Chapter-1 Baggi Power Plant
Chapter-1 Baggi Power Plant
1
1.2.1 THE BEAS PROJECT HAS TWO UNITS CALLED UNIT-I – BSL PROJECT AND
UNIT-II – BEAS DAM
It was considered as the part of the Master plan and it was to construct to harness the waters of
the three eastern rivers through the Satluj, the Beas and the Ravi for irrigation and power-
production in an integrated manner. After the construction of Bhakra-Nangal Project, the water
of Satluj (average flow 16,652 million cum or 13.5 million-acre feet) was entirely utilize.
Through the support of the existing Madhopur-Beas link, which carry-over, on around 2344
million cum (0.9 million acre feet) water of Ravi to the Beas, the Beas dam at Pong jointly with
the Bhakra Dam help India in utilizing around 92% of the average inflow of water of the three
eastern rivers. After finishing of construction work of Beas-Satluj Link project, the figure has
further reached at 97%.
2
Beas Project; and the Chief Engineer, Rajasthan Canal Project. A Board of Consultants for Beas
Project was constituted under the chairmanship of Dr.A.N.Khosla consisting of some most
eminent and experienced engineers from within the country and outside. The present scheme was
gradually evolved through a detailed and systematic study of the various alternatives after
seeking advice from United States Bureau of Reclamation (USBR)
3
CHAPTER-2
BEAS PROJECT UNIT-1
The 1957 project contemplated a link of 254.85 cumecs capacity comprising the following
components:Diversion Dam at Pandoh 11.26 km long tunnel from Pandoh to Riggar 19.31 km
long open channel from Riggar to Sundernagar4.824 km long tunnel from Sundernagar to the
Alsed khad near the Malindi village In the second stage, the tunnel from Sundernagar to the
Alsed khad was proposed to be extended to the power plant site on the right bank of the Satluj
River. The power house was also to be constructed in this stage. In the ultimate stage, it was
proposed to construct dam at Larji. However, the construction of a 213.86 m (700 ft) high dam at
Larji was subject to its technical and financial feasibility.
4
million acre ft) in the Suketi Reservoir, besides meeting the additional irrigation needs of
Southern Punjab from the Bhakra Reservoir.
The proposed Suketi Reservoir covered an area of about 9308 hectares (23000 acres) in the Balh
Valley and the fact of its submergence was viewed unfavourably by the Government of Himachal
Pradesh. However, the scheme was abandoned because the feasibility of 134.11 m (440 ft) high
dam in the seismic zone could not be properly established with the data available. Further studies
indicated that a dam of 99.06 m (325 ft) height with a live storage of 1233 million cubic
metres(1.0 x 106 acre ft) would submerge an area of 6475 hectares (16000 acres) only and would
still retain a substantial power potential. Moreover, it was considered feasible to construct a
rockfill dam of this height. But, on account of the objection of Himachal Pradesh Government to
the submergence of the Balh Valley, this scheme was also held in abeyance.
5
8.53 m dia, 13.68 km long Sundernagar Satluj Tunnel for design discharge of 212.376
cumecs (7500 cusecs).
Bumka/Bharari By-pass Link.
21.95 m dia, 76.2 m high differential type surge shaft with an internal riser of 7.62 m
diameter.
Satluj Power Plant on the right side of Satluj River with an installed capacity of 636 MW
(Units of 106 MW each).
The features of the proposal of the final scheme as adopted for construction are as below:
6
CHAPTER-3
BEAS PROJECT UNIT–II
3.1 BEAS DAM PROJECT
The idea of a storage dam across Beas River at Pong was first mooted by Mr. C.E. Blaker of
the Punjab PWD Irrigation Branch in 1926. A committee, led by Mr. A.J. Willey, Consulting
Engineer, to the United States Bureau of Reclamation, Dr. P.S. Pinfold, the Chief Geologist
to Attock Oil Co., and Mr. W.H. Nicholson, Superintending Engineer of Punjab PWD
Irrigation Branch was appointed by Punjab Government in 1927 to report on the possibilities
of storage of surplus waters of the Punjab rivers and their tributaries. The committee, on the
basis of Mr. Blaker’s report, recommended that in view of high floods which were likely to
occur at that site, an economical storage would be difficult to arrange. The committee was
also of the opinion that in view of the soft, though uniform foundation a shingle and boulder
embankment might prove to be the most practicable proposition.
7
3.1.3 FINAL PROPOSAL OF THE PROJECT
Subsequent to the preparation of 1959 project report, considerable work on geological
explorations, investigations for materials, preparations of preliminary designs, comparison of
the economics of various types of layout of appurtenant works etc., was carried out. The
Board of Consultants under the Chairmanship of Dr. A.N. Khosla, comprising some of the
most eminent engineers from within the country and abroad contributed towards finalization
of project proposal. The advice of United States Bureau of Reclamation was also sought on
various features of the project. Numerous hydraulic model tests were conducted at Central
Water & Power Research Stations, Pune and Irrigation & Power Research Institute, Amritsar,
as an aid to designs. The final scheme was gradually evolved through a detailed and
systematic study of the various alternatives.
The Proposal of features of the final scheme as adopted for constructions are as below:
Dam: An earth-core-cum-gravel shell dam is 132.59 m (435 ft) above the deepest foundation
level and 100.58 m (330 ft) above the deepest river bed Beas Dam at Pong.
Diversion Works: The construction of the dam involved diversion of the river through five
cement concrete lined tunnels which have been designated as T1, T2, P1, P2 & P3 from left
to right. These tunnels each of 9.14 m (30 ft) finished dia, have an aggregate length of 5016.7
m.
Outlet Works: Permanent intakes alongwith trashrack structures, etc., have been provided on
bench at El. 374.90 m. The gates are normally operated from the control chamber floor at
El.343.66 m and can also be operated from the hoist house, located above El.435.86 m in
case of emergency. Each control chamber is connected to the hoist house through a vertical
shaft.
Penstock Works: Each of the three penstock tunnels P1, P2, P3 is equipped with 3.048 x
6.401 m (10 x 21 ft) fixed wheel type emergency gate operated by a hydraulic hoist of 150
tonne capacity. The gates are operated from hoist structures located on top of the dam, which
are connected to the tunnels by means of vertical shafts. Downstreams of emergency gates,
steel penstocks of 7280-mm inner dia have been installed in each tunnel of 9.14 m dia.
Butterfly valves are provided at downstream end of each penstock branch.
Spillway: An overflow type, gated chute spillway, with a discharging capacity of
approximately 12375 cumecs (437000 cusecs) at the highest flood level El.433.121 m has
been provided on the left abutment Beas Dam - Spillway.
8
Pong Power Plant: Pong Power Plant (396 MW i.e. 6x66 MW) is a multi storeyed re-inforced
concrete framed structure having 143.04 m length 33.11 m width and 43.48 m height, located
in the stilling basin downstream of penstock tunnels Pong Power House.
Switch-Yard: The 220 kv switch-yard has been located close to the power plant to its right.
Generators are connected to 3 phase step-up transformers for stepping up the generation
voltage of 11 kv to 220 kv.
9
CHAPTER-4
HYDROELECTRIC POWER PLANT
4.1 GENRATION
Generation of electricity by hydropower (potential energy in stored water) is one of the
cleanest methods producing electric power. In 2012, hydroelectric power plants contributed
about 16% of total electricity generation of the world. Hydroelectricity is the most widely
used form of renewable energy. It is a flexible source of electricity and also the cost of
electricity generation is relatively low. This article talks about the layout, basic components
and working of a hydroelectric power station.
Fig4.1 layout
The above image shows the typical layout of a hydroelectric power plant and its basic
components.
10
4.2.1 DAM AND RESERVOIR:
The dam is constructed on a large river in hilly areas to ensure sufficient water storage at
height. The dam forms a large reservoir behind it. The height of water level (called as water
head) in the reservoir determines how much of potential energy is stored in it.\
4.2.3 PENSTOCK:
A penstock is a huge steel pipe which carries water from the reservoir to the turbine. Potential
energy of the water is converted into kinetic energy as it flows down through the penstock
due to gravity.
4.2.5 GENERATOR:
A generator is mounted in the power house and it is mechanically coupled to the turbine
shaft. When the turbine blades are rotated, it drives the generator and electricity is generated
which is then stepped up with the help of a transformer for the transmission purpose.
11
4.3 POWER PLANTS ELECTRICITY GENERATING STATIONS
4.5 ADVANTAGES
No fuel is required as potential energy is stored water is used for electricity generation
Neat and clean source of energy
12
Very small running charges - as water is available free of cost
Comparatively less maintenance is required and has longer life
Serves other purposes too, such as irrigation
4.6 DISADVANTAGES
Very high capital cost due to construction of dam
High cost of transmission – as hydro plants are located in hilly areas which are quite
away from the consumers
13
CHAPTER-5
EMERGENCY ACTION PLAN
5.1INTRODUCTION
The Beas Satluj Link Project, the largest hydro- electric-cum-tunneling project in the
country diverts about 4,716 million cubic meter of Beas Waters from a point at Pandoh
in Mandi District, 114 Km. upstream of Beas Dam at Pong, into the Satluj basin near
village Dehar (upstream of the Bhakra Reservoir) through a water conductor system.
Through it water cascades down a 320m (1049.60 feet) fall to generate power at the
Satluj end.
5.2 DAM
14
5.3 CONCRETE SPILL WAY
Achute spillway constructed on the left abutment is capable of passing discharge of about
9939 cumecs. At the maximum reservoir level of 896.42m (2940.25 feet. A flip bucket at an
Angle of 35 degree is provided at the downstream end of the chute to focus the jet of water
away from the spillway structure.The crest structure has five 12m wide x 13m (39.36 x 42.64
feet)high orifices separated by 3.50m (11.48 feet) wide piers. Each opening is provided
with a hydraulically- operated radial type gate.
15
5.4 PANDOH BAGGI TUNNEL
The 13.10km long tunnel, with a diameter of 7.62m in concrete lined. It has a maximum
discharge capacity of 254.85 cumecs . the upstream and the down strem invert level of the
tunnel vary from the elevation of 867.54m to 835.15m.
16
Fig 5.4 control work
The circular tunnel at the gated control end has been transitioned in rectangular conducts,
each conduct 2.67m wide and 4.27m high. Each conduct is provided with two gates in
tandem, each 2.67m wide and 4.27m high.The down stream gate is of the slide type and
serves as a regulating gate while the upstream is of fixed wheel type with upstream stealing.
The stilling basin is divided into two compartments by a longitudinal wall.
17
full supply depth varies from 6.26m to 5.85m. The channel has a slope of 1 in 6.666 and the
expected maximum velocity is 1.84m
18
fig 5.6 balncing reservoir
The Sundernagar Satluj Tunnel is the last link of the long water conductor system with
a discharge capacity of 403.52 cumecs (14250.18 Cs.) for feeding the machines of Dehar
Power Plant. This tunnel, 12.35 Kms. Long and having a finished diameter of 8.53 m (27.97
feet), takes off from the balancing reservoir and ends in the surge shaft and penstocks. The
upstream and downstream invert levels of the tunnel vary between 818.08 m (2683.30 feet)
and 762m (2499.36 feet).The intake structure of the tunnel at the Pung is of a conventional
semicircular type-a trash rack structure jutting out of the vertical faced wall. The trashrack
structure which is about 20.12 m (65.99 feet) high has 6 bays of 4.52 m (14.82 feet) each.
The structure is followed by a cut- and- cover conduit 6.10m (20 feet) high and 9.39 m (30.79
feet) wide with a high breastwall at its face. The conduit is transitioned into a 8.53 m (27.97
feet) diameter tunnel.
19
type surge shaft of 22.86m (75 feet) finished diameter and 125 m (410 feet) depth with a
reinforced concrete riser of 7.62 m (25 feet) diameter linked with the main shaft
20
Fig 5.8 Penstocks
21
CHAPTER-6
ACHIEVMENT
22
Implementation Programme.E-Procurement Has Been Implemented For Procurements
Having Threshold Value Of Over Rs.10 Lacs.Integrity Pact Has Been Implemented And Two
Independent External Monitors Have Been Appointed With Whom Regular Meetings Are
Being Held
.
6.3 NATIONAL HYDROLOGY PROJECT
World Bank Aided National Hydrology Project For Real Time Decision Support System To
Facilitate Optimum Operation Of Reservoirs Was Successfully Completed. This Is First Of
Its Kind Project In The Country Which Will Further Improve And Expand The Water
Resources Monitoring System, Strengthen Water Resources Operation And Planning And
Will Enhance Institutional Capacity For Water Resources Management.
In Technical Collaboration With Central Board Of Irrigation And Power, Central Water
Commission Supported By World Bank. Delegates From India And Across The World
Participated In The Conference. The Conference Provided Interactive Platform For Eclectic
Brainstorming And Sharing Path Breaking Ideas & Case Studies In Respect Of Flood And
Drought Management, System, Storage Projects Etc.To Address Pressing Issues Regarding
Sustainable Management Of Water Resources.
23
6.5 RENOVATION, MODERNIZATION AND UPRATING (R,M&U)
All The Five Units Of Bhakra Right Bank Powerhouse Have Been Renovated, Modernized
And Uprated From 120 Mw To 157 Mw Each, Resulting In An Additional Installed Capacity
Of 185 Mw And Additional Annual Generation Of 310 Mu.The Ministry Of New And
Renewable Energy Set The Target Date Of 13 Oct.,2017 Of Commissioning Of 175kwp
Solar Power Plant On The Roof Top Of Bbmb Secretariat Sector-19 And Sldc Building,
Industrial Area, Chandigarh. This Solar Power Plant Has Been Commissioned On 18th July,
2017 Much Before The Target Date.Bbmb, A Pioneer In Hydro Electric Generation Added
Another Feather In Its Cap On 18.12.2018 By Installing Grid Connected Roof Top Solar
Power Plant Of Total Capacity Of 100kwp At 220kwp Sub-Station, Jalandhar And 60kwp At
220kwp Sub-Station, Bbmb, Jamalpur.Installing Of 20kwp And 80kwp Solar Roof Top Pv
Plant Have Been Also Commissioned On 29.01.2019 At Control Room Building Of 220kv
Sub-Staton At Narela And Punjabi Bagh, Delhi Respectively.Installing Of 300kwp And
850kwp Solar Roof Top Pv Plant Have Been Commissioned At Talwara On 16.05.2019
& At Nangal (From 01.06.2019 To 24.06.2019) Respectively.Bbmb Has Replaced Old
Transformer At 220 Kv Sub-Stations Dhulkot, Jagadhari And Jalandhar And Commissioned
With Higher Capacity New Power Transformers Of Rating 100mva.The Commissioning Of
These Three Power Transformers Has Helped In Achieving The Target 24x7 Power Supply
Initiative Of The Ministry Of Power, Govt. Of India And The People Of These Areas Would
Get Uninterrupted Power Supply.
24
CHAPTER-7
COMPONENTS
7.1 COMPONENT USED IN BAGGI CONTROL ROOM
1. Water Flow Control System/Control Gate.
2. Substation
3. Eot Cranes
4. Control Panels
5. Genrating System
25
7.1.2 SUB-STATION
A substation is a part of an electrical generation, transmission, and distribution system.
Substations transform voltage from high to low, or the reverse, or perform any of several
other important functions. Between the generating station and consumer, electric power may
flow through several substations at different voltage levels. A substation may
include transformers to change voltage levels between high transmission voltages and lower
distribution voltages, or at the interconnection of two different transmission voltages.
Substations may be owned and operated by an electrical utility, or may be owned by a large
industrial or commercial customer. Generally substations are unattended, relying
on SCADA for remote supervision and control. handling the emergency situation aptly.
The word substation comes from the days before the distribution system became a grid. As
central generation stations became larger, smaller generating plants were converted to
distribution stations, receiving their energy supply from a larger plant instead of using their
own generators. The first substations were connected to only one power station, where the
generators were housed, and were subsidiaries of that power station.
26
7.1.3 ELECTRIC OVERHEAD TRAVELING CRANE
Electric overhead traveling crane or EOT crane is one of the most common types of
overhead crain, or called bridge cranes, which consist of parallel runways with a traveling
bridge spanning the gap. As obvious from the name, EOT crane is operate by electric,
generally there is an operator cabin or a control pendant along with the EOT crane.
27
CHAPTER-8
GENRATION
8.1 GENERATORS:
In hydro generation, a generator is a device that converts motive power (mechanical energy)
into electrical power for use in an external circuit. Sources of mechanical energy include
steam turbines, gas turbines, water turbines, and internal combustion engines and even hand
cranks. The first electromagnetic generator, the Faraday disk, was invented in 1831 by British
scientist Michael Faraday. Generators provide nearly all of the power for electric power
grids.
Electromagnetic generators fall into one of two broad categories, dynamos and alternators.
Dynamos generate pulsing direct current through the use of a commutator
Alternators generate alternating current
28
8.2 CONSTRUCTIONAL DETAILS:
Basically, a generator is consisting of 2 parts
8.2.1 STATOR:
A stator is a stationary part of a genitor that means the stator do not move physically at all. In
entire process of generation, the stator remains stationary. In a large synchronous
machines/generators the stator is consist of a magnetic material core and a copper winding.
The core is made up of silicon steel stamped together. It is done so to reduce the leakage
current and the eddy current losses. The 3phase winding is made up of copper and are
inserted in the core of the stator. The core has slots in them to hold on the windings. There
are 2 types of windings done in the stator one is lap winding and the other one is wave
winding. The wave winding is a complex and commonly used winding type in synchronous
generators. Stator winding terminals are connected with the bus bar connections in the circuit.
29
8.2.2 ROTOR:
A rotor is a rotating device which means the rotor rotates physically all the time during
the/1generation.
In a large synchronous generator, the rotor consists of a core mounted on the shaft and the
field copper windings the windings are of single phase. The rotor is connected with the
turbine and the windings of the rotor are connected with the battery bank first and then short
circuited with the stator windings of the generator. The rotor plays the main role in the
generation of the electricity a rotor may be of silent pole and non-silent pole rotor. The silent
pole rotor basically consists of the more then 4 to 5 poles and an no silent pole is consist of 2
to 4 poles. The non-silent pole is more fast then the silent pole rotor. By joining these two
components together we can make a large synchronous generator to reduce the effect of
vibration and friction in the alternator the fluid friction reduction process is used. And the
flooring process is used to reduce the vibration effect of the power station. The turbine is
attached to the shaft of the rotor and the rotor windings are mounted on the shaft.
30
Fig 8.4 Rotating Magnetic field
Supplied by the generator determines the voltage. If the load is inductive, then the angle
between the rotor and stator fields will be greater than 90 degrees which corresponds to an
increased generator voltage. This is known as an overexcited generator. The opposite is true
for a generator supplying a capacitive load which is known as an under excited generator. A
set of three conductors make up the armature winding in standard utility equipment,
constituting three phases of a power circuit— that correspond to the three wires we are
accustomed to see on transmission lines. The phases are wound such that they are 120
degrees apart spatially on the stator, providing for a uniform force or torque on the generator
rotor. The uniformity of the torque arises because the magnetic fields resulting from the
induced currents in the three conductors of the armature winding combine spatially in such a
way as to resemble the magnetic field of a single, rotating magnet. This stator magnetic field
or "stator field" appears as a steady rotating field and spins at the same frequency as the rotor
when the rotor.
31
moving past the armature windings. Each passing of a north and South Pole corresponds to a
complete "cycle" of a magnet field oscillation. Therefore, the constant of proportionality is,
where P is the number of magnetic rotor poles (almost always an even number), and the
factor of 120 comes from 60 seconds per minute and two poles in a single magnet;
In practice, the typical load is inductive in nature. The diagram above depicts such an
arrangement. It is the voltage of the generator, and is the voltage and the current in the load
respectively and is the angle between them. Here, we can see that the resistance, R, and the
reactance, play a role in determining the angle. This information can be used to determine the
real and reactive power output from the generator.
32
The rotating magnetic field induced an as voltage in the stator winding. often there are three
sets of stator windings, physically offset so that the rotating magnetic field produce a three
phase current, displaced by 1/3 of a period with respect to each other. The rotor magnetic
field may be produced by induction by permanent magnet or by a rotor winding energized
with direct current through slip rings and brushes. The rotor magnetic field may even be
provided by stationery field winding. with moving pole in the rotor. Automotive voltage by
varying the current in the rotor field winding. Permanent magnet machine avoids, the loss due
to magnetizing current in the rotor, but the restricted in size, due to cost of magnet materials.
Alternator used in central power station may also control the field current regulate reactive
power and held to stabilize the power system against the effect of momentary fault
33
Fig 8.6 Power Transformer
8.7.2 BREATHER:
Installed in a pipe from conservator. One end is connected to air cushion in conservator.
Other end to external air. Air cushion in upper portion of conservator is in communication
with external atmosphere through the breather. Breather is filled with dry silica gel (PINK).
When oil is contracted during low temperature/loads, air is breathed in by the conservator
through the breather. Silica gel absorbs the moisture and admits only dry air.
34
8.7.4 WINDING TEMPERATURE INDICATOR:
It takes input from thermocouple placed in the tank near hot oil and from the CT secondary
which measures the current in winding.
35
Electrical circuit just by switching off the circuit breaker. So for better safety, there must be
some arrangement so that one can see the open condition of the section of the circuit before
touching it. The isolator is a mechanical switch which isolates a part of the circuit from the
system as when required. Electrical isolators separate a part of the system from rest for safe
maintenance works. So the definition of isolator can be rewritten as an isolator is a manually
operated mechanical switch which separates a part of the electrical power. Isolators are used
to open a circuit under no load. Its main purpose is to isolate one portion of the circuit from
the other and is not intended to be opened while current is flowing in the line. Isolators are
generally used on both ends of the breaker so that repair or replacement of circuit breaker can
be done without any danger.
36
8.10.1 CURRENT TRANSFORMER
A current transformer (CT) is a type of transformer that is used to measure alternating current
(AC). It produces a current in its secondary which is proportional to the current in its primary.
Current transformers, along with voltage or potential transformers are instrument
transformers. Instrument transformers scale the large values of voltage or current to small,
standardized values that are easy to handle for instruments and protective relays. The
instrument transformers isolate measurement or protection circuits from the high voltage of
the primary system. A current transformer provides a secondary current that is accurately
proportional to the current flowing in its primary. The current transformer presents a
negligible load to the primary circuit.
Fig 8.9 CT
37
the voltage to a safe limit value which can be easily measured by the ordinary low voltage
instrument like a voltmeter, wattmeter and watt-hour meters, etc.
It is the instrument used to measure the high voltage. It is connected in parallel. It is basically
a step down transformer which steps down the voltage and step up the current The potential
transformer uses a bus isolator to protect itself. The main use of this transformer is to
measure the voltage through the bus. This is done so as to get the detail information of the
voltage passing through the bus to the instrument.
Fig 8.10 PT
38
an electrical circuit from damage caused by excess current from an overload or short circuit.
Its basic function is to interrupt current flow after a fault is detected. Unlike a fuse, which
operates once and then must be replaced, a circuit breaker can be reset (either manually or
automatically) to resume normal operation.
39
Construction: It is basically an Inductive coil of value in mill henry. To discharge the surges,
one LA is provided the Wave Trap Mounting is done some times over the Coupling capacitor
and sometimes separately on support insulators depending on design.
40
CHAPTER-9
CONTROLLING
9.1 HYDRAULIC REGULATING GATES
9.1.1 FEATURES OF REGULATING GATES
No of gates 4
Type Slide hydraulic
Normal speed 1ft/min
Weight 13.3 Ton
Size 8.75×14ft
Hoist capacity 600 Ton
41
9.1.2 GENERAL REQUIREMENTS
Hydraulic gates are utilized in different kinds of facilities that serve different purposes. For
example, a navigation lock is a site that as the name says facilitates navigation, while the
main purpose of a flood barrier is to facilitate land defense against inundation. Yet, they both
utilize movable hydraulic closures, or for short hydraulic gates. The very fact that they do this
does not imply, however, that they do it in the same way. The gates in a navigation lock are
usually operated a few dozen times a day, while those in a flood barrier may be operated once
a year for testing and once in 5–10 years for the actual flood defense. This generates a
number of other differences in gate operation.
We will, therefore distinguish a number of different application groups for hydraulic gates—
and call these groups “operation profiles.” The following sections introduce such profiles,
describing the general operation purposes, main features, and the resulting specific
requirements for hydraulic gates. However, while discussing the differences one should also
not lose sight of the similarities. Therefore, it is good to approach this discussion in a
systematic manner, as used in the so-called Systems Engineering (SE) method [1,2].
In line with the SE method, there are two principal functions that all hydraulic gates must
perform; no matter what their operation profile is. These functions are:
The manners in which these functions are performed can vary depending on the gate
operation profile. This has generally been presented in Table 2.1. The miter gate shown in the
headline of this table is an example; the introduced approach applies to all types of hydraulic
gates.
42
Fig 9.2 Hydraulic emergency gates
43
used interchangeably, as both types of crane straddle their workload. The distinction most
often drawn between the two is that with gantry cranes, the entire structure (including gantry)
is usually wheeled (often on rails). By contrast, the supporting structure of an overhead crane
is fixed in location, often in the form of the walls or ceiling of a building, to which is attached
a movable hoist running overhead along a rail or beam (which may itself move). Further
confusing the issue is that gantry cranes may also incorporate a movable beam-mounted hoist
in addition to the entire structure being wheeled, and some overhead cranes are suspended
from a freestanding gantry
45
premade slots inside a weir, gate, or channel. Use of Stop log Gates Stop logs are modular in
nature, giving the operator of a gated structure the ability to control the water level in a
channel by adding or removing individual stop logs. A gate may make use of one or more
logs. Each log is lowered horizontally into a space or bay between two grooved piers referred
to as a stop log . In larger gate structures, there will be multiple bays in which stop logs can
be placed to better control the discharge through the structure. Stop logs are frequently used
to temporarily block flow through a spillway or canal during routine maintenance. At other
times stop logs can be used over longer periods of times, such as when a field is flooded and
stop logs are being used in smaller gates in order to control the depth of water in fields. The
logs may be left in and adjusted during the entire time that the field is submerged. In most
cases, the boards used are subjected to high flow conditions. As individual stop logs begin to
age they are replaced. Typically small amounts of water will leak between individual logs.
46
9.5.1 SPECIFICATION OF STOP LOGS
Number of sets 2
Number of unit in each sets 4
Unit size (meter) 3.70×3.2×0.395
47