Revision History
Page 1 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
CONTENTS
1. PURPOSE
Page 2 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
2. SCOPE
3. PRINCIPLE
4. RESPONSIBILITY
5. WORK PROCEDURE
6. INSTALLATION
7. INSPECTION AND TEST
8. ENVIRONMENT, HEALTH AND SAFETY (EHS)
9. JOB SAFETY ANALYSIS (J.S.A.)
10. RISK ASSESSMENT
1. PURPOSE
The purpose of this method Statement is to explain the procedure of the DCS, PLC, CONTROL PANEL
installation work for JAWAHARPUR SUPER THERMAL POWER STATION. With this, we can perform
construction safely and consistently.
Page 3 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
2. SCOPE
This method statement covers the general requirements of installation for DCS,PLC/CONTROL PANEL
installation of JAWAHARPUR SUPER THERMAL POWER STATION.
3. PRINCIPLE
All the concerning works’ procedure should follow this method statement.
4.RESPONSIBILITY
5.WORK PROCEDURE
5.1Required tools & equipment:
Page 4 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
1. Installation works shall be carried out only with respect to approved shop drawings of latest
revision
2. Site Engineer (Electrical) has to ensure that all the materials are received at site as per BOM
3. Ensure all civil works are completed for the area of installation and released / cleared by civil section to
proceed on with the installation of DCS, PLC/CONTROL PANE.L
4. Ensure that the necessary tools and tackles are made available for installation purpose.
5.3.1 Examine the drawing of DCS, PLC/ CONTROL PANEL erection layout with respect To the general layout.
5.3.2 Shift the Panel from stores to location by means of suitable Truck/lifting arrangement.
5.3.3 Carryout physical verification or any possible damage.
5.3.4 Check for necessary lifting tools &tackles in relation with load to be lifted and ensure safe lifting.
5.3.5 Check for the level alignment of the foundation before starting the erection.
Page 5 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
7.3.1 Ambulance car with driver, helper and stand by nurse are available at site or First Aid
Station at all times.
Page 6 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
A. Workers A.1 Not properly equipped with PPE A.1 Instructing to wear proper PPE
A.2 Worker abnormal physical condition A.2 Make the worker to take enough rest
(drunken &fatigue)
B. Transportation of B. Crash/ traffic accident B.1 Check the access road before passing the area
equipment & delivery of B.2 Designate a signalman who wear the red suit and safety helmet and
materials control the work
C.Heavy Lifting Works C. Crushing may cause fatal injury or permanent C.1 Preparation of a rigging lift list and plans for lifts of ten (10) tons
disability or greater.
C.2 Only a qualified and Certified operators. Signalman should be
n-place
C.3 Do not stand beneath the lifting areas
C.4 Ensure loads are fixed with sling belt correctly
C.5 All lifting equipment must be in good conditions
C.6 Experienced lifting supervisor at all times
C.7 Only monthly checking color attached lifting tools allowed to use
C.8 All lifting tools must have identification tag (including serial number,
certification number, SWL inspection date and due date)
C.9 Provide safe entrance and exit access road for the labors passing
D. Unloading Equipment D.1 Struck down by things and materials D.1.a Make sure the sling is tied / bound / tightened correctly
and Materials D.1.b Check the lifting devices(slings, shackles, etc…) for proper and
safe use
D.1.c Analyzing the load (weight, shape, lifting points, etc…) and the
lifting device
D.1.d Only monthly checking color attached lifting tools allowed to use
D.1.e All lifting tools must have identification tag (including serial
number, certification number, SWL inspection date and due date)
D.1.f Provide safe entrance and exit access road for the labors
passing
D.2 Squeezed by the sling D.2.a Use hand gloves when tighten the slings
D.2.b Tighten the slings before carrying-out lifting
D.3 Squeezed by the materials D.3.a Use wooden bar or support of the materials on the ground
D.4 Crane fall accidentally D.4.a Analyzing the loads (weight, shape, lifting points, etc…) and lifting
E. Working Operation device to suit the crane capacity
During Night Time. E.1 Working operation of the equipment may cause E.1.a Must provide sufficient lightening on the entire working area
injury to personnel due to E.1.b All equipment must ensure all lights are operational and not
poor visibility of the area. obscured by dirt or mud
E.1.c Supervisor must always be present for the entire working
operation
E.1.d All workers must be wearing proper PPE
E.1.e Ambulance and nurse must be available in first aid station
E.1.f Must use and connect 3 core codes electric wire and separate
distribution panel (must pass arrangement of ELCB) and avoid any water affect
E.1.g Provide safe entrance and exit access road for the labors passing
E.1.h All kinds of electric cable must be hanged over ground
E.1.i Must use industrial socket and plug
E.1.j Electric cabinet should not affect any water
E.2.a Daily check of the equipment prior to start of work
E.2.b Regular check & monitoring of the equipment prior to use
E.2 Generator (Diesel) equipment oil leakage E.2.c Provide secondary containment protection under the equipment top prevent
contamination of soil by oil spillage
G. Welding G.1 Electric shock, fire, burn to body and injury to G.1.a Proper earthing and connection of welding machines and
Page 7 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Page 8 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Page 9 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Page 10 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Grinder wheel damaged and that Setting cover to grinder and grinder
fragment hit worker may cause of injury. Injury 3 3 M(3) wheel can use only authorized and
Dangerous
approve by test.
tool(GRINDER)
Grounder and ungrounded plug mismatch Electric Only grounded plug must be use into
may cause of electric shock. shock 3 3 M(3) grounded in let
When using the side wheel of grinder. If wheel not allow to use side of wheel
Fragment impact to worker. Injury 2 2 T(4) which prohibit use side of wheel
Worker use grinder at unsafe a tune safe Injury 3 4 S(2) When use the grinder must be safety
cause injury. cover
Worker use unconnected circuit breaker Electric Grinder used to connect the circuit
& grinder use may cause of electric shock. shock 2 3 M(3) breaker and ground conducted main
panel IELB ATTACHED
Page 11 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Grinder wheel damaged and that Injury 3 3 M(3) Setting cover to grinder and grinder
fragment hit worker may cause of injury. wheel can use only authorized and
Dangerous approve by test.
tool(GRINDER) Grounder and ungrounded plug mismatch Electric 3 3 M(3) Only grounded plug must be use into
may cause of electric shock. shock grounded in let
When using the side wheel of grinder. Injury 2 2 T(4) If wheel not allow to use side of wheel
Fragment impact to worker. which prohibit use side of wheel
Worker use grinder at unsafe a tune safe Injury 3 4 S(2) When use the grinder must be safety
cause injury . cover
Worker use unconnected circuit breaker Electric 2 3 M(3) Grinder used to connect the circuit
& grinder use may cause of electric shock. shock breaker and ground conducted main
panel IELB attached.
Page 12 of 13
METHOD STATEMENT
FOR DCS,PLC/CONTROL PANEL INSTALLATION
DP16003-DD09-P0ZEN-750015
Page 13 of 13