Demolition Cost Estimate

This document is a cost estimate and bill of quantities for the proposed demolition of space for Beauche International located on the ground floor of SM City Baguio in Baguio City. It provides a breakdown of materials, labor costs, and total amounts for 11 line items involved in the demolition, including the removal of tiles, drywalls, ceilings, electrical components, and accessories. The grand total cost for the demolition is estimated to be 44,712 Philippine pesos.

Uploaded by

Rodolf Bautista
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
60% found this document useful (15 votes)
38K views3 pages

Demolition Cost Estimate

This document is a cost estimate and bill of quantities for the proposed demolition of space for Beauche International located on the ground floor of SM City Baguio in Baguio City. It provides a breakdown of materials, labor costs, and total amounts for 11 line items involved in the demolition, including the removal of tiles, drywalls, ceilings, electrical components, and accessories. The grand total cost for the demolition is estimated to be 44,712 Philippine pesos.

Uploaded by

Rodolf Bautista
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

OFFICE ADDRESS: CONTACT NUMBERS:

3F No. 90 Project Luke Building Tel. (074)-620-5713


Leonard Wood Road cor. Engineer's Hill mobile: +63932-444-9955
Baguio City
email: rbautista.cbs@gmail.com

PROJECT: PROPOSED DEMOLITION OF SPACE


OWNER: BEAUCHE INTERNATIONAL
LOCATION: GROUND FLOOR, SM CITY BAGUIO, BAGUIO CITY
SUBJECT: COST ESTIMATE AND BILL OF QUANTITIES

Updated October 2, 2017

MATERIAL LABOR
CODE DESCRIPTION QTY UNIT UNIT COST TOTAL AMOUNT
COST COST

CODE-01 GENERAL REQUIREMENTS

1.0 Equipment (Mobilization/Demobilization) 4 days 1,000.00 4,000.00 4,000.00

2.0 Deliveries & Hauling 6 travels 300.00 1,800.00 1,800.00

3.0 Permits & Clearances


2.2 Working Permit Documentation 1 l.s. 500.00 500.00 500.00
2.3 Scaffolding Rental 4 pairs 600.00 2,400.00 2,400.00
2.4 Contractor's All Risk Insurance (CARI) 1 l.s. 2,000.00 2,000.00 2,000.00
Sub Total 10,700.00

CODE-02 SITE WORKS/CIVIL WORKS

4.0 Tile Chipping 32.2 sq.m. 150.00 150.00 4,830.00

5.0 Concrete Toppping Chipping 32.2 sqm 150.00 150.00 4,830.00

6.0 Removal of Drywalls & Studding 1 l.s. 3,000.00 3,000.00 3,000.00

7.0 Removal of Ceiling & Ceiling Hangers 1 space 5,250.00 5,250.00 5,250.00

8.0 Removal of Electrical Components 1 l.s. 2,240.00 2,240.00 2,240.00


9.0 Removal of Glass Frontage 1 l.s. 3,340.00 3,340.00 3,340.00

10.0 Removal of accessories (signage, etc) 1 l.s. 1,290.00 1,290.00 1,290.00

11.0 Handling & Disposal (two way) 1 l.s. 3,400.00 3,400.00 3,400.00
Sub Total 28,180.00

TOTAL 38,880.00
5% OCM 1,944.00
10% CONTRACTOR'S PROFIT 3,888.00
GRAND TOTAL 44,712.00

Prepared by:

___________________________________
Rodolf E. Bautista, CE, REB
Project Manager
-