Wastewater Collection And Treatment in
Upcoming IIT Palakkad Permanent Campus
CE3025 - Environmental Engineering
Department Of Civil Engineering
Indian Institute of Technology, Palakkad
Submitted By- Submitted To-
Ishan Agrawal (101501015) Dr. Sunitha K Nayar
Ashutosh Maurya (101501009)
Swati (101501026)
Divyansh Dubey (101501012)
Akshansh Gupta (101501003)
ABSTRACT
The project aims at designing wastewater collection system for the campus and setup a
treatment plant. Specifications of the entire management system such as pipe diameters, capacity
of the treatment plant, etc. are calculated based on population estimates for the next 30 years.
Factors including topography of the campus, isolation of the location and ease of discharge are
considered to decide the site for the treatment plant as well as the course of the sewer conduits.
Various components of the treatment plant are designed based on flow characteristics, type of
contaminants, acceptable effluent standards and typical dimensions.
1
ACKNOWLEDGEMENT
The successful completion of this project brings immense joy and satisfaction for the entire team
involved. We extend our gratitude to Dr Sunitha K Nayar for giving us the opportunity to work
upon this problem statement. Inputs from her lectures for this course as well as her guidance all
through our period of work were invaluable.
Mr Vineesh Kumaran from the engineering works department was appreciably cooperative in
providing us with the required maps and drawings for the project.
This report is a result of the combined efforts and dedication of all the members of the group and
a significant credit goes to our team work as well.
2
TABLE OF CONTENT
1. Treatment Plant Site Identification ………………………………………………6
2. Population and Influent Amount Estimation …………………………………….7
3. Design of Sewer Conduits ……………………………………………………....10
4. Wastewater Treatment Process ……………………………………………….....13
4.1 Primary Treatment ………………………………………………………….13
4.2 Secondary Treatment ..……………………………………………………...14
4.3 Sludge Thickening …………………………………………………………..15
4.4 Sludge Digestion …..………………………………………………………..15
4.5 Disinfection ……..………………………………………………………......15
5. Treatment Plant Design ……………………………………………………….....16
5.1 Design of Receiving Chamber ………………………………………………16
5.2 Design of Grit Chamber ……………………………………………………..16
5.3 Design of Bar Screen ………………………………………………………...18
5.4 Design of Primary Sedimentation Tank ……………………………………..19
5.5 Design of Trickling Filter …………………………………………………...20
5.6 Design of Secondary Clarifier ……………………………………………....21
5.7 Design of Disinfection Tank ………………………………………………...22
6. Treatment plant design parameters.………………………………………………23
7. Contribution of team members ………………………………………………….27
8. References ……………………………………………………………………….28
3
LIST OF TABLES
1. Population Estimation …………………………………………………………..7
2. Influent Amount Estimation ……………………………………………………..8
3. Pipe diameter ……………………………………………………………………13
4. Treatment plant design parameters ……………………………………………...23
4
LIST OF FIGURES
1. Location of Treatment Pant ………………………………………………………6
2. Course of Sewer Conduit ………………………………………………………..10
3. Screen …………………………………………………………………………....18
4. Suspended solids and BOD removal as a function of overflow rate ……………19
5. Flow chart of treatment plant …………………………………………………....25
6. Plan of treatment plant …………………………………………………………...26
5
1. Treatment Plant Site identification
Fig. 1 Location of Treatment Pant
The red rectangle in the drawing represents the location of the treatment plant. The elevation of
the area, obtained by using the contour map of the permanent campus site lies around 103
metres. Attempts have been made to keep the plant at the lowest possible altitude to avoid
pumping mechanisms for the wastewater to reach the treatment facility. A secluded location has
been chosen to cause minimum hindrance to general campus life and ease of transportation from
far away places.
6
2. Population and Influent Amount Estimation
All estimates have been made for a period of 30 years.
Categories Population
UG Program 6000*
Masters Program 1800*
Doctoral Program 1200*
Total number of students 9000
Faculty 600#
Faculty with family 2400#
Staff 600^
Staff with family 1800^
Total Population 13,200
Table 1 Population Estimation
* UG Students per department per year - 100
Total number of departments - 15
For 4 years of UG Program, Total number of UG Students = 15*4*100
= 6000
Students in masters program per department - 120
Total contribution to population = 120*15
= 1800
Students in doctoral program per department - 80
7
Total contribution to population = 80*15
= 1200
# Assumed faculty - student ratio - 1:15
Number of faculty members = 9000/15
= 600
Assumed family size - 4
Total contribution to population = 600*4
= 2400
^ Assumed number of staff members - 600
Assumed family size - 3
Total contribution to population = 600*3
= 1800
Category Amount of Influent (MLD)
Hostel Complex 1.0*
Residential Complex 0.80#
Academic Complex 0.450^
Total Influent Amount 2.250”
Table 2 Influent Amount Estimation
8
For influent amount estimation, it is assumed that 80% of the consumed water goes out as
wastewater.
* Assumed daily consumption per student - 135 lit/head/day
Total wastewater output = 0.8*135*9000
= 972000 L/day
=0.972MLD
≃ 1.0M LD
# Assumed daily consumption by faculty, staff and respective family members - 225 lit/head/day
Total wastewater output = 0.8*225*4200
= 756000 L/day
=0.756MLD
≃ 0.80M LD
^ Assumed daily consumption - 50 lit/head/day
Total wastewater output = 0.8*50*(9000+600+600)
= 408000L/day
=0.408MLD
≃ 0.450M LD
“ Total discharge from campus = 1.0+0.80+0.450
= 2.25MLD
9
3. Design of Sewer Conduits
The bold lines in the picture represent the plan for the pipelines carrying wastewater from across
the campus to the treatment plant (T).
Fig. 2 Course of Sewer Conduit
Half of the total discharge from the academic complex (225 kL/day) is collected at node 1 and
carried to T. Node 2 receives wastewater from the other half of the academic area (225 kL/day)
10
and 2/3rd of the influent released by the hostel complex (670 kL/day) which is transported here
from node 3.
Node 7 is used to locally collect inflow from 1/3rd of the future residential complex (270
kL/day) which then goes to node 6 and meets the other 1/3rd of the residential inflow (270
kL/day). Finally all the wastewater from node 6 goes to node 5 and receives the remaining ⅓ of
the residential wastewater on the way. Henceforth, the entire wastewater from the residential
complex reaches node 5 and then to node 4 where it meets the remaining 1/3rd of the wastewater
volume from the hostel complex coming from node 8 (330kL/day). Finally, from node 4, it
reaches the treatment facility, T.
CALCULATION OF PIPE DIAMETER USED BETWEEN NODE 1 & TREATMENT PLANT
We assume half flow condition in the pipes. The material selected is PVC ( Manning’s
coefficient, n - 0.01) for it is extremely chemical-resistant, able to withstand acids, salts and
bases because of which it is often used in sewage piping. It is even resistant to some solvents,
such as fuel and paint thinners.
Let the diameter of the pipe be D.
Total Discharge, Q - 225 kL/day
- 0.002604 m3 /s
Elevation of node 1 (upstream end)- 109.4 m
Elevation of Treatment plant (downstream end)- 103 m
11
Distance between node 1 and treatment plant - 600 m
109.4−103
Slope, S0 = 600
= 0.010667
πD2
So, Sectional area of flow, A = 8
πD
Wetted Perimeter, P = 2
A
Hydraulic radius, R = P
D
= 4
1 πD8/3 S 1/2
Using Manning’s equation, Q = n ( 8*4 2/3
0
)
3/8
8*42/3 Qn
On rearranging, D = ( )
πS 1/2
0
On substituting Q = 0.002604 m3 /s, n = 0.01 and S0 = 0.010667
D = 0.09 m
= 3.54 in
Based on available pipe diameters, D = 4 in
Similar calculation were performed for the all paths and results are tabulated below .
12
Table 3 Pipe diameter
4. Wastewater Treatment Process
Water collected in wastewater sewers contains wide variety of contaminants have to be removed
before disposal into the river. In our case, major part of wastewater is black water and grey
water and these contains contaminants like suspended solids, biodegradable organics, pathogens
and nutrients. So following processes are required for treatment of wastewater before disposal.
4.1 Primary Treatment
Wastewater contains a wide variety of solids of various shapes, size and densities. Effective
removal of these solids may require a combination of unit operations such as screening and
settling.
A. Screening
This stage of the plant will have screening devices to remove coarse solids which consist
of sticks, rags, boards and other large objects from wastewater.
13
B. Grit Chamber
Wastewater contains a wide assortment of inorganic solids which are abrasive in nature
and will cause wear of pumps and sludge handling equipment. Additionally these
materials are non-biodegradable therefore desirable to separate them from the organic
suspended solids
C. Primary sedimentation tank
It is a unit operation designed to concentrate and remove suspended organic solids from
the wastewater. It will be equipped with mechanical scrappers to settle sludge and drive it
towards a hopper from where it will be pumped to the treatment facility. Grease or oil
will be skimmed off as they gradually rise to the surface of the water.
4.2 Secondary Treatment
Considering the low population and scarcity of level terrain in the permanent campus, we
propose to setup a trickling filter for secondary treatment of wastewater. It will be used to
degrade the biological content of the sewage derived from human and food waste, soaps and
detergents. Low operational costs and power requirements are other reasons for this choice over
suspended culture system.
The biomass generated by trickling filter represents a substantial organic load and must be
removed to meet acceptable effluent standard by secondary clarifier. Design of secondary
clarifier for attached cultural system (trickling filter) is same as primary clarifier.
14
4.3 Sludge Thickening
The sludge produced and collected during the primary and secondary treatment processes will be
concentrated and thickened to enable further processing. It will be put into a gravity thickening
tank for settling and dewatering. The remaining water will be sent for further treatment and the
sludge will be sent for digestion.
4.4 Sludge Digestion
The sludge settling out after the primary and secondary treatment stages will be directed to
digesters where it undergoes anaerobic digestion. The methane gas and other nutrient rich bio
solids formed in this process can be recycled and used for supplying power to the treatment
plant.
4.5 Disinfection
After the primary and secondary treatment procedures, there are still some diseases causing
organisms in the remaining treated wastewater. To eliminate them, the wastewater will be
subjected to disinfection for a period of 15 minutes in tanks that contain a mixture of chlorine
and sodium hypochlorite. The effluent will be later released into the environment through the
local waterways.
15
5. Treatment Plant Design
5.1 Design of Receiving Chamber
Assumed detention time, t - 60 sec
Average flow = 2250 KL/D
Maximum Flow, q = 2250 * 2.5
= 5625 m3 /day
5625
Volume, V = 24*60
= 3.9 m3
Provide the dimensions as Length = 3 m
Width = 1.5 m
Depth = 1 m
Corrected volume = 4.5 m3
5.2 Design of Grit Chamber
Average Flow- 2.25 MLD
Maximum Flow = 2.5* Average flow
= 2.25*2.5
= 5.625 MLD
= 0.065 m3 /s
Assuming settling velocity = 0.02 m/s
Velocity of Flow = 0.3 m/s
Assuming the depth of the tank, D = 1.5*W , where, W-Width of the tank
16
Q
Area of cross section of the tank = V
0.065
W*D = 0.3
1.5 W2 = 0.216
W = 0.38 m
D = 1.5*W
= 0.57 m
0.57
Detention time, t = 0.02
= 28.5 sec
Length, L = Vt
= 0.3*28.5
= 8.55 m
Provide length, L = 8.6 m
Provide a free board of 0.3 m and Grit accumulation zone of 0.25 m
Then, D = 0.57 + Free Board + Grit Accumulation Zone
= 0.57 + 0.3 + 0.25
= 1.12 m
Provide D = 1.2 m
Length, L = 8.6 m
Width, W = 0.4 m
Depth, D = 1.2 m
17
5.3 Design of Bar Screen
Number of bars in the screen is taken as ‘n’
Assumed bar diameter, d = 10 mm
Clear Spacing, s = 10 mm
Width, w = d(n+1) + s*n
400 = 10(n+1) + 10*n
n = 19.5
Provide n = 20 bars
Fig. 3 Screen
18
5.4 Design of Primary Sedimentation Tank
We assume a 60% removal of suspended solids at average flow.
Fig. 4 Suspended solids and BOD removal as a function of overflow rate
For 60% suspended solids removal, the overflow rate is 35 m/d.
2.25*1000m3 /d
Required Surface Area = = 65 m2
35 m3 /m2 .d
Using Circular Tank, the diameter is
d=
√ 4*A
π =
√ 4*65
3.14 = 9.09 m
Taking the diameter of 9m and assuming a sidewall depth of 3m,
Volume of tank, V = 3*65
= 195 m2
195 m3
Detention time at average flow, t = 2250 m3 /d
= 2.08 hours
5625 m3 /d
At peak flow conditions, the overflow rate - 65 m2
= 86.5 m/day
19
Permissible range of overflow rate - 80 to 100 m/day
Hence, OK.
Typical speed of sludge scraper = 0.03 rev/min
Bottom Slope = 80 mm/m
5.5 Design of Trickling Filter
We propose to install a high rate filter with hydraulic loading ‘Q’ and diameter ‘d’
Assuming Influent
substrate concentration, S0 = 200 mg/l
and Effluent substrate concentration, Se = 25 mg/l
Treatment constant, k = 0.055 min-1
Coefficient relating to the medium characteristics, n = 0.5
Circulation ratio, R = 2
S 0 +RS e
BOD in the mixture of raw and recycled mixture applied to the medium, Sa = 1+R
200 + 2*25
= 1+2
= 83.33 mg/L
−kD
Se e Qn
Sa
= −kD
(1+R)− Re Qn
−0.055*1.5
eQ0.5
25
83.33
= −0.055*1.5
(1+R)− Re Q0.5
20
Q = 0.029 m3/m2.min
Total flow from campus, q = 2250 m3 /day
= 1.5625 m3 /min
q
Surface area, A = Q
= 1.5625
0.029
= 53.88 m2
√
4A
Diameter of the filter, d = π
= 8.28 m
Provide d = 8.5m
Efficiency of trickling filter = ( 200−25
200 ) * 100
= 87.5%
5.6 Design of Secondary Clarifier
Design parameters are same as the primary sedimentation tank.
Diameter = 9 m
Depth = 3 m
Bottom Slope = 80 mm/m
Detention time = 2.08 hr
Speed of Sludge Scraper = 0.03 rev/sec
5.7 Design of Disinfection Tank
Design average flow for tank = 2250 m3 /day
Chlorine dosage = 5 mg/L
21
Contact time = 15 min
Residual chlorine = 0.2 mg/L
2250 15
Volume of tank = 24 *
*60
= 23.4 m3
Provide the dimensions as , Length = 4 m
Width = 3 m
Depth = 2 m
Corrected volume = 24 m3
Amount of chlorine required per day = 2250*1000*5
= 11250000 mg/day
= 11.25 kg/day
22
6. Treatment plant design parameters
S.No. Design Specifications
1. Receiving Chamber
Length 3m
Width 1.5 m
Depth 1m
Detention Time 60 sec
2. Screen
No. of bars 20
Diameter of bars 10 mm
Clear Spacing 10 mm
3. Grit Chamber
Length 8.6 m
Width 0.4 m
Depth 1.2 m
4. Primary Sedimentation Tank
Diameter 9m
Depth 3m
Detention Time 2.08 hrs
Bottom Slope 80 mm/m
Speed of Sludge Scraper 0.03 rev/min
5. Trickling Filter
Diameter 8.5 m
23
Depth 1.5 m
Medium Plastic media
Type High rate filter
Influent BOD 200 mg/L
Effluent BOD 25 mg/L
Recycling Ratio 2
6. Secondary Clarifier
Diameter 9m
Depth 3m
Detention Time 2.08 hrs
Bottom Slope 80 mm/m
Speed of Sludge Scraper 0.03 rev/min
7. Disinfection Tank
Length 4m
Width 3m
Depth 2m
Amount of Chlorine 11.25 kg/day
Table 4 Treatment plant design parameters
24
Fig 5 Flow chart of treatment plant
25
Fig 6 Plan of Treatment Plant
26
7. CONTRIBUTION OF TEAM MEMBERS
Ishan Agrawal - Calculation of population and influent amount, design parameters
Ashutosh Maurya - Deciding the location of the treatment plant and calculation of pipe diameters
Swati - Calculation of influent amount and Making project report
Divyansh Dubey - Treatment process selection and calculation of design parameters
Akshansh Gupta - Population estimation and Making project report
27
8. REFERENCES
● Environmental Engineering by Howard S. Peavy and Donald R. Rowe
● https://en.wikipedia.org/wiki/Sewage_treatment
● https://en.wikipedia.org/wiki/Wastewater_treatment
● https://www.conserve-energy-future.com/process-of-wastewater-treatment.php
28