RECOMMENDED START-UP PROCEDURE
FOR KRAMER
          THERMOBANK HOT GAS DEFROST SYSTEMS
•   Review system refrigerant piping layout. All piping must be
    adequately clamped and supported, (particularly at valve stations), to
    prevent possible movement during system operation which can
    result in line breakage and refrigerant loss. All suction risers over
    (2) feet must have a P-trap at the bottom of the riser. All suction
    lines must be pitched a minimum of ¼” per foot in the direction of
    flow to ensure proper oil to the compressor(s). All field piped
    suction line(s) must be insulated wherever practical to minimize
    excessive return gas temperatures on suction cooled compressors
    and prevent condensate dripping and potential safety and / or
    product damage. Confirm ALL lines are properly sized for the
    intended operating design conditions in accordance with the
    Operation & Installation manual supplied with the equipment. Note:
    To minimize pressure drop through the liquid line during the defrost
    cycle the common liquid line on Thermobank systems is typically at
    least (1) size larger than required for normal liquid line duty on a
    conventional refrigeration system.
•   With ALL electrical power disconnected and locked out to the
    system, check ALL factory and field electrical connections for
    tightness, including at compressor motor terminals.
•   Visually verify the correct settings of all operating and safety
    controls as per the supplemental data provided. Adjust as
    necessary and confirm actual cut-in & cut-out settings of all pressure
    controls after system has been placed in operation.
•   Remove pipe fill plug and add 100% tap water to Thermobank(s) to
    the point of overflowing. Remove immersion heater cover and adjust
    thermostat setting to maintain approx. +120 degrees.
•   Remove fan guards and check all fan / motor assemblies. Check
    motor mounting bolts / brackets & fan blade set screws for proper
    tightness. Confirm proper location / height of fan blade with respect
    to venturi. Manually rotate fan blades to confirm proper blade
    clearance and motor rotation. (Perform this check on ALL
    evaporator and condenser fan assemblies).
•   Turn off, (down position), both manual pumpdown and compressor
    kill switch.
•   TEMPORARILY place a jumper wire around the post defrost pressure
    control to force evaporator fans to run and also to prevent excessive
    cycling of suction and liquid line solenoid valves due to abnormally
    high suction pressure during initial room temperature pulldown.
•   TEMPORARILY remove all defrost tripper pins from the outer defrost
    timer dial to prevent the system from initiating a defrost cycle while
    the post defrost pressure control is jumped out. Note: Do not under
    any circumstances allow the system to initiate a defrost cycle while
    the post defrost control is jumped out or the compressor may suffer
    irreparable liquid damage.
•   TEMPORARILY lower the control settings or otherwise jump out all
    condenser fan cycling controls to force all fans on during the initial
    refrigerant charging process. Remember to remove all jumpers and
    re-adjust these controls after the initial charging process is
    completed.
•   Calculate the approx. year-round operating refrigerant charge for
    each system. Manually open the liquid line solenoid valve via the
    manual lift stem on the bottom of the valve body. Attached the high
    side hose of a service gauge manifold to the ¼” service gauge fitting
    on the receiver outlet, (king), valve and attached the charging hose
    to a cylinder of the appropriate system refrigerant. Purge the service
    gauge hoses and set the refrigerant cylinder for liquid charging.
    Open the receiver valve stem to the mid-seat position and introduce
    liquid refrigerant directly into the receiver and liquid line until the
    pressure equalizes. Once the pressure has equalized and refrigerant
    flow has stopped, front seat, (close), the receiver outlet valve so that
    the refrigerant tank is open directly into the liquid line downstream of
    this valve. Note: Once this initial liquid refrigerant charge has been
    added to the system, be sure to close the liquid line solenoid valve
    manual lift stem.
•   Attach a service gauge manifold to the suction and discharge service
    valves of each compressor in the unit. The discharge valve(s)
    should be front seated approx. (1/2) turn to allow gauge pressure
    reading. Completely close, (front seat), the suction service valve on
    each compressor and then open the valve approx. (2) full turns.
    Manually attend to this valve throughout the initial start-up period to
    help prevent excessive, (high), suction pressure or any potential
    liquid refrigerant return to the compressor(s).
•   Momentarily apply main power to the system and verify correct
    rotation of all condenser and evaporator fans. If the unit is equipped
    with the optional phase loss monitor, it may be necessary to switch
    any (2) of the (3) main power leads feeding the phase loss monitor in
    order to energize the unit control circuit. (Compressors are not
    rotation sensitive). If any or all fan motors are running backwards,
    disconnect main power and switch any (2) of the (3) power leads
    feeding these motors. Verify correct power supply is available, (+/-
    10% of unit nameplate rating), between all (3) phases at main power
    terminal block.
•   Re-establish main power and turn on, (up position), both manual
    pumpdown and compressor kill switch(es). Allow compressor(s) to
    start and cycle off on low pressure control.
•   Continue to add liquid refrigerant directly into the receiver outlet /
    liquid line to speed the charging process. Since the compressors
    can essentially only be operated in short bursts during this time, it
    may be necessary to manually adjust or otherwise close the contacts
    of the low pressure control in order to maximize the compressor(s)
    run time and introduce as much liquid refrigerant into the system as
    possible. Note: If compressor oil levels should happen to drop
    below the visible level in the oil sight glass during this time,
    discontinue refrigerant charging by turning off the charging manifold
    gauge attached to the receiver outlet, (king), valve, then opening,
    (backseating), this valve to allow full refrigerant flow through the
    liquid receiver, then open, (backseat), the suction service valve. If
    sufficient liquid refrigerant has been added to the system to maintain
    a reasonable, operating suction pressure at the compressor, then the
    velocity of the refrigerant gas through the suction line should be
    enough to return any excessive oil laying out in the system back to
    the compressor(s).
•   Add the remainder of the refrigerant charge as a vapor through the
    suction filter gauge access fitting or directly into the suction service
    valve at the compressor(s). During the initial room temperature pull
    down, it is not unusual to observe flashing in the liquid line sight
    glass due to high load conditions and / or high superheat at the
    evaporator outlet. Note: If bubbles are observed in the liquid line
    sight glass after the system is completely charged, DO NOT add any
    additional refrigerant beyond the quantity originally calculated for
    the system unless a refrigerant leak is confirmed.
•   Continue to manually monitor all system operating conditions and
    controls throughout the entire, initial room temperature pull down
    period. Periodically check system oil levels, compressor and fan
    motor amperage draws, refrigerant system pressures and
    compressor suction superheat during this time. High superheat
    would be considered normal during this time but if excessive
    floodback, (ie. low), superheat is observed it may be necessary to
    begin adjustment, (closing), of the thermostatic expansion valve(s),
    particularly as the room temperature is reduced.
•   Normal “wetting” of all internal system piping components may
    necessitate that additional oil be added to the sealed system. If this
    becomes necessary, use only a POE lubricant approved by the
    compressor manufacturer. On parallel compressor systems utilizing
    an oil equalization system, (discharge oil separator, oil reservoir and
    individual compressor oil floats), the operating oil level should be
    maintained between the (2) sight glasses on the oil reservoir.
•   Remove ALL jumper wires from operating controls, (fan cycling
    controls and post defrost control), and return ALL controls to
    recommended factory settings.
•   After the system has operated for several hours and the room
    temperature has been reduced to a minimum of +40 degrees, the
    tripper pins should be reinserted into the outer dial of the defrost
    time clock and the timer manually advanced to initiate a defrost
    cycle. A MINIMUM of (2) service gauge manifolds should be installed
    to adequately monitor the operating system pressures during the
    defrost cycle. Install (1) set of service gauges at the compressor(s)
    service valves and a second set on the gauge port fitting of the
    suction line filter. NOTE: Due to the high pressure, (approx. 200
    P.S.I.G.), produced in the suction line during the defrost cycle, we
    recommend that you attach the high side gauge to the suction
    connection at the suction line filter connection.
•   Manually advance the timer into defrost and observe readings at
    both service gauge manifolds. Be prepared to make quick
    observations of both pressure gauge readings as the defrost cycle
    may progress quite rapidly, particularly if little frost build up is
    present on the evaporator coil(s) when the defrost cycle is initiated.
    Initially, both operating suction and discharge pressures will drop at
    the compressor, temporarily stabilize after a short period of time and
    then begin to steadily increase as the defrost cycle progresses. The
    suction pressure at the compressor should never exceed 15 - 20
    P.S.I.G., based upon the setting of the holdback valve(s) located at
    the suction inlet of the Thermobank(s). The high side gauge
    pressure measured at the suction filter connection, (upstream of the
    holdback valves), will continue to rise steadily until the evaporator
    coil temperature exceeds +32 degrees, then level off for a short
    period of time as the frost build-up is melted from the coil surface.
    Once all frost is melted from the evaporator coil surface, the
    “suction” pressure will rise rapidly towards defrost termination
    pressure, (approx. 200 P.S.I.G.). When the defrost termination
    pressure control closes energizing the “X” terminal on the defrost
    time clock, the clock will be automatically switched back into the
    refrigeration cycle. For the next 2 - 3 minutes, (approx.), the post
    defrost pressure control will remain open as the suction pressure
    upstream of the holdback valve(s) is reduced to the cut-in setting of
    this control, (approx. 25 P.S.I.G. on low temp. systems). This
    provides for a “pump-out” cycle, continuing to run the high pressure
    liquid still contained in the low side through the Thermobank(s),
    where it is reduced to a low pressure vapor. This post switch also
    prevents the liquid solenoid valve from opening and allowing any
    additional liquid refrigerant into the evaporator and also provides an
    evaporator fan delay.
•   If the operating suction pressure during the defrost cycle exceeds 15
    – 20 P.S.I.G. at the compressor suction service valve, then the
    adjustment caps should be removed from the holdback valve(s) and
    the valves adjusted during the next subsequent defrost cycle. Using
    a 5/16” hex wrench, the valve(s) should be adjusted slowly, (approx.
    (1) turn at a time, (counterclockwise), to decrease the pressure
    setting. On systems employing (2) holdback valves, both valves
    should be adjusted simultaneously in order to equalize refrigerant
    flow through both Thermobanks. NOTE: In order to avoid potential
    compressor damage, DO NOT RUN THE SYSTEM THROUGH
    MULTIPLE, BACK TO BACK DEFROST CYCLES. Always allow the
    system to “regenerate” the heat stored in the Thermobank(s) by
    allowing the system to operate continuously for a minimum of (1)
    hour in the normal refrigeration cycle before initiating a second
    defrost cycle.