PMP Formulas
PMP New Horizon
        p: +91- 938-029-5210 or +1- 470-504-2231
              w: www.pmpnewhorizon.com
           e: pmpnewhorizon@gmail.com OR
              pmpnewhorizon@yahoo.com
Cost Variance Earned Value - Actual Cost (EV-AC)                         Schedule      Earned Value -Planned Value (EV-PV)
(CV)          If the variance is positive, Project is under              Variance      If the variance is positive, Project is ahead of
                  budget                                                 (SV)          schedule
                  If the variance is neutral, Project is within the                    If the variance is neutral, Project is on schedule
                  budget
                  If the variance is negative, Project is over                         If the variance is negative, Project is behind
                  budget                                                               schedule
Cost              Earned Value/ Actual cost                              Schedule   EV/PV
Performance       IF CPI is >1, Project is under budget                  Performanc IF SPI is >1, Project is ahead of schedule
Index (CPI)       IF CPI is =1, Project is within the budget             e Index    IF SPI is =1, Project is on schedule
                                                                         (SPI)
                  IF CPI is <1, Project is over budget                                 IF SPI is <1, Project is behind schedule
EAC
               EAC if BAC remains the same(Future Work at   AC+(BAC-EV)         the variance is caused by a one time event and
               planned Rate)                                                    not likely to happen again
               EAC if CPI remains the same                  BAC/CPI             If the CPI remains the same till end of project
                                                                                i.e. the original estimate is not accurate
               EAC if substandard performance continues     AC+(BAC-            use when the question gives all values (AC, EV,
                                                            EV)/(CPI*SPI)       BAC, SPI, CPI)
               Estimate at Completion (EAC)                 Actual cost+ New    If the estimate is based on wrong assumptions
                                                            ETC
VAC
Variance at    BAC - EAC                                        Estimate to     ETC= EAC- AC
completion                                                      completion
                                                                (ETC)
(VAC)
               IF VAC is >0, Project is over budget             Schedule at     SAC= BAC/CPI
                                                                completion
               IF VAC is =0, Project is on budget
               IF VAC is <0, Project is under budget            Return of       Net Income/Total Investment
                                                                Investment
                                                                (ROI)
                                                                Working         Current Assets - Current Liabilities
                                                                Capital
To-complete    (BAC-EV)/(BAC-AC)                                Internal rate Bigger is better
Performance                                                     of return (IRR)
Index (TCPI)   IF TCPI is >1.0, Harder to complete              Benefit Cost    Benefit/Cost
               IF TCPI is =1.0, Same to complete                Ratio (BCR)
                                                                Cost Benefit    Cost/Benefit
               IF TCPI <1.0, Easier to complete                 Ratio (CBR)
                                                                Opportunity     The value of the option not chosen
                                                                Cost
PERT
PERT 3-point      (Pessimistic+(4*Most Likely)+Optimistic)/6    O = Optimistic Estimate(Best-case Scenario)
PERT SD (Standard (Pessimistic - Optimistic) / 6                M= Most likely Estimate(Realistic)
Deviation
Variance          (SD)^2                                        P= Pessimistic Estimate(Worst-case Scenario)
PERT Activity     ((Pessimistic - Optimistic) / 6)^2
Variance
PERT Variance all sum((Pessimistic - Optimistic) / 6)^2
activities
No. of            n(n-1)/2                                      Control Limits = 3 sigma from mean
communication     N is number of members in the team and
channels          should include the project manager
Point of Total    (Ceiling Price- Target Price)/Buyer's share   Control Chart USL & LSL (Upper and Lower Specification limit) =
Assumption        ratio+Target cost                             Defined by customer; looser than the control limits
(PTA)
Target Price      Target cost+ Fee                              Order of Magnitude estimate = -25% to +75%(Early stage when
                                                                the scope and requirements are not defined)
                                                                Preliminary estimate = -15% to + 50% ( Made in early stage of
                                                                Project)
Sigma values                                                    Budget estimate = -10% to +25% (Made during Planning phase)
1 sigma = 68.26%                                                Definitive estimate = -5% to +10% (Most accurate and time
                                                                consuming)
2 sigma = 95.46%                                                Final estimate = 0% (Final estimate is always zero)
3 sigma = 99.73%                                                Float on the critical path = 0 days
6 sigma = 99.99%                                                Time a PM spends communicating = 90%
                                                                Crashing a project = Crash least expensive tasks on critical Path
                                                                JIT inventory = 0% (or very close to 0%.)