STEEL PLANT
Steel making > Oxygen converter
Project Start Completion Location Client Capacity
POSCO Pohang Steelworks
A project to increase annual production capacity to 4.65 million tons by improving
compatibility, cost saving, and the quality of the converter furnace operation via the
introduction of facilities with the same capacity as those of No.2 steelmaking plant
for the purpose of enhancing the competitiveness of the small No.1 steelmaking
plant at Pohang Steelworks.
Pohang New steelmaking plant Dec. 2007 Apr. 2010 POSCO 4.6 milion T/Y
- De-P converter 1 set, De-C converter 1 set
- Heat Size: Max. 345 ton
- Boiler system for waste heat, Hot metal charging crane
- Bag filter precipitator
A project to construct a De-P converter in No.2 steelmaking plant for the purpose of
establishing a system for high quality steel (electro plated steel plates and API) and
cost saving to meet the productivity of annual capacity of 1.5 million tons FINEX
De-P Converter for No.2 Plant.
Feb. 2005 Mar. 2007 POSCO 4.5 milion T/Y
Steelmaking plant Pohang
Steelworks - Heat Size: Max. 300 ton
- Boiler system for waste heat, Hot metal charging crane
- Bag filter precipitator
A project to improve the capacity of aged No.1 steelmaking plant by revamping the
converter shell, trunnion ring, tiliting equipment and other converter facility.
○ Converter capacity : 110ton (Inner volume : 81㎥)
Revamping of No.1 Steelmaking ○ Main facility
May 1996 Dec. 1997 POSCO 2.5 milion T/Y
plant (2nd step) - Converter shell and converter tilting equipment
- Cooling facility for converter shell
- Converter trunnion ring
- Combined blowing technology adopting, localization of Converter bearing
block, Material conversion of Converter shell and trunnion ring (SGV 42-CR)
STEEL PLANT
Steel making > Oxygen converter
Project Start Completion Location Client Capacity
POSCO Gwangyang Steelworks
Capacity: 2,430,000 T-S/year (Converter : 280 T/ch)
Summary: A project to newly construct KR(2sets) & converter(1set) facilities for the
purpose of producing high grade steel plate(TMCP,API)
○ Main facility
1. KR Facility (De-S) : 250 T/ch x 2 set
Converter of SMP for Gwangyang 2.43 million
Feb. 2008 Apr. 2010 POSCO - KR Facility, Transfer car, Pouring pit, etc.
Plate Mill Project T-S/Y
2. Converter : 280 T/ch x 1 set
- Converter, Gas cooler, Waste gas treatment facility, O2 Lance Facility
3. Auxiliary facility
- Ladle, Relining facility, Water supply equipment,
Compressor, Power Receiving&Sending station,
Transformer,etc.
A project to newly construct KR(3sets) & converter(1set) facilities for the purpose of
establishing a system for the mass production of strategic products.
Gwangyang
De-P converter of No.2 steel Steelworks 4.5 million ○ Reduction of construction period : 19 months → 16.5 months
Jun. 2006 Dec. 2007 POSCO
making plant T-S/Y ○ Main facility
- Converter vessel, KR Facility, Gas cooler
- Electrostatic Precipitator, Water supply equipment, Utility facility
- Flux charing equipment, Main Lance, Transfer car
After converter tapping, this facility add coating materials, such as magnesia,
dolomite, to slag in converter and uniformly attach them to refractory bricks by
blowing high pressure N2 gas through lance.
This facility allows stable maintenance of converter and long life time of refractory
N2 Splash Slag Coating of No.2 bricks. As a result, it is expected to reduce expenses.
May 2000 Mar. 2001 POSCO 8.5 million T/Y
steel making plant
○ Main facility
- N₂Compressor / N₂Piping / N₂Holder - Control System
○ Applied technology: Automatic control of N2 pressure, flow rate &
operation technique of N2 coating