Date : 14 Oct 2019
PROJECT REFINERY JOBS PUNCH LIST PROGRESS STATUS                                                                                      Rev :
                                                                                                                                                                                            Prepared Report By : Ronaldo Arland
                                                                                                                                                          LIST
NO                     SECTION                                                  DESCRIPTIONS                                                                           New                                           STATUS                                  PROGRESS
                                                                                                                               VI   Check   Cleaning     Repair                  Yes   No
                                                                                                                                                                     Installed
                                                                                                                                                                                                Already open manhole and VI, cleaning waiting the
1                        Vessel                                                                                                                                                                                                                               50.00%
                                                                        Open Manhole & Internal Cleaning                                                                                                          contractor
                                                                                                                                                                                            VI & Check, need new check status after collecting some
2                    Cooling Tower                                                                                                                                                                                                                            20.00%
                                                                                 Internal Cleaning                                                                                                                  data
3                      Deodorizer                           Internal VI including Crown Nozzles & Mammoth Pumps                                                                                        Progress collecting data & make report                 50.00%
                                                          Open the cover for VI filter leaves, cleaning and check for any
4                    Niagara Filter                                                                                                                                                                 Checked, some repaired & ordered accessoris               75.00%
                                                              damage. Install chain hoist for the filter leaves lifting
5                       Bleacher                                           Internal Visual Inspection ( VI )                                                                                           Progress collecting data & make report                 50.00%
                                                         All pump inspection, physical check for any damages and manual
                                                        turn the shaft by hand if posible. Use portable power supply to test                                                                   Wait merger, some damaged specialy G 301 not yet
6                        Pump                                                                                                                                                                                                                                 50.00%
                                                          the motors or use multi meter to test motors power windings. To                                                                                          repaired
                                                                          re-wind the motors if necessary
                                                                                                                                                                                             All done ( need macthed data with Pak Darmono & Pak
7                     Lubricant Oil                                                                                                                                                                                                                           100.00%
                                                                  Refill lubricant oils for all pump and gearbox                                                                                                    Idris )
                                                          VI Barometric Condensers and Water Nozzles, check Ejectors
8                   Vacuum System                                                                                                                                                                                   Some done                                 50.00%
                                                                                  Steam Nozzles
9       Visual Inspection all Process Connection            Check if any parts / components are missing or misplaced                                                                                     Some done, some still on progress                    50.00%
10                        PLC                                                  Power up if possible                                                                                                                 On Progress                                0.00%
                                                                                                                                                                                              Some done, some still on progress. Progress by Pak
11                 Instrument & Valve                                           Check all condition                                                                                         Kongli for installed valve Instrument at refinery, finish with    75.00%
                                                                                                                                                                                                              3 tag device minor repair.
12                      Flushing                                  All process, water, steam, compressed air etc                                                                                 Not yet in the near future, later with the contractor          0.00%
13                     Leak Test                                                For Complete Test                                                                                               Not yet in the near future, later with the contractor          0.00%
14        Panels ( Breakers & Terminal Block )                       Replace and Fix all missing Components                                                                                               On Progress by Pak Nur Hidayat                      50.00%
15                   Cabling Works                       For Instruments & Power including installing the new Instruments                                                                                 On Progress by Pak Nur Hidayat                      50.00%
16              Solenoid for the Actuator                                        All need serviced                                                                                                      Checked and have spare 4 Linear Kit                   50.00%
17                  Piping for plant                                        Complete all the remaining                                                                                        On Progress by Ronaldo and Pak Husain ( BQ done )               50.00%
                                                         All replaced accessoris need to be completed, including installing
18             Cooling Tower Accessoris                                                                                                                                                                        Not yet VI & Checked                            0.00%
                                                                              the Cooling Tower Fan
19   Carbon Steel Pipes Steam Sparging Piping Lines                       Advisable to be Stainless Steel                                                                                                   Checked & macthed with BQ                         50.00%
20              Floor Plates & Staircase                              Damaged checkered need to replaced                                                                                                    2nd Floor staircase repaired                      25.00%
21                 Conveyor Housing                                      Found rusted, repair and painted.                                                                                                         VI & Checked                               50.00%
                                                                                                                                                                                               On progress follow up with Pak Darmono & Pak Idris
22                       Tools                                                   All Tools needed                                                                                             ( Maintenance Oleo ). Have some data from Pak Idris             25.00%
                                                                                                                                                                                                               about tools needed.
                                                                                                                                                                                              VI, checked and collect data. Replacement with new
                                                          All Gasket replacement, including vessels manholes & flanged
23                      Gasket                                                                                                                                                                gasket not yet installed, on progress follow up status,         50.00%
                                                                                   connection
                                                                                                                                                                                                                ordered or not yet.
24             Air Blower & Power Supply                                     Visual Inspection needed                                                                                                     On progress and collecting data                     50.00%
25                      Lighting                                                   For the plant                                                                                                             Some done, some not yet                          50.00%
26                   Lifting Device                                         For any heavy lifting items                                                                                                               Ordered                                 50.00%
                                                                                                                                                                                                                                        Progress Status       43.08%
                   Checked By                                                      Checked By                                                          Approved By                                                          Approved By
                   Sudarmono                                                          Husain                                                             Budi A                                                               Hendry S