Description Quantity SL NO Total Cost (INR)

The document is a quotation for proposed warehouse office building near Azikkal port providing estimates for civil works. It includes 16 line items with descriptions and quantities for earth work excavation, RCC work for footing, columns, beams and slabs up to floor two level, plastering, flooring and other construction works up to plinth level and above excluding electrical, plumbing and septic tank works. The total estimated cost is not provided.

Uploaded by

kiran m v
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views8 pages

Description Quantity SL NO Total Cost (INR)

The document is a quotation for proposed warehouse office building near Azikkal port providing estimates for civil works. It includes 16 line items with descriptions and quantities for earth work excavation, RCC work for footing, columns, beams and slabs up to floor two level, plastering, flooring and other construction works up to plinth level and above excluding electrical, plumbing and septic tank works. The total estimated cost is not provided.

Uploaded by

kiran m v
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 8

SEANDA ENGINEERING PVT.

LTD
CLIENT KL ABDUL SATHAR
PROJECT WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT
QUOTATION FOR PROPOSED WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT(CIVIL WORKS)

SL TOTAL COST
DESCRIPTION QUANTITY
NO (INR)

CIVIL WORK UP TO PLINTH


1 Earth work excavation by mechanical means
(hydraulic excavator) /manual means over areas
( exceeding 30cm in depth 1.5m in width as well as
10 sqm on plan) including disposal of excavted
earth up to 50 m and lift upto 1.5 m, disposed soil
to be levelled and neatly dressed

LS

2 Cement Concrete 1:4:8 using 40mm.nominal size


hard granite broken stones including cost and
conveyance of all materials and all labour charges
etc.complete.

For Footing LS

3 R.C.C work upto plinth level including the cost of


centering ,shuttering finishing and reinforcement
with 1:1.5 :3 (1 Cement, 1.5 Coarse sand, 3
Graded stone aggregate 20 mm nominal size)

For Footing LS
For Column LS
For Plinth beam LS
For Lintel LS

4 Steel Reinforcement for R.C.C work including


straightening ,cutting,bending , placing in position
and binding all complete above plinth level
Thermo Mechanically Treated

For Footing LS
For Column LS
For Plinth beam LS
For Lintel LS

5 Soil filling with excavated good soil from the site


including lead and lift , ramming etc. complete

For Footing EXCLUDED


For Plinth (supplying, leveling & compacting) EXCLUDED
SEANDA ENGINEERING PVT. LTD
CLIENT KL ABDUL SATHAR
PROJECT WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT
QUOTATION FOR PROPOSED WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT(CIVIL WORKS)

SL DESCRIPTION QUANTITY TOTAL COST


NO (INR)

STRUCTURAL STEEL WORK


6 Suppying and fixing anchor bolts in RCC
pedestal/column reqiured length as per design.

For steel column LS

7 Design, engineering, fabrication, painting supply &


erection of Pre-engineered building as per the
stated scope & specifications.
LS
Pre enginered Building - structural beams for
supporting deck sheet for first floor slab LS
Decking sheet for supporting first floor slab. LS
The proposed PEB will be made of primary
members, secondary members, connections, roof
sheeting, wall sheeting & sheeting fasteners as per
following specifications:

• STRUCTURAL MEMBERS

- Members fabricated from plate or bar stock shall


have flanges and webs joined on one side of the
web by a continuous welding process and will
conform to minimum yield strength of 345 MPa.
- Members fabricated from hot rolled structural
shapes shall conform to the physical specifications
of having minimum yield strength of 250 MPa.
- Rod and angle bracing, as the case may be, shall
conform to the physical specifications of having
minimum yield strength of 250 MPa.

• PAINT ON STRUCTURAL MEMBERS

- All structural members shall be cleaned by hand


tool to remove dirt, grease, oil and loose mill scale
and given one shop coat of red oxide primer. Two
coats of synthetic enamel paint of approved shade
will be provided over the primer.
- Purlins shall be G.I

• CONNECTIONS:

- All field connections shall be bolted (Unless


otherwise noted).
- Primary bolted connections shall be furnished
with high strength GI bolts conforming to the
physical specifications of Gr. 8.8 (or equivalent).
- Secondary bolted connections shall be furnished
with GI bolts conforming to the physical
specifications of Gr. 4.6 (or equivalent).

8 Roofing with MP tiles above structural purlins


SEANDA ENGINEERING PVT. LTD
CLIENT KL ABDUL SATHAR
PROJECT WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT
QUOTATION FOR PROPOSED WARE HOUSE OFFICE BUILDING NEAR AZHIKKAL PORT(CIVIL WORKS)

SL DESCRIPTION QUANTITY TOTAL COST


NO (INR)

CIVIL WORK ABOVE PLINTH


9 Laterite stone masonry using neatly dressed stone
40x20x20 cms size in cement mortar 1:6 for
superstructure above plinth upto floor two level
including cost of all materials,labour charges etc.
complete

For wall above plinth beam LS

10 R.C.C work above plinth level including the cost of


centering ,shuttering finishing and reinforcement
with 1:1.5 :3 (1 Cement, 1.5 Coarse sand, 3
Graded stone aggregate 20 mm nominal size)

For Lintel LS
For deck slab with nominal reinforcement LS

11 Steel Reinforcement for R.C.C work including


straightening ,cutting,bending , placing in position
and binding all complete above plinth level
Thermo Mechanically Treated

For Lintel LS
For deck slab LS

12 Wall plastering with CM 1:4, 12mm thick finished


with afloating coat of neat cement 12mm cement
plaster

For Wall LS

13 Fixing Doors, windows & ventilators frames (Only


labour charges)
For doors LS
For windows LS
For ventilators LS

14 Flooring PCC 1:3:6, including cost and conveyance


of all materials and all labour charges etc.complete
as per standard specification.

For flooring LS

ELECTRICAL FITTINGS
15 Electrification charges for suplying and fixing
electrical fittings complete including all labour
charges etc complete.

EXCLUDED

SANITARY FITTINGS, SEPTIC TANK & SOAK PIT


16 Supplying and fixing plumbing and sanitary fittings
including all labour charges etc complete.

EXCLUDED

GRAND TOTAL
1 Earth work excavation by mechanical means (hydraulic
excavator) /manual means over areas ( exceeding 30cm in
depth 1.5m in width as well as 10 sqm on plan) including
disposal of excavted earth up to 50 m and lift upto 1.5 m,
disposed soil to be levelled and neatly dressed

960 cum

2 Cement Concrete 1:4:8 using 40mm.nominal size hard granite


broken stones including cost and conveyance of all materials
and all labour charges etc.complete.

For Footing 25 cum


For Plinth beam 15 cum

3 R.C.C work upto floor five level excluding the cost of


centering ,shuttering finishing and reinforcement with 1:1.5 :3
(1 Cement, 1.5 Coarse sand, 3 Graded stone aggregate 20 mm
nominal size)

For Footing 100 cum


For Column 56 cum
For Plinth beam 53 cum
For Stub column 15 cum
For Lintel 17 cum

4 Steel Reinforcement for R.C.C work including straightening


,cutting,bending , placing in position and binding all complete
above plinth level Thermo Mechanically Treated

For Footing 7 MT
For Column 9 MT
For Plinth beam 9 MT
For Stub column 3 MT
For Lintel 2 MT
For flooring 18 MT

5 Soil filling with excavated good soil from the site including lead
and lift , ramming etc. complete
For Footing 800 cum
For Plinth 4000 cum

6 Cement Concrete 1:4:8 using 40mm.nominal size hard granite


broken stones including cost and conveyance of all materials
and all labour charges etc.complete.

For flooring base 510 cum

7 Flooring with cement concrete 1:2:4 using 20mm.metal and


reinforced with 8mm dia bar @ 300 c/c and platered over with
cement mortar 1:4, 12mm thick one coat floated hard and
trowelled smooth including cost and conveyance of all
materials and al labour charges etc.complete except
reinforcement.

For flooring 510 cum


8 Laterite stone masonry using neatly dressed stone 40x20x20
cms size in cement mortar 1:6 for superstructure above plinth
upto floor two level including cost of all materials,labour
charges etc. complete

For wall above & below plinth beam 250 cum

9 Wall plastering with CM 1:3, 12mm thick finished with afloating


coat of neat cement 12mm cement plaster
For Wall 2500 sqm

10 Supplying and fixing Rolling shutters of approved rates and


painted with a priming coat of iron primer made of 80x1.25mm
MS laths inter locked together through their entire length and
jointed.

Rolling shutters 6m x 6m 4 nos

11 Providing UPVC fully glazed windows & ventilators , materials as


per standard specification including cost and conveyance of all
materials and all labour charges etc. complete.

For windows W1 46 nos


For windows W4 1 nos
For ventilators V1 4 nos

12 Providing and fixing M.S grills of required pattern in frames of


windows etc. with M.S flats,square or round bars etc. including
priming coat with approved steel primer all complete. Fixed
windows by weld

For windows W1 =46x2x15= 1380 kg


For windows W4 =1x4x15= 60 kg
For ventilators V1 =4x3x8= 96 kg

13 Providing wood work in frames of doors wrought framed and


fixed in position with hold fastlugs or with dash fasteners of
required dia &length (hold fast lugs or dash fastener shall be
paid forseperately).using good quality Irul wood

For Doors 3 nos

14 Providing and fixing panelled and glazed shutters for


doors,windows and clerestory windows and clerestory
windows,35 mm thick shutters including ISI marked
M.S.pressed butt hinges bright fininshed of required size with
necessery screws, excluding panelling which will be paid for
seperately,all complete as per direction of Engineering-charge.

For Doors 3 nos

15 Flooring with ceramic floor tiles (first quality ) over plastered


surface in CM 1:3, 12m thick, providing neat cement grout as
required pointing the joints and filling the voids appropriate
coloured cement to match the floor including cost and
conveyance of all materials and all labour charges etc.complete
as per standard specification.

For Dining & Toilets 80 sqm


16 Dadoing walls with best glazed white or coloured tiles 7.5mm
thick or nearest size over cement plastering in cement mortar
1:3, 12mm.thick and pointing with cement of suitable colour
including cost and conveyance of all materials and all labour
charges etc.complete.

For Toilets 70 sqm

17 Electrification & Plumbing charges

18 Sanitary fittings

19 Painting and White washing