The document discusses the importance of proper subgrade and subbase preparation for concrete slabs. The subgrade is the top layer of natural soil compacted to support the subbase and slab. The optional subbase layer provides a work platform and more uniform support. Both layers must be well-drained and compacted to uniform bearing capacity to prevent slab cracking and settlement. Failure to properly prepare the subgrade and subbase can compromise the slab's performance.

Uploaded by

Kruger
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views5 pages

Sub Base

The document discusses the importance of proper subgrade and subbase preparation for concrete slabs. The subgrade is the top layer of natural soil compacted to support the subbase and slab. The optional subbase layer provides a work platform and more uniform support. Both layers must be well-drained and compacted to uniform bearing capacity to prevent slab cracking and settlement. Failure to properly prepare the subgrade and subbase can compromise the slab's performance.

Uploaded by

Kruger
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

1 Introduction

Subgrade and subbase are the foundation of a concrete slab and play critical role in its performance.
According to the ACI Code, the subgrade is a compacted and improved natural soil or brought infill
whereas subbase is a layer of gravel placed on the top of the subgrade.
Both subgrade and subbase shall be constructed according to design requirement so as to offer the
expected performance. They must be well drained, dry at the time of concrete placement, and provide
uniform support for the weight of the slab and anything placed on the slab.
If a floor slab is constructed on unstable subgrade or subbase, then the concrete placed may get wasted
during construction and concrete slab is highly likely to suffer from settlement after construction.
Therefore, substantial cautions shall be practiced while subgrade and subbase are placed.

2 Subgrade and Subbase for Concrete Slabs


2.1 Subgrade for Concrete Slab
The subgrade is considerably significant for concrete slab since concrete slab load and imposed loads are
supported by subgrade. When required, Concrete slab can be placed on the top of natural soil without the
need for extra layers provided that it is clean and compactable. In this case, the only problem would be
the improper drainage of the soil.

If the soil is wet due to rain or any other reason, then it cannot be compacted and flatted properly and
suitable grade cannot be obtained.
The project site is excavated to remove hills and fill pits and then compact the entire area so as to prepare
the subgrade for loads of subbase and concrete floor. The degree of work required to prepare the subgrade
is controlled by different types of soils namely: organic, granular, and cohesive soils.

Figure 1: Subgrade for Concrete Slab

The organic soil is the least desirable because it cannot be consolidated and hence shall be removed from
the site. Granular soil offers ultimate load carrying capacity and can be compacted easily.
Cohesive soil does not provide bearing strength as much as granular soil. additionally, it may suffer from
shrinkage and settlement and hardly compacted when it is wet. Finally, cohesive soil requires great effort
to make it suitable for subgrade of concrete floor.

3 Bearing Capacity of Subgrade


Generally, a weight of 15cm thick concrete slab is around 3.6 KN/m2, and live load imposed on concrete,
According to International Residential Code, ranges between 0.96KN/m2 and 2.9 KN/m2. Consequently,
the total load imposed on subgrade is around 6KN/m2.
It is reported that, the allowable soil pressure for clean sandy soil is around 95KN/m2, and for weaker soil
such as silt or soft clay is approximately 20KN/m2. Therefore, it can be concluded that, the allowable soil
pressure for concrete slab would not cause any problem.
Nonetheless, the subgrade shall be uniform so as to avoid crack development in the slab due to bending.
This may be achieved by recognizing cut and fill areas and compacting subgrade properly.

4 Subgrade Improvement Strategies


Commonly, all types of soil whether it is natural soil or brought infill used for subgrade of concrete slab
need certain degree of improvement, and the following methods can be used to achieve that purpose:
1. Soil compaction.
2. Soil stabilization; Portland cement, calcium chloride, or lime blended into the soil then it is
compacted.
3. Excavated subgrade, mix it with gravel then apply compaction effort.

5 Subbase for Concrete Slab


Subbase is a layer of gravel, which is fairly cheap material, placed on top of subgrade. The subbase
placement is optional and it serves as a work platform for construction of the slab and provide more
uniform support for the slab.
As the thickness of subbase increases, the ultimate load carrying capacity of slab increases. Therefore, the
designer shall select thick subbase if the imposed load is large.
Apart from carrying slab load, subbase interrupts capillary and prevent water to move upward from
groundwater into the slab.
Figure 2: Placement of Concrete Subbase

6 Materials for Subgrade and Subbase Construction


There are several soil types which might be used for subgrade and subbase construction. However,
Certain types provide the most desired result. Different soil type for subgrade and subbase include:
1. For subgrade natural soil at project site or fill is brought to the construction site.
2. For subbase, granular material is employed.

Figure 3: Subbase Materials

7 Saturated or Frozen Subgrade and Subbase


It is possible that subbase and subgrade get saturated due to rains or freezing conditions before concreting
is started. In that case subbase would turn into a soft layer which might not be suitable to support
concrete.
The suitability of subbase for supporting concrete is checked by proof rolling. It involves driving across
over the subbase right before the beginning of concreting. If the tires sink more than 12.7mm, then the
subbase needs improvement and shall be recompacted.
Supervisor shall look for rutting or pumping during proof rolling. According to ACI 302.1, the former is
when the surface of the subbase is wet, greater than three percentage points above optimum moisture
content, whereas pumping is when the surface of the subbase is dry and the underlying soils are wet.

8 Subgrade and Subbase Construction Sequence


1. Removal of surface vegetation and topsoil
2. Excavation of high spots of grade
3. Prepare and Compact Subgrade
4. Brought in materials if natural soil bearing capacity is poor.
5. Compact subgrade fill
6. Place and Compact subbase

9 Compaction Equipment
Gravel and sand compacts best with a drum roller or a vibrating plate compactor.
Cohesive soil can best be compacted using a vibrating sheepsfoot roller or a rammer.
For small projects, or around the edges, pipes, or columns, a plate compactor provides good compaction
for sand or gravel.

Figure 4: Subbase Compaction

10 Effect of Poor Subgrade and Subbase Preparation


1. Settlement.
2. Varying concrete slab thickness.
3. Poor drainage.
4. Cracking.