144 VV
144 VV
NEW DELHI
Coram:
Shri P.K. Pujari, Chairperson
Dr. M.K. Iyer, Member
Shri I. S. Jha, Member
Date of Order: 9th April, 2019
In the matter of
Petition under Central Electricity Regulatory Commission (Indian Electricity Grid Code)
(Fourth Amendment) Regulations 2016 and Central Electricity Regulatory Commission's
DOP on Reserve Shutdown and Compensation Mechanism dated 5.5.2017 for seeking
upward revision of the Technical Minimum fixed for schedule of operation of NLCIL lignite
based Generating Stations (TPS I Expn, TPS II stage 1 & 2, TPS II Expn) and other related
issues.
And
In the matter of
NLCIL
(a joint venture of NLC & TANGEDCO)
Harbour Estate, Tuticorin-628004 …. Petitioner
Vs.
5. APTRANSCO / APPCC,
Vidyut Soudha, Khairatabad,
Hyderabad - 500 082
6. TSTRANSCO / TSPCC,
Vidyut Soudha, Khairatabad,
Parties present :
Shri M.G. Ramachandran, Advocate, NLCIL
Ms. Ranjitha Ramachandran, Advocate, NLCIL
Ms. Anushree Bardhan, Advocate, NLCIL
Shri J. Dhanasekaran, NLCIL
Shri K. Ravikumar, NLCIL
Shri S. Vallinayagam, Advocate, TANGEDCO
Shri Ashok Rajan, SLDC
ORDER
The present petition has been filed by the Neyveli Lignite Corporation of India
Technical Minimum fixed for schedule of operation of NLCIL lignite based Generating
Electricity Grid Code) (Fourth Amendment) Regulation, 2016, which provides for
(b) Provision of fuel oil support leads to mixed firing and this is injurious to the
furnace in the long run, as slagging on the furnace gets accelerated due to this and
use of water lancing is also not possible during low load operation of the Unit.
linked mines capacity of the petitioner is getting affected, resulting in huge revenue
(d) To mitigate the effects of low load operation of Units, reserve shut down of the
Units can be taken but, this affects the performance of the Units in the long run, as
these Units are not designed for frequent shut down and start up.
3. The Petitioner has further submitted that its pulverized lignite fired plants i.e.
Thermal Power Station II – Stage I (3 x 210 MW), Stage II (4 x 210 MW) and Thermal
Power Station I Expansion (2 x210 MW) are also facing following technical problems
(a) Four (4) Mills need to be kept in service while operating the Unit at low loads,
as three (3) Mill operations will lead to Unit tripping in the event of tripping of any one
mill. With the necessity to operate the Units at low load on a continuous basis due to
URS schedule given by beneficiaries in most of the time blocks of the day, operating
the Unit with 3 mills in service warrants fuel oil support, as otherwise, this will lead to
tripping of Unit on any slightest disturbance. This results in mixed firing for prolonged
also could not be taken into service during low load conditions due to furnace
pulsations. Further, shifting of fire ball in the furnace also occurs due to operation of
(b) Single stream operation could not also be followed due to difficulty in ramping
up the load when there is requirement as per schedule and unreliable operation of
the Unit, as tripping of any equipment (Fan, mill etc.,) will lead to Unit tripping.
(c) Increase in mill outlet temperature also leads to unsafe operation. Lignite is
dried in the mill using hot flue gas using flue gas drawn from the furnace through
Resuction duct due to self ventilation of the beater wheel Mill and the temperature of
o
the lignite – gas mixture is to be maintained at 120-180 C as per OEM
recommendation. Hot air is used to reduce the flue gas temperature so as to control
the After Mill Temperature (AMT). The air admission has to be kept at optimum level
so as to maintain the oxygen levels at safer limits to avoid pre ignition and possible
explosions in the mill outlet duct. When the lignite flow is reduced, AMT goes beyond
the limits, resulting in unsafe operation and endangering safety. The vibration levels
(d) There are restrictions in use of Water Lances, which is used for furnace
walls to remove the slag deposits. This process is unique for only Lignite Fired
Boilers. At low loads, heavy fluctuations develop in the furnace if water lances are
taken into service, leading to furnace instability as water quenches the fire ball and
eventually results in tripping of the Unit. Since technical minimum schedule is given
for most of the time blocks, the water lances could not be pressed into operation. If
water lances are not operated for a few days continuously, heavy deposition of slag
Dislodging of this heavy mass of slag from furnace subsequently using water lance
and fall of the same from heights result in damages to furnace hopper (S panel area)
and bottom ash handling systems like After Burning Grates and slag conveyor, which
are located below the furnace. Fall of heavy mass of slag had created explosions in
the Slag bath in the earlier days and repeat of the same cannot be ruled out if the
present situation continues. Unit has to be eventually stopped for attending to the
above problems.
(e) Low load operation results in furnace instability because of flame failure,
leading to eventual tripping of Unit on Fire ball protection, even under optimised air
flow condition. The turbulence created for effective combustion of pulverized lignite
during tripping of running mill/feeder. The after effect on such occasions is violent
other words, there is no more combustion but only explosion. Such incidences are
unpredictable and the only effective way to control this is to take precautionary steps.
Hence oil burners are necessarily to be taken into service to ensure fireball/furnace
(g) Keeping RGMO in service during low load operation also causes difficulties.
Any sudden increase / decrease in load / lignite flow affects the furnace stability very
much.
(h) Reserve shut down of Unit(s) will lead to further under-utilisation of lignite
mines feeding the Power Plants. Moreover, the Units are designed for base load
4. The Petitioner has submitted that apart from the aforesaid problems, the following
additional station specific technical problems are being faced in different Plants of Petitioner
210 MW):- HRH temperature goes as low as 520 degree celcius even with no RH
spray. Sustained low operation of the Unit will damage the LP Turbine last stage
(b) Technical problem Specific to Thermal Power Station II Stage I & Stage
II: Increased RH & SH attemperation flow and furnace temperature due to possible
(c) Technical problem Specific to TPS II Expansion: The petitioner w.r.t. TPS
II Expansion has submitted that this station has Circulating Fluidised Bed
Combustion (CFBC) boilers of 250 MW rating which are the first of its kind in the
country. After overcoming numerous technical problems faced in these boilers, only
from 4th quarter of 2016-17, we are able to run the Units at more than 200 MW and
the availability of the Units is also showing steady improvement. The quantum of
refractory used in the boiler is more than 5000 Tonnes and because of the constant
circulation of hot bed materials along with lignite, many peculiar problems are being
faced in these boilers compared to conventional PF fired boilers. Varying the load as
per schedule and lowering the load up to Technical Minimum schedule pose lot of
technical problems and some of them seriously affect the safe operation of the
operation of the boiler. Any outage of the Unit due to any small disturbance results in
forced outage of Unit for a minimum period of 15 days. Since, more time is required
for the cooling of refractory for the people to enter inside to take up the works.
Order in Petition No. 144/MP/2017 Page 6 of 25
Depending upon the location of the problem, dismantling / recasting of refractory
also becomes necessary and in which case, outage time is still higher. The
fluidization of the bed material and disturbing the evaporation. The high
differential pressure also reduces the primary air flow through nozzles and
sometimes completely blocks the air flow, resulting in fire out in boiler. High
DP also leads to shifting of bed material from one pant leg to another,
affecting the combustor stability. To normalize the above situation and to re-
establish the primary air flow, huge quantity of very high hot bed material has
unsafe operation endangering the safety of the nearby equipment and also
material, lignite feeders will trip, leading to Unit tripping. During normal
ash coolers.
SH/ RH steam temp: The SH and RH coils are located in the Fluidized Bed
Heat Exchangers (FBHEs) in the boiler of TPS II Expansion and there are 4
FBHEs per boiler. During reduction of firing while ramping down, non
FBHE and this causes disturbances in the fluidization process in FBHE, which
iii. High SH/ RH Tube Metal Temperature:- The partial load operation
from its position. This in turn leads to loss of heat due to radiation. Failure of
refractory voids causing erosion of Super heater and Re heater tubes, ending
in tube leakage which warrants forced outage of Boiler. Any repair of coils in
only for 3 to 4 blocks and thereafter firing could not be raised continuously due
wall temperature, leading to eventual tube puncture and shut down of the Unit.
5. The petitioner regarding under-utilization of Neyveli Pit head mines has submitted as
under:
(ii) Since the coming in vogue of technical minimum of 55%, heavy surrender of
(iii) If capacity utilisation of Neyveli mines becomes lesser than 85%, there will be
under recovery of lignite cost as the annual fixed charges of lignite cost is recovered
(v) Due to issues in surrender of power by the beneficiary States, full quantum of
power is not made available to the Generator before hand to undertake trading. This
wasted.
(vi) Under the above circumstances scaling down the technical minimum to 55 %
would result in enormous reduction of power generation by NLCIL Power Plants vis –
a vis lignite production, which ultimately would lead to under utilisation of mines and
under recovery of lignite cost and cascading impact on the financials of the
Company.
6. The petitioner has submitted that, the Petitioner had made a presentation to the
Central Commission during the process of amendment of the Grid Code on the technical
difficulties that the Petitioner’s power plants would face due to reduction of technical
minimum to 55% of installed capacity. In this regard the Petitioner had also filed a Petition
no 132/MP/2016, seeking upward revision of the Technical Minimum fixed for operation of
withdrawn by the Petitioner, but a detailed representation dated 13.12.2016 to that effect
7. Sale of URS in Market:- Further, the petitioner for the sale of URS in market has
submitted that as facilitated by Tariff Policy, ISGSs are permitted to trade the URS power of
beneficiaries in the Power Market. Quantum of URS Power traded in the Power exchange
is included by the RLDCs while notifying the Technical minimum schedule, and this defeats
the very purpose of the Tariff Policy which facilitates trading of surplus power. The
petitioner has prayed to the Commission that URS sold in the market should be treated
independently and allowed over and above the technical minimum schedule of 70%.
8. The respondent TANGEDCO vide affidavit dated 18.9.2017 has submitted that as
per the Notification dated 19.5.2016 of the Ministry of Power, the Central Generating
Stations are given the option of sale of un-requisitioned power at the power exchange due
to surrender of power by the State Utilities and TANTRANSCO has given “No objection
Certificate" to the Central Generating Stations for sale of URS power in the power
exchanges. Further, on one side the Central Generating Stations are benefitted by
collecting the capacity charges from the beneficiary utilities according to the share allocated
in the respective generating station, on the other, by sale of URS power through
exchanges, the Central Generating Stations are once again getting the capacity charge and
energy charge from 3rd party purchasers. In other words, the CGS by selling URS power
9. The respondent no.7 SRLDC vide affidavit dated 10.2.2018 has submitted that the
request of NLCIL for raising the technical minimum to 70% was already raised during the
considering the views of all stakeholders has decided the technical minimum of 55%. The
technical minimum of 55% is very helpful to the system operator in managing the grid as
well as managing the growth of renewable energy variation and unexpected demand
variation. SRLDC has further submitted that technical minimum of 55% may be maintained
and has requested to treat the URS sold in the market as part of technical minimum only.
10. The Petitioner, vide affidavit dated 20.2.2018 in its rejoinder has submitted that
inferior quality lignite power stations need to be considered due to unique nature of Modus
operandi and technical difficulties and further reiterated its contention that URS sold in the
market shall be treated independently and should be allowed over and above the technical
11. The Commission referred the issues raised by the Petitioner to CEA vide letter dated
26.3.2018, seeking suitable advice. The CEA vide its report dated 12.9.2018 on upward
revision of the Technical Minimum of NLCIL's thermal generating stations has given it’s
(i) CERC notified the 4th Amendment to CERC (Indian Electricity Grid Code)
Regulations, 2010 on 06.04.2016 vide which technical minimum was fixed to 55%
MCR of the Thermal units operating with coal and lignite as primary fuel.
Subsequently, CERC vide order dated 05.05.2017 notified the Detailed Operating
(ii) The specific technical aspects of pulverized lignite based plants having
bearing on technical minimum load have been examined in detail including design
and the same are indicated in enclosed Appendix-1 (along with its annexures).
issues brought out M/s NLCIL during visit in CEA officials to their plant, survey of
international literature/ studies on the issue, we are of the opinion that M/s NLCIL
may be allowed to operate its conventional pulverized lignite fired units at the
technical minimum load of 65% MCR vis-à-vis that set at 55% MCR for coal based
plants. However, if in future, the technical minimum load of coal based power plants
is set below the present level of 55% MCR, the technical minimum load of NLCIL’s
lignite based power plants shall also be considered for appropriate reduction from
technology, it is stated that these are the first set of 250 MW CFBC units installed in
the country and modifications are being carried out by them to improve their
Appendix-2 (along with its annexures). They have indicated that a time period upto
30.06.2019 is required for completing the modifications and test the sustainability of
minimum load of 55% for these units upto 30.06.2019 seems to be reasonable. The
13. CEA has given its further analysis /observations on upward revision of the Technical
minimum from 55% to 70% in respect of NLCIL's pulverized lignite fired thermal generating
14. Considering the GCV and the moisture content, the design conditions of fuel for
lignite based plants are inferior to that for coal based plants. In comparison to the boilers for
Order in Petition No. 144/MP/2017 Page 12 of 25
indigenous coal which are designed for a typical GCV of 3800 kcal/kg with moisture content
in the range 10- 15%, the design calorific value of lignite on NCV basis is 2350 kcal/kg with
moisture content as 52% for TPS-1 Expansion units, and gross GCV of 2800 kcal/kg with
15. CEA's standard technical specifications for coal based sub- critical 500 MW units
provide for control range of boiler as 50% TMCR to 100% BMCR. This requirement is
expected to be similar for coal based sub- critical 210 MW units also. The design steam
parameters are to be maintained up to 60% load in case of pulverized lignite power plant
and up to 50% load in case of conventional pulverized coal plants. Moreover, as per the
O&M manual of TPS-II Stage-I main steam, hot reheat steam, cold reheat steam
temperatures shall be controlled within close tolerances between 60 to 100% boiler load.
16. The CEA in comparison to 210 MW conventional coal fired boiler with 210 MW
lignite fired boiler has analysed that low load operation of lignite fired boilers with reduced
number of operating mills results in displacement of the fire ball and has implication of
Further, the combustion stability gets adversely affected at low load for lignite fired boilers
due to very high moisture content as the flue gas is used for heating the lignite and
conventional coal fired boilers, air heated by flue gas in APH is used to dry the coal and
17. The O&M manual also indicates that mill outlet temperature is to be in the range 120
to 180 deg C (140 deg C at 100% MCR). The technical details of mill & lignite burner
system as furnished by NLCIL also indicate that temperature of fuel/ gas mixture at the
milling circuit, it has been indicated that if temperature after the mill increases above 180
deg C, the mill must be immediately stopped. NLCIL made a control desk demonstration to
Order in Petition No. 144/MP/2017 Page 13 of 25
CEA on 25/26 May 2018. Initially, the unit was operating at near full load of about 207 MW
with 5 mills in operation and the outlet temperature of the mills was in the range 154-164
deg C. Slowly and gradually load was reduced to 170 MW with 4 mills in operation and mill
outlet temperature increased to the range of 168-180 deg c. The load was further reduced
to 160 MW, the mill outlet temperature was in the range of 140-165 deg c however, the
combustion stability deteriorated with disturbance in the 2 flame scanner. With further
reduction of load up to 135 MW the combustion was very poor and intensity of 3 flame
scanners deteriorated with mill outlet temperature in the range of 146-183 deg c. The
petitioner NLCIL at this juncture has stated that for further reduction of load one more mill
needs to be taken out and oil gun needs to be cut in. However, the same was not
attempted as tripping of any mill on any account would have resulted in tripping of the unit.
18. The CEA in its observations has mentioned various international references which
mention that technical minimum load achievable by lignite fired thermal power plants are
higher than corresponding minimum load achievable by coal based thermal power plants.
19. Considering all the factors given above , CEA is of the opinion that the petitioner
NLCIL may be allowed the technical minimum load of 65% MCR with a condition that if in
future, the technical minimum load of coal based power plant is set below the present level
of 55% MCR, than the technical minimum load of NLCIL lignite based power plant shall
also be considered for appropriate reduction from the present proposed of 65%.
20. CEA in its technical analysis of operation of TPS-II expansion has observed that
minimum load of 55%. However, the petitioner NLCIL in its request to CERC has submitted
that they are facing technical difficulties in stabilisation of its units and it would require
exemption from operating the unit under technical minimum till a stable operation level is
achieved. The technical difficulties faced by the petitioner NLCIL are as under:-
21. CEA has observed that main problems faced by CFBC based units of NLCIL TPS-II
expansion are increase in combustor differential pressure requiring draining of 860°C bed
material to control the same, significant drop in temperature of HRH steam and disturbance
in Fluidized Bed Heat Exchanger (FBHE) fluidization & drop in its temperature. Although
COD of both the units has been achieved in 2015 (Unit- 1 on 4.7.2015 and Unit- 2 on
22.4.2015), even after 3 years of COD, these units have not been able to achieve the
stable and sustained operation due to various reasons including equipment design
deficiency. The PG test has not been carried out for any unit as yet.
22. As per CEA, there is improvement in the performance of the units over the years.
Modifications are also being carried out in FBHE-coil with the support by BHEL, to improve
the performance. Accordingly, arrangements are also being made to conduct the PG test.
23. The Commission, on request of respondents shared the report of CEA with the
24. TANGEDCO vide affidavit dated 28.12.2018 and 10.01.2019 has filed its reply with
respect to the report of CEA. TANGEDCO vide affidavit dated 10.1.2019 has submitted as
under :
(a) The Commission has notified the Fourth Amendment to Grid Code in 2016
which is binding on the petitioner and cannot be challenged before this Commission.
that CFBC technology was adopted by the petitioner for its characteristics of
excellent vertical and lateral mixing and capability of optimum carbon burn out
resulting in high combustion efficiency with simple operation and quick start-up.
However, the TPS-II Expansion has not able to achieve its full capacity from the date
(c) The petitioner is seeking to modify the operational parameters for the purpose
of technical minimum to suit its convenience after the amendment of the Grid Code
following due process of law. In the light of settled law, once the recommendations of
CEA and the comments of all the stakeholders are considered and an amendment
is notified by CERC under Scetion 178 of the Act and the same legislation cannot be
25. The petitioner in its rejoinder vide affidavit dated 19.2.2019, has submitted that, the
the Petitioner is not challenging the provisions of Grid Code but it has only sought for relief
from the Commission in exercise of the powers to remove difficulties and power to relax,
which are provided in the Grid Cod itself. Further, the petitioner has submitted that the
report submitted by CEA was after examining all the aspects and difficulties faced by the
generating station during operation, hence, there is no legal ground for TANGEDCO to
consideration :
27. TANGEDCO has submitted that the present petition is not maintainable as the
amendment in Grid Code was brought after following the due procedure of giving
opportunities to the affected parties. The review of Technical minimum of 55% MCR of the
generating units is a direct challenge to the Fourth Amendment of Grid Code. TANGEDCO
has further submitted that, the petitioner can challenge the amendment to the Regulation
before the appropriate forum. It has stated that on one hand the Central Generating
Stations are benefitted by collecting the capacity charges from the beneficiary utilities
according to share allocation and on the other hand, they are getting capacity charge and
energy charge from the purchasers by sale of URS power through power exchange. The
28. Regulation 54 and Regulation 55 of the Grid Code deals with "Power to Remove
Difficulty" and "Power to Relax". The said provision have been put in place to cater to the
specific difficulties faced by a particular stake holder including any generator as well
beneficiaries in application of certain regulations. The Power to Relax and Power to remove
difficulties may be exercised in appropriate cases and it does not amount to the
amendment of the Regulation. The Appellate Tribunal in its judgment dated 25.3.2011 in
Appeal No.130 of 2009 (RGPPL V CERC & ors) had held that the power to remove
difficulties is to be exercised when there is difficulty in effecting the Regulations and not
India (1975) 2 SCR 640, the Hon’ble Supreme Court had held as under:-
29. In the present case the Petitioner is facing specific difficulties while operating its
lignite based stations at technical minimum of 55% as notified by the commission for
thermal units and therefore, is seeking relaxation by invoking power of relaxation under
Regulation, 55 and power to remove difficulty under Regulation, 54. It is observed that only
lignite fired thermal stations, are facing technical problems in operating at the technical
Remove Difficulty" and "Power to Relax" under Grid Code based on the merits.
30. We are not inclined to accept the contention of TANGEDCO that the present petition
is not maintainable.
pulverized lignite fired plants as prayed by the petitioner based on technical difficulties
being faced by these units of the petitioner, the Commission has observed the following
a) Design conditions of fuel for lignite based plants are inferior to that for coal
based plants. Boilers for indigenous coal are designed for a typical GCV of 3800
kcal/kg with moisture content in the range 10- 15%, the design calorific value of
lignite on NCV basis is 2350 kcal/kg with moisture content as 52% for TPS-1
Expansion units, and gross GCV of 2800 kcal/kg with moisture content of 48.5% for
c) As per O& M manual of TPS-II Stage-I main steam, hot reheat steam, cold
d) Low load operation of pulverized lignite fired boilers with reduced number of
operating mills results in displacement of the fire ball and has implication of
boilers. Further, the combustion stability gets adversely affected at low load for
lignite fired boilers due to very high moisture content as the flue gas is used for
heating the lignite and transporting it to boiler and there is no regulation on flue
gas drawn, however, in conventional coal fired boilers, air heated by flue gas in
e) While in operation, in case temperature after the mill increases above 180
degree celcius, the mill must be immediately stopped. NLCIL made a control desk
demonstration to CEA on 25/26 May 2018. Initially, the unit was operating at near
full load of about 207 MW with 5 mills in operation and the outlet temperature of
the mills was in the range 154-164 deg C. Slowly and gradually load was reduced
to 170 MW with 4 mills in operation and mill outlet temperature increased to the
range of 168-180 degree celcius. The load was further reduced to 160 MW, the
mill outlet temperature was in the range of 140-165 degree celcius. However, the
further reduction of load up to 135 MW (around 65% MCR) the combustion was
very poor and intensity of 3 flame scanners deteriorated with mill outlet
temperature in the range of 146-183 degree celcius. The Petitioner at this juncture
Order in Petition No. 144/MP/2017 Page 19 of 25
has stated that for further reduction of load, one more mill needs to be taken out
and oil gun needs to be cut in. However, the same was not attempted as tripping
of any mill on any account would have resulted in tripping of the unit.
33. After consideration of the above observations based on the technical issues as brought
out by the petitioner in the petition and as submitted by CEA in its report, we are of the view
that technical minimum of 55% as per the Fourth Amendment of the Grid Code is not
sustainable for pulverized lignite fired units and is leading to unstable and unsafe operation
with shifting of fire ball and possible tripping of mills/units. Accordingly, the Commission in
line with the recommendation of CEA that technical minimum of 65% may be allowed for
pulverized lignite fired units of NLCIL, allows technical minimum of 65% for TPS-II, Stage-1
34. However, CEA in its report has also recommended that if in future, the technical
minimum load of coal based power plants is set below the present level of 55% MCR, the
technical minimum load of Petitioner’s lignite based power plants shall also be considered
for appropriate reduction from the present proposed 65% MCR. In the light of this, NLC
may explore with Original Equipment Manufacturer, the possibilities to run these units at
Issue No. 3 : Whether any exemption may be granted to generating stations based on
CFBC technology?
technology, the Commission, based on difficulties as brought out by the petitioner in the
a) The CFBC units of NLCIL are the first set of 250 MW CFBC units installed in
the country and modifications are being carried out by them to improve their
performance.
b) During low load operation , the units face following operational problems i)
860°C bed material to control the same, ii) significant drop in temperature of HRH
steam and iii) disturbance in Fluidized Bed Heat Exchanger (FBHE) fluidization &
c) Although COD of both the units has been achieved in 2015 (Unit- 1 on
4.7.2015 and Unit- 2 on 22.4.2015), even after 3 years of COD, these units have not
been able to achieve the stable and sustained operation due to various reasons
"Based on consideration of the factors indicated in Appendix-2, the request of NLCIL for
exemption from compliance of technical minimum load of 55% for these units upto
30.06.2019 seems to be reasonable. The same is recommended to be favourably
considered by CERC."
36. After consideration of the above observations based on the technical issues as
brought out by the petitioner in the petition and as submitted by CEA in its report, we are of
the view that low load operation of CFBC based units of NLCIL is not sustainable as it is
causing operational difficulties as brought out above and leading to low availability and
forced outages. CEA has observed that with the modifications being carried out in FBHE
coil with the technical support of BHEL, trend of improvement in performance has been
Accordingly, Commission in line with the recommendation of CEA allows CFBC based plant
of NLCIL i.e TPS II Expansion, exemption from technical minimum of 55% till 30.06.2019.
The Technical Minimum for such plants shall be 65% till 30.06.2019.
37. Regarding the submission of SRLDC that Grid Code limit of 55% may be maintained
other incidents like abnormal weather conditions etc., it is observed that upward revision of
technical minimum of only specific generators based on the technical difficulties would not
take away the flexibility for accommodating RE generation which is available to system
operators in terms of going down to technical minimum of 55% for all inter-State generating
Issue No. 4 : Whether the Petitioner’s generating station should be made exempted
from Reserve Shut Down provision ?
38. The third proviso to clause (3) of Regulation 6.3 B of the Grid Code reads as under :
“Where the scheduled generation falls below the technical minimum schedule, the
concerned CGS or ISGS shall have the option to go for reserve shut down and in such
cases, start-up fuel cost over and above seven (7) start / stop in a year shall be considered
as additional compensation based on following norms or actual, whichever is lower:”
39. It is observed that on one hand the Petitioner has put forward various operational
issues its generating stations face during low load operation based on which its prayer of
considering technical minimum of 65% has been accepted for its pulverized lignite fired
stations and exemption has been granted to its CFBC generating station and on the other
hand it prays to remain out of reserve shutdown if the scheduled generation falls below the
technical minimum schedule. In this regard, the Grid Code has given option to the
generators for going for Reserve Shut Down, if the scheduled generation falls below the
on operating at the technical minimum, the difference between the actual generation and
scheduled generation would be accounted under DSM mechanism. As such, the prayer of
Issue No. 5 : Whether URS sold in the market should be treated as independently
over and above the technical minimum schedule ?
40. The Petitioner has prayed that the URS sold in the market should be treated
independently and be allowed over and above the technical minimum schedule of 70 %. In
this regard the respondent SRLDC has submitted that the URS sold in the market should
be treated as a part of technical minimum only and URS should not be treated
41. URS Power includes (i) the quantum of power which has not been dispatched by the
power plant owing to the original procurer not dispatching the same; (ii) the quantum of
power which has not been taken within two hours by procurers entitled to exercise their first
right to receive the quantum not dispatched by the original procurer; and (iii) the said
42. In this regard, we are agreeable with the contention of SLDC that URS should not be
treated independently i.e. over and above the technical minimum otherwise it would defeat
the very purpose of allowing the RLDCs/SLDCs to call for operating the generators on
generation to its full potential. We therefore, hold that URS shall be treated as a part of
43. Further, we are not inclined to accept the submission of TANGEDCO that generators
are collecting double capacity charges as well as energy charges by way of sale of URS
power in the market, based on consent of beneficiaries. The clause 6.5 (A) (c) of IEGC (fifth
(a).....................
(b)....................
(c) In case of sale of share of original beneficiaries in market by ISGS for which
consent has been given, the realized gains shall be shared between the ISGS and
the concerned beneficiary in the ratio of 50:50 or as mutually agreed by the ISGS
and concerned beneficiary in the billing of the following month. This gain shall be
calculated as the difference between selling price of such power and fuel charge
including incidental expenses.
Provided that such sale of power by ISGS shall not result in any adverse impact on
the original beneficiary (ies) including in the form of higher average energy charge
vis-à-vis the energy charge payable without such sale:
Provided also that, the liability of fixed charge in such cases shall remain with
original beneficiary (ies) as determined in accordance with the Tariff Regulations
notified by the Commission from time to time
44. The provision of Grid Code (Fifth Amendment) Regulation, 2017 clearly provides for
sharing the gains in the ratio of 50:50 in case of sale in open market. It is observed that
provision of sharing of the revenue, earned over and above the fuel cost, with the
beneficiaries takes due care of the interests of the beneficiaries. Hence, the contention of
the TANGEDCO that generating stations are recovering two capacity charges by selling
45. In view of the above discussions, the decisions of the Commission are summarised as
under:
(b) TPS-II, Stage-1 & Stage-2 Units: Technical minimum of 65% MCR is allowed.
(Provided, with a condition that if in future, the technical minimum of coal based
generating station is set below the present level of 55%, than the technical minimum
load of NLCIL lignite based power plant shall also be revised appropriately.)
operations up to 30.06.2019.