
     Administrator,I,T.D.A,Nilagiri or transfer be made by the Power of Attorney authorizing
     others to receive payment on the contractor’s behalf.
43   If further necessary information is required, the Engineer-in-Charge will furnish such it
     must be clearly understood that tenders must be received in order and according to
     instructions
44   (a) The contractor shall have to furnish a certificate along with the tender to effect
           that he is not related to any officer of ITDA of the rank of Asst. Engineer and
           above and any officer of the rank of Asst. Secretary and above of he Works
           Department.
     (b)   Each tender must submit along with the tender a note regarding his previous
         experience on construction of bridge. The following detail must be given.
         (a) Name of the Bridge                 (e) Type of Bridge
         (b) Estimated Cost                     (f) Date of Commencement
         (c) Total length                       (g) Date of completion
         (d) Length of each span                (h) Other details if any
45   Tenderers are requested to go through each clause of P.W.D. F-2 agreement
     carefully in addition to the clause mentioned there in before the tendering.
46   All reinforced cement concrete works should be confirmed to Orissa detailed standard
     specification I.R.C. and I.R.T. and I.S.I. code.
47   Shuttering and centering shall be with seasoned sal wood plants the issued of which
     shall be the writing suitable sheeting and make leak proof water tight of alternative
     steel shuttering and centering may be used.
48   The department will have the right to inspect the scaffolding centering and shuttering
     made for the work and can reject partly or fully such shuttering if found defective in the
     opinion.
49   Concrete should be machinery mixed unless otherwise ordered in writing by the
     Project Administrator. The contractor should arrange his own concrete mixture
     (Machine) Vibrators Pumps etc. for this purpose at his own cost.
50    Cement shall be used by the bags weight of one bag of cement being taken as fifty
     (50)kgs.
51    The following materials will not be supplied by the Department to the Contractor at
     P.W.D. Store at…the rate inclusive of store as noted against each. After issued it will
     be the contractor’s responsibility for safe custody and upkeep of materials. He has
     also to bear incidental charges such as Transport, storage, handling and return of
CONTRACTOR                                       PROJECT ADMINISTRATOR
     empty cement bags at the issuing sore. His rate quoted for the work is to be inclusive
     of all such charges.
     a) Cement @ Rs……………………… (Rupees                                     )per
         Quintal excluding cost of Empty cement Bags
     b) M.S. Rods @ Rs……………………. (Rupees                                   )per
     c) Hume pipe will be supplied by the Deptt. At P.W.D. store and the carriage of hume
        pipe will be made by the contractor at his own cost.
     d) Maxphalt will be issued @ Rs……………………(Rupees
                    )per MT excluding cost of container and the carriage with packing the
        buckltument from vats and packing into the drum will be made by the contractor at
         his own cost.
52   In the event of any delay in the availability of materials / unavoidable reason if the
     work progress is hampered then reasonable extension of time will be granted on
     the application of the contractors. But no claim for compensation will be entertained
     under any circumstances.
53   The contractor will be responsible for the loss or damage of any departmental
     materials during transit and in the execution of the works due to reason whatsoever
     and the cost and the cost of such materials will be recovered from the bill at stock
     issue or market rate’s is higher.
54    If the contractor removes any Government materials supplied to him from the site of
     the work view to dispose of the same disponestly he shall be in addition to any other
     liability, civil or criminal arising out of his concrete be liable to pay penalty equivalent
     to five times the price of the materials according to the rate stioulat in clause 40
     penalty so imposed shall be recovered at any time from any such that may be then or
     at any time thereafter become due to the contractor or from his security deposit or
     from the proceeds of sale thereof.
55    The selected tenders may take delivery of departmental supply according to his mean
     for the work issued by the Assistant Engineers. The tenders shall make all
     arrangements for proper storage of materials but no cost for rising shed for store of
     materials and pay of watchman etc. will be borne by the department. They are all to
     borne by the Contractor. The department is not responsible for considering the theft of
     materials at site. It is contractor’s risk. Under any such plea, if the tender store the
     work shall have to pay full penalty as per clause of the F-2 contract.
56   The department will have the right to supply at any time in the interest of work any
     departmental materials to be used in the work and contractor shall use materials
     without any controversy or dispute on that account. The rates of issue of such
     materials will be at stock issue rates inclusive of storage charges or rate fixed by
     department or current schedule of rates ever is higher.
CONTRACTOR                                        PROJECT ADMINISTRATOR
57   All materials which are to be supplied from P.W.D. stock will be as per availability of
     stores and the contractors will have to bear the charges of straightening, cutting,
     jointing, welding etc. less than 3-0” in the length will be accepted back as surplus and
     all those will be the contractor’s property. After the issue from the P.W.D. store the
     materials will be under custody of the contractor and the contractor will be responsible
     for its safety and storage Cut pieces more than 3’-0” in length will be return the
     contractor at the issuing store without any conveyance charges.
58   The contractor should at his own cost arrange, necessary tools and plants required
     efficient execution of the work and the rates quoted should be inclusive of the running
     charges of slant and cost of consumables.
59   After completion of the work contractor shall arrange at his own cost all requested
     equipments for testing of bridge and bear the entire cost of test.
60   Empty cement bag to be returned in good and serviceable condition failing which
     Rs.3.00 (Rupees three only) will be recovered per bag from the Contractor.
61   Measurement of earth work in road embankments will be done the P.L. measurement
     after the earth is well consolidated in rolling with power roller or sheep foot and no
     extra payment will be made in the jungle clearance for taking earth from borrows
     areas. Earth work for cutting wil be accordingly be utilized in filling.
62   The stock and road metal and gravel will be measured in box of 1.5M x 1.5M which
     will be taken as 1.5m x 0.7m-1 cum. The contractor will be measured in suitable
     stacks with deduction for the roads @ 1/6 volume or more depending upon the
     losseness stacking which will be determined on actual observation and deduction.
63    In the event of delay in the supply of departmental materials road roller for
     unavoidable reason, reasonable extension of time will be granted to the application of
     the contractor but no claim for compensation will be entertained under any
     circumstances.
64   The tender should furnish alongwith their tender of works which are at present in their
     hand in the prescribed proforma enclosed herewith.
65   Sinking of well shall be measured from bottom f well cap to bottom of cutting edge.
66   A methods of sinking including penumating sinking by employment of drivers and
     other equipment shall be including in the rate removal of any trees, legs of tress or
     isolate boulders etc. shall also be included within the rate of sinking.
67    The depth of foundation indicated on the drawing are provisional but these may be
     altered if necessary in the light of the nature at site indicated by boring which must be
     taken in advance of the actual execution of the foundation.
68    When resort has to be made to pneumatic sinking the necessary for the same and
     rates thereof shall be decided by the authority accepting the tender.
CONTRACTOR                                      PROJECT ADMINISTRATOR
69   Construction of cofferdam or islands or the works of open excavation or dressing
     required laying welcurbs shall be included in the rate of well shinking.
70    For concreting the bottom plugs of well under water the method of pouring concrete
     should be either with baskets of boxes or bags as will be directed by Engineer-in-
     Charge.
71   No claim will be entertained in respect of difficulty due to sandblowing met with during
     sinking of well.
72   No parts of the bearings for the superstructure shall be allowed to rest on the Nos of
     the piers.
73    Cast steel roller and rocker bearings shall be to IRC specification (Provisional) 1950
     and shall be designed according to the formula P+1420 ‘D’ is the load in Ibsinches
     length of a roller of “D” is the diameter of the roller in inches if the number of roller in
     any assembly or the roller in inches.
74   The use of mild steel rollers and pins may be permitted provided these are made
     either of Class III Class IV Steel in accordance with IRC specification M-3 Expansion
     rollers may be alternatively be turned from carriage and wages axes those may be
     designed according to the formula P+0082d, where p is the permissible load in tons
     per inch length of a roller and “D” the diameter of the roller in inches.
     If the number of rollers in an Assembly of rollers excess to the permissible stress on
     each roller shall produced by 20%.
75   The use of motor pads or R.C.C. Rubber or Neoperance bearings shall not be
     allowed on bridges.
76   Mild steel mesh reinforcement shall be provided in the concrete of girder or of the
     caps of piers and abutments immediately in concrete with the bearings to ensure
     proper distribution of heavy loads.
77   Lugs and groves shall be provided in the bearings to prevent them sekwing or getting
     out of alignment.
78   Sliding plate bearings shall normally be from only one metal and a combination of
     plates or different of metals which are likely to result in electronic action shall be
     permitted. For example copper plate interposed between steel plates will not be
     allotted.
79   In section by Director General of Suppliers and Disposal of bearings during
     manufacture and X-ray or Grance-ray examination of thickness more then 8 inches
     and load testing of bearing of considered necessary shall have to be carried out at the
     Contractor cost. The same procedure of testing may have to be followed for ribbed
     bearing manufactured by welding.
80   It should be clearly understood that :-
     a) The joins of the bars are to be provided with laps well or bottnuts as will be
      directed by the Engineer-in-Charge.
CONTRACTOR                                        PROJECT ADMINISTRATOR
     b) Concrete tests specimen (Whether plain or reinforced) for the test shall be taken
        by a representative of the Contractor in the presence of a responsible officer of the
        rank not lower than the Assistant Engineer, or Sub-Divisional Officer. If so desired
        by the Engineer-in-Charge.
     c) Test specimens shall be formed carefully in accordance with the standard method
        of test specimen and no pleas be entertained late on the grounds that the casting
        of the test specimen was faulty and that the result of the test specimen did not give
        a correct indication of the actual quantity of concrete.
     d) The construction of a well steining by injecting cement grout in coarse aggregate
        place in position shall not be permitted.
     e) The construction of well steining by injecting cement grout in coarse aggregate
        place in position shall not be permitted.
81   a) The minimum reinforcement I.C.C. well steing should be 0.15% one the cross
        sectional area
     b) The reinforcement I.C.C. well curbshould not be less than 1% (one percent) of the
        cross sectional area to with sand the hoop tension developed due to soil pressure.
82   Power steam Road Roller will be supplied at the work site hire at a rate of
     Rs……………rupees………………) per hour without POL roller cover and above the
     running charge excluding day in a week for cleaning. If the Roller due to the fault of
     the contractor remains idle, the contractor have pay the chargeRs……………
     (Rupees………………………………………….) plus the pay of the roller due shall be
     cleaner for every idle day. Running charge will should also be paid by the contractor.
     The roller shall be returned to the Deptt., in good condition at the place of delivery
     other work without any charges.
83   All empty Tardurms should be returned to the issuing store in good condition at the
     cost of the contractor failing which the cost thereof shall be recovered @Rs……
     (Rupees……………………………) only from the contractor per each drum.
84   Thickness cement concrete (1:3:6) is to plugging should be as the departmental
     drawings.
85   Concrete of strength below. 80% of the required strength (as determined by actual
     tests shall not be accepted. Concrete of strength upto 80% of the required strength
     may be accepted as substandard work with a penalty of 40% of the value of the work
     at the schedule of rates in force during the actual execution of the work, which such
     concrete is actually used provided the use of this under strength concrete is confirmed
     to such members and in such quantities that the safety of the structures is not
     enraged. The penalty so imposed shall be recovered from any sum that may be than
     or at any time thereafter become due to the contractor or from his security deposit.
CONTRACTOR                                      PROJECT ADMINISTRATOR
86   In well sinking maximum tolerance permissible in the titles is 1;60 and t\shifts is 6” (six
     inches) where it is not featible to work these tolerance the contractor shall carry out
     suitcase remedial as may be directed by the Engineer-in-Charge over come the
     adverse effects of filts and shift without any extra cost of measurement and for this
     type of substandard work a penalty of Rs. 10,000/- (Rupees ten thousand) only for
     single or set well under one pier or an abutment shall be imposed on the contractor
     and will be recovered from any sum that may be thnor at any time thereafter become
     due him or security deposit.
87   No claim for carriage of water whatsoever will be entertained.
88   I.R.R. will be supplied by deptt. on requisition of the contractor on usual @
     Rs……………………… (Rupees………………………………………….) per day and the
     contractor bears the responsibility for its charge from and to the place of delivery in
     good condition.
89   The contractor shall if so required by Engineer-in-Charge employ one or more
     Engineering Graduates or diploma holders as apprentices at his own cost if the cost of
     the work as shown in the tender exceeds Rs.2,50,000/-. The apprentices will be
     selected by Chief Engineer. The period of employment will commenced within one
     month after the date of work is complete. The stipend to be paid to the apprentices-
     should not less than Rs.200/- per month in case Graduate Engineer, and not less than
     Rs. 150/- PM in case of Diploma Holders. The number of apprentices to be employed
     should be fixed by the Engineer in a manner so that total Expenditure do not exceed
     one percent of the tendered cost of the work.
90   List of tools and plants in possession of the contractor as to be furnished.
91   It is responsibility of the contractor to procure store explosive required for blasting
     operation Deptt. may tender necessary possible helps for procuring explosive licence.
92   The Orissa Construction Corporation Limited will be allowed price for the performance
     on the lowest quotation or tender as laid down in works and Transport Department
     Resolution No. 285 dated 17.4.74.
93   Under no circumstances interest is chargeable for the dues any additional dues if any
     payable for work.
94   Where the contractor quoted a abnormally low rate for any individual items, the
     payment against the remaining items withheld to the extent of flow percentage
     between the low rates items and schedule rate is fully executed.
95   Lime will be used in lace of Cement during executing in suitable prop in lime of the
     works where cement can be subsisted by lime.
96   When any item of work not specifically covered an accepted tender or contract is to be
     executed. It should be taken up departmental through job or place workers on
   Nominal Muster Rolls at the prevailing schedule of rates or the rates approved by
CONTRACTOR                                 PROJECT ADMINISTRATOR
     Superintending Engineer, unless there is no record the prior written contractor to
     execute such items of works at the prevailing schedule of rate or at the rates
     approved by the Superintending Engineers.
97   Certificate of No-Relationship.
     I/We hereby certify that I/We am/are not related to any Officer of P.W.D. of the rank of
     Assistant Engineer and above any Officer of the rank of Assistant Secretary and
     above of the Works Department. I am also aware that if the facts subsequently proved
     to be false my/our contract will be rescinded with forfture of P.W.D. and total security
     deposit and I/we shall be liable to make good the loss or damage resulting from such
     cancellation.
     I/We also note that non-submission of this certificate will tender my/our tender liable
     for rejection.
                                  TENDER SCHEDULE
Detail Tender call Notice Number :-936/ITDA dt: 09.12.2011
Name of the Project               :- Const. of Two storied 300 seated Boy’s Hostel
CONTRACTOR                                      PROJECT ADMINISTRATOR
                                                    Building at Banabhuin High School .
           Estimated Cost                        :- Rs.150,00000/-
           Amount put to Tender                  :- Rs. 11324407.00 /-
           Date of Sale of Tender Paper          :- 13.12.2011—17.12.2011
           Date of Receipt of Tender Paper       :- 19.12.2011 upto 3.00 P.M
           Date of opening of Tender Paper :- 19.12.2011 at 4.00 P.M.
           Earnest Money to be Deposited   :- Rs. 1,15,000/-
           Class of Contractor             :- ‘A’ & ‘SPECIAL CLASS’
           Cost of Tender Paper                  :- Rs.10000/-+4%VAT
           Stipulated period of Completion
           of project                            :- 10 months
Sl.   Description of Items                             Quantit   Unit    Rates to be Quoted
No.                                                    y                 Rate         Amount
      ( GROUND , FIRST & SECOND
      FLOOR)
1.    Excavation of foundation trenches and
      column foundations and pits in all kinds of      390.13    %cu     5400.00      21066 .00
      soil within a lift of 1.5 mtrs including         cum       m
      dressing the sides shoring (if necessary),
      bailing out water and leveling the bed and
      depositing the excavated material away from
      the site within an initial lead of 50 mtrs ,
      including cost of all labour, sundries, tools
      and plants etc., complete as per the direction
      of the Engineer-in-charge.
2.    Filling in foundation trenches and plinths
      with sand well watered and compacted and
      dressed and leveled to proper gradient           311 .73   Cum     232.30       72414 . 00
      including cost of all materials, labour,         cum
      conveyance, loading and unloading, taxes,
      royalties, watering, sundries, tools and
      plants, etc., complete as per the direction of
      the Engineer-in-charge.
3.    Laying plain cement concrete(1:4:8) in
      foundation and bottom layers of flooring and
      in the pipe lines and drains using 40mm
      thick black hard crusher broken granite metal
      of approved quality from approved quarry         127.98    Cum     2654.20      339684 . 00
      including mixing, lowering, laying and           cum
      compacting to proper thickness, watering
      and curing for the required period, including
      cost of all materials, labour, conveyance,
      loading and unloading ,taxes, royalties,
      scaffolding, watering, curing ,sundries, tools
      plants, etc. ,complete as per the direction of
      the Engineer-in-charge.
           CONTRACTOR                                            PROJECT ADMINISTRATOR
4.   K.B. brick masonry work using 1st class
     K.B. bricks having crushing strength not less
     than 75 kg/cm2 with cement mortar 1 :6 (1        141.44    CU    2732.95   386547 . 00
     cement: 6 sand) in foundation & plinth           cum       M
     including cost of all materials, labour,
     conveyance, loading, and unloading, taxes,
     royalties, scaffolding, watering, curing,
     sundries, tools and plants, etc.,complete as
     per the direction of the Engineer-in-charge.
5.   K.B. brick masonry work using 1st class
     K.B. bricks having crushing strength not less
     than 75 kg/cm2 with cement mortar 1 :6 (1
     cement: 6 sand) in superstructure including
     cost of all materials, labour, conveyance,
     loading, and unloading, taxes, royalties,
     scaffolding, watering, curing, sundries, tools
     and plants, etc.,complete as per the direction   208.62    cum   2765.95   577031.00
     of the Engineer-in-charge.                       212.58    cum   2833.25   602291.00
     GROUND FLOOR                                       41.13   cum   2910.00   119687.00
     FIRST       FLOOR
     SECOND FLOOR
          CONTRACTOR                                            PROJECT ADMINISTRATOR
6.   Lifting, hoisting and laying reinforced
     cement concrete(M-20) to base of columns
     and footing, columns, beams, plinth band,
     lintels; chajja, shaft, fins, roof slabs,
     balconies, stair cases, parapets, window sills
     as shown in the drawing for all floors with
     12mm H.G. chips, Providing strong, rigid,
     leveled, and plumbed centering and
     shuttering to required shape and size, for
     floors with wooden or steel centering
     materials with all necessary bracing.and tiles
     and supports with leveling centering covered
     with bituminous paper with provisions
     necessary including, watering and curing the
     required period, including cost of all
     materials, labour, conveyance, loading and
     unloading, royalties, sundries, tools and
     plants, etc., complete as per the direction of
     the Engineer-in-charge.
     Ground Floor                                     82.23   Cum   4125.10   339206.00
     Column bases                                     35.24   Cum   4363.75   153778.00
     Plinth Beams                                     41.25   Cum   7053.80   290968.00
     Beams & Column                                   14.01   Cum   6227.75    87250.00
     Lintel                                           55.42   Sqm   513.45     28454.00
     Chajja                                           6.17    Cum   6208.20    38304.00
     Stair case                                       99.87   Cum   6313.35   630513.00
     Roof slab
     First     Floor                                  38.81   Cum   7371.45   286085.00
     Beams & Column                                   13.27
                                                              Cum   6690.15    88777.00
     Lintel                                           50.78
                                                      6.17    Sqm    565.20    28700.00
     Chajja
                                                      88.29   Cum   6666.70    41133.00
     Stair case
                                                              Cum   6792.90   599744.00
     Roof slab
     Second Floor :-
                                                      4.60    cum   7751.60   35656.00
     Beams & Column
                                                      0.26    cum   7243.95    1882.00
     Lintel
                                                      2.04    sqm   663.60     1353.00
     Chajja
                                                      5.46    cum   7367.20   40224.00
     Roof slab
          CONTRACTOR                                          PROJECT ADMINISTRATOR
7.    Supplying M.S.round/ deformed/tor steel
      reinforcement bars of required diameters of
      approved quality including straightening,
      cutting to size, bending, and binding the
      reinforcement, lifting and placing in position
      as per design complete including cost of
      bars, binding wires 18 gauge, including cost
      of all materials, labour, conveyance, loading
      and unloading, taxes, royalties, sundries,
      tools and plants, etc. complete as per the
      direction of the Engineer-in-charge.
      Ground Floor:-                                 340.59    Qtl   5799.30   1975183.0
      First Floor:-                                                            996238.00
                                                     171.61    Qtl   5805.25
      Second Floor
                                                      13.30    Qtl   5811.50   77292 . 00
8.    20 mm thick plaster in cement mortar 1 :4 (1
      cement: 4 sand) on the rough surface of
      masonry walls for ground floor sub structure
      including cost of all materials, labour, 166.11          Sqm   90.65     15057 . 00
      conveyance, loading and unloading, taxes, sqm
      royalty, scaffolding, watering, curing,
      sundries, tools and plants, etc., complete as
      per direction of Engineer-in-charge.
9.    12mm thick plaster in cement mortar 1 :6 (1
      cement:6 sand) to outside surface/plumbed
      surface of masonry, raking out joints,
      scrapping and cleaning the surface and
      finishing the plastered surface smooth to
      proper plumbs and levels including cost of
      all materials, labour, conveyance, loading
      and unloading, taxes, royalties, scaffolding,
      watering, curing, sundries, tools and plants,
      etc complete as per the direction of the
      Engineer-in- charge.                           1062.19   Sqm   57.30     60862.00
      Ground Floor                                   630.76    Sqm   58.65     36993.00
      First    Floor                                 217.93    sqm   60.00     13076.00
      Second Floor
10.   16mm thick plaster in cement mortar 1 :6 (1
      cement:6 sand) to inside surface/plumbed
      surface of masonry, raking out joints,
      scrapping and cleaning the surface and
      finishing the plastered surface smooth to
      proper plumbs and levels including cost of
      all materials, labour, conveyance, loading
      and unloading, taxes, royalties, scaffolding,
      watering, curing, sundries, tools and plants,
      etc complete as per the direction of the 2046.56         Sqm   80.10     163929.00
      Engineer-in- charge.
                                                    1851.40    Sqm   81.35     150611.00
      Ground Floor
      First    Floor                                 171.60    sqm   82.65      14183.00
      Second Floor
           CONTRACTOR                                          PROJECT ADMINISTRATOR
11.   6mm thick cement plaster 1-4 and chips of
      size up to 6mm with cement / punning to
      match with the shade of the roof-ceiling in
      all floors, with mirror polishing etc.
      complete including cost of all conveyance,
      taxes, royalties, loading, all labour and
      scaffolding, lifting, watering, curing,
      sundries, tools and plants, etc., complete as
      per the direction of the Engineer-in-charge.
      Ground Floor                                                781.13    sqm   56.60     44212.00
      First    Floor                                              737.78    sqm   57.40     42349.00
      Second Floor                                                36.86     sqm   58.20      2145.00
12.   Supplying, laying, and fixing         tiles of
      homogenous color and texture monolithic in
      300mm x 300mm x 7.5mm size on floors in
      specific pattern and combination with (1
      cement:1sand) mix cement mortar having
      perfect level and required gradient with all
      joints finished with necessary pigmented
      white cement, including cost of all materials,
      labour, sundries, tools and plants, etc.,
      complete as per the direction of the
      Engineer-in- charge.
      Antiskid Floor Tiles
      Ground Floor:-                                              608.63    Sqm   689.70    419772..0
                                                                  565.29    Sqm   695.10    392933..0
      First Floor:-
      Granite Floor Tiles
                                                                    3.79    sqm   1442.20   5466.00
      Ground Floor:-
                                                                    3.71    sqm   1447.55   5370.00
      First Floor:-
13.   Supplying , laying 6mm thick glazed wall tile of 150mm
      x 150mm size of approved make and shade in
      dado/skirting to any height in all floors fixed with neat
      cement slurry (after soaking the tiles in water) over
      12mm thick cement mortar 1 :3 mix, with white cement
      pointing in joints, including washing and cleaning with
      oxalic acid, including cost of all materials, labour,
      conveyance, taxes, royalties, scaffolding, watering,
      curing, sundries, tools and plants, etc., complete as per
      the direction of the Engineer-in-charge.
      Antiskid Floor Tiles
                                                                  87.74     Sqm   601.95    52815.00
      Ground Floor
                                                                  77.84     sqm   609.70    47459.00
      First  Floor
      Ceramic Tiles                                                               601.95    103909.00
                                                                  172.62    Sqm
      Ground Floor                                                                609.70     99125.00
                                                                  162.58    Sqm
      First  Floor
14.   Applying with water proof weather coat paint to all
      external plastered surfaces by applying two coat, to give
      an even shade including cleaning and smoothening the
      surface thoroughly including cost of all materials,
      labour, conveyance, taxes, royalties, scaffolding,
      watering, curing, sundries, tools and plants, etc.,
      complete as per the direction of the Engineer-in-charge.
      Ground Floor                                                1062.19   Sqm   57.11     60662.00
      First  Floor                                                641.63    Sqm   58.13     37298.00
      Second Floor                                                315.45    sqm   59.16     18662.00
            CONTRACTOR                                                      PROJECT ADMINISTRATOR
15.   Applying paint over internal plastered surfaces with 2
      coats of distemper of approved quality and shade, using
      the required quantity of paint as specified by the
      manufacturer to give an even shade including providing
      1 coat of primer and watering the surface before
      applying and curing for the required period, including
      cost of all materials labour, conveyance, taxes, royalties,
      scaffolding, watering, curing, sundries, tools and plants
      etc., complete as per the direction of the Engineer-in-
      charge.                                                       2827.69   Sqm   50.30    142233.00
      Ground Floor                                                  2578.31   Sqm   51.05    131623.00
      First     Floor                                               110.95    sqm   51.80      5747.00
      Second Floor
16.   Supplying, side hung M.S. grill door&
      windows frame with panel shutter made
      out of structural steel, plates and bars
      confirming to IS specification as per
      drawing and design, to be fixed to walls
      and columns with grouted clamps with
      provision of handles locking arrangements
      etc. complete set as per the direction of
      the Engineer-in-charge.                                       6357.85   Kg    65.00    413260.00
      Ground Floor                                                  5485.50   Kg    65.00    356558.00
      First     Floor                                               232.00    kg    65.00     15080.00
      Second Floor
17.   Painting with synthetic enamel paint of
      approved quality and shade over surfaces
      as specified below to give an even shade
      with 2 coats over 1 coat of primer of
      approved quality including cost of all
      materials, labour, conveyance, taxes,
      royalties, scaffolding, sundries, tools and
      plants, etc., complete as per the direction
      of the Engineer-in-charge.
      Ground Floor                                                  349.01    Sqm   75.30    26280.00
      First     Floor                                               297.62    Sqm   76.50    22768.00
      Second Floor                                                   11.49    sqm   77.75       893.00
18.   Fitting & Fixing of M.S. grill door&
      windows frame with panel shutter made
      out of structural steel, plates and bars,
      fixed to walls and columns with grouted
      clamps with provision of handles locking
      arrangements etc. including priming 1
      coat with approved quality metal primer
      and making good to the damages in walls
      and floors etc. including cost of all
      materials, labour, conveyance, taxes,
      royalties, scaffolding, sundries, tools and
      plants,etc., complete as per the direction
      of the Engineer-in-charge.                                    349.01    sqm   70.10    24466.00
      Ground Floor                                                  163.20    sqm   70.10    11440.00
      First     Floor                                                 8.36    sqm   70.10       586.00
      Second Floor
            CONTRACTOR                                                        PROJECT ADMINISTRATOR
19.   Supplying, fitting & fixing of M.S.
      collapsible grill gate of size 8’0”x7’0” 252.00     kg    65.00     16380..00
      with made out of structural steel, plates
      and bars confirming to IS specification as
      per drawing and design, to be fixed to
      walls and columns with grouted clamps
      with provision of handles locking
      arrangements etc. complete set as per the
      direction of the Engineer-in-charge.
20.   Supplying, fitting and fixing PVC Door
      conforming to IS specification as per
      drawing and design, fixed to walls and
      columns with grouted clamps with
      provision of handles locking arrangements
      etc. making good to the damages in walls
      and floors etc. including cost of all
      materials, labour, conveyance, taxes,
      royalties, scaffolding, sundries, tools and
      plants,etc., complete as per the direction
      of the Engineer-in-charge.                  37.39   sqm   1930.00   72163.00
      Ground Floor                                37.39   sqm   1930.00   72163.00
      First     Floor
21.   2.5 cm thick artificial stone flooring
      using cement concerte (1:2:4) proportion
      on floor using 6 mm crusher broken
      hard granite chips including, watering
      and curing the required period, including
      cost of all materials, labour, conveyance,
      loading and unloading, royalties, sundries,
      tools and plants, etc., complete as per the
      direction of the Engineer-in-charge.
      Ground Floor                                86.30   sqm   148.30    12798.00
      First     Floor                             86.30   sqm   148.30    12798.00
22.   Suplying, fitting and fixing of Aluminium
      window of sliding type with OEL
      anodized section151—154,151—155,151-
      153,151--157 fitted with shutter frame
      with 5mm plain glass as panel fitted
      with rubber biding with locking
      arrangement etc          completed in all
      respect with all cost of materials
      conveyance , taxes , labour charges for
      fitting and fitting materials like
      nails,bolts,hooks,aldrop etc .
                                                  18.67         3298.60   61585.00
      Ground Floor                                        sqm
                                                  18.67         3298.60   61585.00
      First     Floor                                     sqm
          CONTRACTOR                                      PROJECT ADMINISTRATOR
23.   Grading concrete (1:2:2) proportion on
      roof slab using 6 mm crusher broken
      hard granite chips including, watering
      and curing the required period, including
      cost of all materials, labour, conveyance,
      loading and unloading, royalties, sundries,
      tools and plants, etc., complete as per the
      direction of the Engineer-in-charge.
      Second Floor                                824.53   sqm   172.30       142067.00
24.   Suplying, fitting and fixing of Aluminium
      Hand-railing of stainless steel of 304
      grade using 50 mm dia of 2 mm thick
      circular pipe with Balustrade of size 32
      mmx 32 mmx2 mm @ 0.90 mtr c/c and
      stainless steel circular pipe as bracing
      in 2 rows in stair case as per approved
      design and specification etc complete .    5.03      Rmt   3112.10      15654.00
                                                19.29      Rmt   3112.10      60032.00
      Ground Floor
      First    Floor
      (One crore thirteen lakhs twenty-four                      Rs.1,13,24,407.00
      thousands four hundreds seven only .)
          I,Sri___________________________________________aged______years S/O
          Sri_____________________________________________ at present residing
          at________________ P.O______________P .S______________
          Dist__________________ PIN_________________ do hereby solemnly affirm that I am willing
          to execute this work at_______% less/excess in word (          )that is my offering amount
          is Rs____________
          (                       ) as against Rs.______________ the amount put to tender .
          No. of Correction.:-
          No. of Over writing:-
          No. of ommisions:-
          CONTRACTOR                                       PROJECT ADMINISTRATOR