OFFICE ADDRESS: CONTACT NUMBERS:
3F No. 90 Project Luke Building Tel. (074)-620-5713
Leonard Wood Road cor. Engineer's Hill mobile: +63932-444-9955
Baguio City
email: rbautista.cbs@gmail.com
PROJECT: PROPOSED DEMOLITION OF SPACE
OWNER: BEAUCHE INTERNATIONAL
LOCATION: GROUND FLOOR, SM CITY BAGUIO, BAGUIO CITY
SUBJECT: COST ESTIMATE AND BILL OF QUANTITIES
Updated October 2, 2017
MATERIAL LABOR
CODE DESCRIPTION QTY UNIT UNIT COST TOTAL AMOUNT
COST COST
CODE-01 GENERAL REQUIREMENTS
1.0 Equipment (Mobilization/Demobilization) 4 days 1,000.00 4,000.00 4,000.00
2.0 Deliveries & Hauling 6 travels 300.00 1,800.00 1,800.00
3.0 Permits & Clearances
2.2 Working Permit Documentation 1 l.s. 500.00 500.00 500.00
2.3 Scaffolding Rental 4 pairs 600.00 2,400.00 2,400.00
2.4 Contractor's All Risk Insurance (CARI) 1 l.s. 2,000.00 2,000.00 2,000.00
Sub Total 10,700.00
CODE-02 SITE WORKS/CIVIL WORKS
4.0 Tile Chipping 32.2 sq.m. 150.00 150.00 4,830.00
5.0 Concrete Toppping Chipping 32.2 sqm 150.00 150.00 4,830.00
6.0 Removal of Drywalls & Studding 1 l.s. 3,000.00 3,000.00 3,000.00
7.0 Removal of Ceiling & Ceiling Hangers 1 space 5,250.00 5,250.00 5,250.00
8.0 Removal of Electrical Components 1 l.s. 2,240.00 2,240.00 2,240.00
9.0 Removal of Glass Frontage 1 l.s. 3,340.00 3,340.00 3,340.00
10.0 Removal of accessories (signage, etc) 1 l.s. 1,290.00 1,290.00 1,290.00
11.0 Handling & Disposal (two way) 1 l.s. 3,400.00 3,400.00 3,400.00
Sub Total 28,180.00
TOTAL 38,880.00
5% OCM 1,944.00
10% CONTRACTOR'S PROFIT 3,888.00
GRAND TOTAL 44,712.00
Prepared by:
___________________________________
Rodolf E. Bautista, CE, REB
Project Manager
-