ESTIMATE FOR:-                                      KHAJANCHI                       Er.
GAURAV AGRAWAL
Railing At Talab                                   CONSULTANTS                     OLD GALLA MANDI,KARELI
BURHAR                                                                                 Branch:-Nagpur
Road,Jbp
DIST-SHAHDOL                                                                           MOB:-9424946643
S.NO           PARTICULARS             NOS. LENGTH WIDTH DEPTH               QTY      UNIT   RATE   AMOUNT
  1 Earth work in excavation by
     mechanical means (Hydraulic
     excavator)/ manual means in
     over areas foudation trenches or
     drains (not exceeding 1.5
     m in width or 10 sqm on plan)
     including dressing of sides and
     ramming of bottoms, lift upto 1.5
     m including getting out the
     excavated soil and disposal
     of surplus excavated soil as
     dircted,within a lead of 50 m
     SOR(2.6.1)
      1.For Footings                       54       1         1        1.8     97.2
      DPC TRENCH                            1   409.5       0.2        0.1     8.19
                                                                             105.39 cu.m      127    13384.53
  2   Centering and shuttering
      including strutting, propping etc.
      and removal of form for
      Footings                             54      4                   0.3     64.8
      Column(20.1.1)upto plinth            54      1                   0.8     43.2
                                                                  TOTAL-        108 SQ.M      138        14904
      column above plinth(20.1.6)          38     0.8                  1.2    36.48
                                                                              36.48 sqm       282        36.48
      Plinth Beam(20.1.5                    2   409.5                  0.3    245.7
                                                                  TOTAL-      245.7 SQM       227     55773.9
  3   Providing and laying in damp
      proof course 50mm thick with
      cement concrete grade M15 with
      10/12mm max. size of aggregate
      BELOW CURTAIN WALL
                                            1   409.5       0.2                81.9
      above brick work
                                            1   345.5       0.2                69.1
                                                                               151 SQM        193        29143
                                                        1
4   Reinforced cement concrete work
    in walls (any thickness),
    including attached pilasters,
    buttresses, plinth courses,fillets,
    columns,
    su spended floor roof slab,
    beams, etc. up to floor two level
    excluding cost of
    centering,shuttering, finishing
    and reinforcement :
    M 20 Nomial mix (with 20mm
    nominal size graded stone
    aggregate)(SOR 5.1.1)
    Footings                                  54        1          1        0.3    16.2
    Column(5.1.1)upto plinth                  54      0.2        0.2          2    4.32
    Plinth Beam(5.1.1)                              409.5        0.2        0.3   24.57
                                                                                  45.09 cu.m    5050    227705
    column above plinth(5.2.1)                38      0.2        0.2        1.2   1.824
                                                                       TOTAL-      1.82 CU.M    5120      9318
5   Reinforcement for R.C.C. work
    including straightening, cutting,
    bending, placing in position and
    binding including cost of binding
    wire up to floor two level
    including all wastage etc.
    complete.(SOR 5.16)
    5.16.3 Cold twisted bars (CTD
                                          1.2% of   46.91       0.56      7850    4396     KG     59    259364
6   Brick work with well burnt
    chimney in bulls patent trench
    kiln manifactured by
    ghol process crushing strength
    not less than 40kg /sqcm and
    waterabsorption not more than
    15% in foundation and
    plinth.SOR(6.1.2)
                                               1    409.5        0.2        0.2   16.38 cu.m    4232     69320
7   Brick work with M.S. bricks of
    class designation 40 in
    superstructure above plinth level
    up to floor II level in all shapes
    and si ze s i n :SOR(6.3
    Above Plinth Beam                          1    345.5        0.2        0.2   13.82 cu.m    4220    58320.4
8
    12mm cement plaster by cement
    mortar1:4 (1 cement:4
    sand)SOR(13.1.1)
    brick work plaster                         2    345.5                   0.3 207.3
    COLUMNS                                   38      0.8                   1.2 36.48
                                                                       TOTAL:- 243.78 SQM        108   26328.24
                                                            2
9    Distempering with dry distemper
     of approved brand and
     manufacture (two or more coats)
     and of required shade on new
     work, over and including priming
     coat of whiting to give an even
     shade.SOR(13.40)
     brick work plaster                      2   345.5                0.3 207.3
     COLUMNS                                38     0.8                1.2 36.48
                                                                 TOTAL:- 243.78 SQM              33   8044.74
10 Cement concrete flooring
   Cement concrete grade M15
   WITH 20MM nominal mix
   SOR(4.1.4)
     pcc base for footing                   54      1        1        0.1      5.4
                                                                 TOTAL:-       5.4 cu.m        4154   22431.6
11 Providing & fixing hand rail of
   approved by welding to steel
   laddr railing , balcony railing, stair
   case railing including apply of
   approved steel primer.MS TUBE
   (SOR10.26.1)
     Railing Around The Pond                     345.5 @         15kg/m     5182.5
                                                                 TOTAL:-    5182.5 84     kg
                                                                                          435330
                                                                              TOTAL     1229404
                                                     Add 5% for contengencies charges      61470
                                                                      GRAND TOTAL- 1290874
                                                                                 SAY- 12.91 LACS
     IN WORDS:-TWELVE LAKH NINETY ONE THOUSAND RUPPEES ONLY