WASTES UTILIZATION in cement
industry
Cement Production India
year Capacity Mn T
2010 228.3
2022 605.8
2027 975.6
Coal requirement for cement plant -2030- 150 Mn T
The availability of linkage coal a major concern for the cement industry.
Even importing coal is not the best option . Will have to compete with power plants .
The industry has no choice but to use waste derived fuels
Linkage coal for Cement sector
No new Coal allotment to Cement industry . Coal materialization thru
linkage has come down from 14. 8 mill T in FY 06 to 11.9 in FY 11
Data based on CMA member companies
Alternate fuel use in Cement kilns
Country % TSR by AFR Country % TSR by AFR
Netherlands 83 Sweden 29
Switzerland 48 Luxemburg 25
Austria 46 Czech Republic 24
Norway 35 Japan 10
France 34 United states 25
Belgium 30 India Less than 1
Germany 42
Source: CEMBUREAU
Waste generation in India
Type of waste Quantity Mil T Quantity Mil T
Municipal waste 58. 4
Hazardous waste A+B+C 6.21
A recyclable 3.08 3.08
B Land fillable 2.72 2.72
C Incinerable 0.41 0.41
Total 64.61
National Inventory of Hazardous Wastes Generating Industries &
Hazardous Waste Management in India February 2009, CPCB
Municipal waste alone can generate 9 mil T of RDF to replace 4. 5 Mil T of coal Equivalent to
22 % of current coal requirement for cement plant operation . Does not include other non
hazardous waste
Incinerable waste generation in India
State
Hazardous waste incinerable
Maharashtra 36.75%
Gujarat 26.12%
AP 7.61%
Rajasthan 5.54%
U.P 3.78%
Punjab 3.57%
WB 3.03%
TN 2.68%
Total Incinerable waste generation 0.41MTA
Total Incinerable waste capacity 0.32 MTA
Deficit of Incineration capacities 0.09MTA
UltraTech - Leading Indian Cement Manufacturer
has taken this Challenge as Technology Mission.
The advantages of co processing of
alternate fuel in cement plant
• Co processing ranks higher in the waste processing hierarchy .
• High flame temperature (2000°C) – ensures complete destruction
of harmful pollutants
• Residence time of combustion gases above 1000°C in excess of 3-4
seconds – ensures complete destruction of pollutants.
• Complete destruction of organic compounds.
• Total neutralization of acid gases, sulphur oxides and hydrogen
chloride, by the active lime in the kiln load, in large excess to the
stoichiometry.
• Embedding of the traces of heavy metals in the clinker structure
with very stable links (metallic silicates formation).
• No production of by-products such as ash or liquid residue from gas
cleaning.
8
The advantages of co processing of
alternate fuel in cement plant
• Produces overall environmental benefits by reducing releases to air,
water and land.
• Maximizes the recovery of energy while ensuring their safe disposal
• Saving of non renewable fossil fuels. Substitution of coal with
waste. Savings are made through resource conservation and
associated CO2 emissions.
• Reduced burden on TSDF
• Immobilization of toxic and heavy material
• Reduced NOx emissions when using certain types of waste
UltraTech Cement in India
• Rajasthan- Three Integrated Units( Aditya Cement works, Kotputli cement works and
Birla white cement plant)
• Chhattisgarh- ( Hirmi Cement Works, Rawan Cement Works)
• Maharashtra- (Awarpur Cement Works, Hotgi cement Works, Ratnagiri Cement Works)
• Madhya Pradesh- ( Vikram Cement Works)
• Karnataka- (Rajshree Cement Works, Ginigera Cement Works)
• Tamil Nadu – (Reddipalayam Cement Works, Arakkonam Cement Works)
• Gujarat - Gujarat Cement Works , Narmada Cement Jafrabad Works, Magdalla Cement
Works
• Andhra Pradesh – ( Andhra Pradesh Cement Works)
• Uttar Pradesh- ( Dadari Cement Works, Aligarh Cement Works)
• Haryana- ( Panipat Cement Works)
• Punjab- ( Bathinda Cement Works
• West Bengal ( West Bengal Cement Works)
• Orissa – ( Jharsuguda Cement Works)
India UAE-
Integrated Units-12 Clinkerisation Units-1
Grinding Units -11 Grinding Units -3
Bulk terminal -4 Grinding Units Bangladesh -1
Bulk terminal Sri lanka -1
Industrial Wastes We Co-Process
Automobile Industry ( Paint Sludge, Phosphate Sludge, ETP Sludge, Spent
Catalyst, Waste Oil)
Textile Industry ( ETP Sludge, Waste Oil)
Pharmaceutical & Bulk Drug Industry (Spent Carbon, ETP Sludge, Spent
Catalyst, Mother Liquor, Waste Oil, Still Bottom Residue, Spent and
distillation Residue)
Soft Drink Industry ( ETP Sludge, Spent Carbon)
Petroleum Refinery
Pesticide Industry
Paint and Dyes Industries
Agro Waste and Biomass ( Rice Husk, Soya Husk, Mustard Husk, Ground Nut
Husk, Saw Dust etc)
Tyre Chips, Rubbers, Plastics and polythene
MSW/RDF
Overall AF Consumption
2.50
2.28 2010-11 2011-12 2012-13…
2.00 Targeted % TSR for FY 2012-13
2.00
1.80 1.84
1.57
1.50
1.26
1.13
1.00
0.68 0.71
0.50
0.15
0.00
% AF Weight % TSR Qty (in Lac MT)
Overview of AF Usage in UltraTech
(Based on Material)
Hazardous waste 43% ,Non Hazardous waste 15%
Biomass fuel 42%
Alternative Raw Material
Utilization of Fly ash, Slag as Substitute materials for Cement
Production . Potential to use LD slag , spent pot liners , lime sludge .
16.81 million tonnes of recycled material used during Fy-10-11 and
Fy-11-12.
Alternative Raw Materials Rate (% total raw materials for cement
production) 14.10 and 13.75 during Fy-10-11 and Fy-11-12.
Storage Yard & Feeding System at RDCW
We have a well covered storage yard with good
ventilation, concrete floor and leachate collection
drainage system.
A special and fully mechanized feeding system with
hopper, belt conveyor, weigh feeder etc.
Fully dedicated handling vehicle like dozer.
Special manpower for pre-processing, handling and
monitoring of waste fuel feeding.
Pump for feeding liquid/semi solid material like sludge.
Plastic and wood shredding machine for size reduction.
15
Alternate Fuel Feeding System at RDCW
BUCKET
ELEVATOR
TRANSFER UNLOADING
TOWER AREA
16
Alternate Fuel Feeding System at RDCW
17
Storage Yard at RDCW With Different Wastes
18
Municipal Solid Waste Plant at Jaipur ( Rajasthan)
(Future plan and Support required )
• Policy to encourage waste generators to divert incinerable
waste to cement plant.
• To include “co processing ”in Hazardous wastes
(Management, Handling, and Trans boundary Movement )
Rules,2008 and place it above incineration .
• To Create a class of Waste processing facilities for fuel
homogenization and preparation for Industry .
• Polluters pay principle to be enforced .
• Need for better coordination between regulatory authority,
TSDF operators and cement industry.
• Inter States movement permission.
• Permit import of non hazardous waste such as Tyres and RDF
.
21