0% found this document useful (0 votes)
119 views1 page

Refinery Maintenance Progress

The document provides a progress status report for project refinery jobs punch list with 21 items. It summarizes the status of tasks such as internal cleaning and visual inspections of various equipment like vessels, filters, pumps, and instruments. The progress ranges from 0% to 100% complete across items, with some tasks still ongoing and others waiting on contractors. Flushing and leak testing are scheduled for the future once contractors are involved.

Uploaded by

Ronaldo Arland
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
119 views1 page

Refinery Maintenance Progress

The document provides a progress status report for project refinery jobs punch list with 21 items. It summarizes the status of tasks such as internal cleaning and visual inspections of various equipment like vessels, filters, pumps, and instruments. The progress ranges from 0% to 100% complete across items, with some tasks still ongoing and others waiting on contractors. Flushing and leak testing are scheduled for the future once contractors are involved.

Uploaded by

Ronaldo Arland
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Date : 14 Oct 2019

PROJECT REFINERY JOBS PUNCH LIST PROGRESS STATUS Rev :


Prepared Report By : Ronaldo Arland
LIST
NO SECTION DESCRIPTIONS New STATUS PROGRESS
VI Check Cleaning Repair Yes No
Installed
Already open manhole and VI, cleaning waiting the
1 Vessel 50.00%
Open Manhole & Internal Cleaning contractor
VI & Check, need new check status after collecting some
2 Cooling Tower 20.00%
Internal Cleaning data
3 Deodorizer Internal VI including Crown Nozzles & Mammoth Pumps Progress collecting data & make report 50.00%
Open the cover for VI filter leaves, cleaning and check for any
4 Niagara Filter Checked, some repaired & ordered accessoris 75.00%
damage. Install chain hoist for the filter leaves lifting
5 Bleacher Internal Visual Inspection ( VI ) Progress collecting data & make report 50.00%
All pump inspection, physical check for any damages and manual
turn the shaft by hand if posible. Use portable power supply to test Wait merger, some damaged specialy G 301 not yet
6 Pump 50.00%
the motors or use multi meter to test motors power windings. To repaired
re-wind the motors if necessary
All done ( need macthed data with Pak Darmono & Pak
7 Lubricant Oil 100.00%
Refill lubricant oils for all pump and gearbox Idris )
VI Barometric Condensers and Water Nozzles, check Ejectors
8 Vacuum System Some done 50.00%
Steam Nozzles
9 Visual Inspection all Process Connection Check if any parts / components are missing or misplaced Some done, some still on progress 50.00%
10 PLC Power up if possible On Progress 0.00%
Some done, some still on progress. Progress by Pak
11 Instrument & Valve Check all condition Kongli for installed valve Instrument at refinery, finish with 75.00%
3 tag device minor repair.
12 Flushing All process, water, steam, compressed air etc Not yet in the near future, later with the contractor 0.00%
13 Leak Test For Complete Test Not yet in the near future, later with the contractor 0.00%
14 Panels ( Breakers & Terminal Block ) Replace and Fix all missing Components On Progress by Pak Nur Hidayat 50.00%
15 Cabling Works For Instruments & Power including installing the new Instruments On Progress by Pak Nur Hidayat 50.00%
16 Solenoid for the Actuator All need serviced Checked and have spare 4 Linear Kit 50.00%
17 Piping for plant Complete all the remaining On Progress by Ronaldo and Pak Husain ( BQ done ) 50.00%
All replaced accessoris need to be completed, including installing
18 Cooling Tower Accessoris Not yet VI & Checked 0.00%
the Cooling Tower Fan
19 Carbon Steel Pipes Steam Sparging Piping Lines Advisable to be Stainless Steel Checked & macthed with BQ 50.00%
20 Floor Plates & Staircase Damaged checkered need to replaced 2nd Floor staircase repaired 25.00%
21 Conveyor Housing Found rusted, repair and painted. VI & Checked 50.00%
On progress follow up with Pak Darmono & Pak Idris
22 Tools All Tools needed ( Maintenance Oleo ). Have some data from Pak Idris 25.00%
about tools needed.
VI, checked and collect data. Replacement with new
All Gasket replacement, including vessels manholes & flanged
23 Gasket gasket not yet installed, on progress follow up status, 50.00%
connection
ordered or not yet.
24 Air Blower & Power Supply Visual Inspection needed On progress and collecting data 50.00%
25 Lighting For the plant Some done, some not yet 50.00%
26 Lifting Device For any heavy lifting items Ordered 50.00%

Progress Status 43.08%

Checked By Checked By Approved By Approved By

Sudarmono Husain Budi A Hendry S

You might also like