Waste Management Plan
Waste Management Plan
Rev 2 Popovici Maria Lucia Iulian Butnaru Paul Popescu Ion Sterian
Head Environmental BRUA BRUA Director General
Protection Service HSE Project manager Project Manager PMU / SNTGN Transgaz SA
SNTGN Transgaz SA
Disclaimer: The sole responsibility for this publication lies with the author. The European Union and the Innovation
& Networks Executive Agency (I.N.E.A.) are not responsible for any use that may be made of the information
contained herein.
Abbreviations Description
BRUA Bulgarian-Romanian-Hungarian-Austrian
CESMP Construction Environmental and Social Management Plan
EIA Environmental Impact Assessment
ESMP Environmental and Social Management Plan
F-CESMP Project Framework Construction Environmental and Social Management Plan
HSE Health, Safety and Environment
HSE-MS Health, Safety and Environment Management System
HSES Health, Safety, Environment System
HSSE Health, Safety, Social and Environment
JOCE Official Journal of European Community
KPI Key Performance Indicators
PMU Project Management Unit
PR Performance Requirement
Whilst the majority of the route is on land currently used for farming, it does pass through a number of
specifically sensitive areas, including seven Natura 2000 Sites, and the nationally important Dinosaurs
Geo-Park. It also passes close to a number of sites of archaeological value including the ancient city of
Tibiscum near Jupa. In some of these areas, as well as near major roads and railways and for the eight
major rivers, this will involve the use of horizontal directional drilling. In mountainous areas, special
“hammering techniques” may also be applied.
2.2 Environmental and Social Commitments
The Project is subject to various environmental and social requirements that are managed by the
Company through the implementation of its Health, Safety and Environmental Management System
The option
with the
Prevention highest
Preparation for reuse priority
Recycle
Other recovery
operations, e.g. energy The option
recovery
with the
Elimination lowest priority
In line with the waste management hierarchy, this Waste Management CESMP seeks to proactively
support a reduction in waste generation as well as increasing resource efficiency. A particular priority is
placed on waste streams with high volumes and waste containing hazardous substances (hazardous
waste). The Contractors should comply with the above-mentioned hierarchy, and should demonstrate
1
Integrated Management Manual Quality-Environment-Occupational Health and Safety, code MSMI-CMSSO Ed. 03/Rev.
Page 4 of 31 DOCUMENT No. 1062-TGN-MNG-PLN-PJM-22-00005 Rev 0
they are actively seeking to promote waste prevention and/or its reuse, and that particular attention will
be paid to the management of hazardous waste.
The Environmental Permit identifies the types of project waste that must be segregated, and the volumes
generated recorded:
Non-hazardous waste categories are: construction material (including concrete); welding waste;
metal waste; wood waste; waste from forestry exploration; packaging; paper; domestic.
hazardous waste categories are: contaminated textile waste (used Personal Protective
Equipment) and contaminated packaging.
The operational cooperation procedures in the construction site will be set in the Statement of Works that
will be an Appendix to the Commercial Contract to be signed between the Beneficiary and the Contractor.
The Contact Point Unit for each construction site, as defined in the Contractor Management Plan, is the
structure responsible for the implementation and monitoring of the provisions in the Statement of Works.
5.2 Company Roles & Responsibilities
Transgaz HSE management roles and responsibilities during the Project construction phase are
detailed in the BRUA PMU - Regulation of organization and functioning. Further information is also
provided in other documents listed in the F-CESMP document.
With regards to this CESMP, Transgaz S.A. is responsible for key management activities including:
• Development of bidding conditions regarding waste management;
• Professional training of a Transgaz Waste Management representative on site;
• Monitoring Contractor performance, supervision and control of Contractors;
Specific roles and responsibilities within the Company presented in Table 5.2 will apply.
Role Responsibilities
Director general - Approves the Waste Management Plan.
SNTGN TRANSGAZ SA
HSSE Coordinator - Ensures the compliance of the Project with the
requirements set out in this Plan;
- Has the general responsibility for the implementation of
this Waste Management Plan, including by the main
contractors;
- Develops, monitors and revises this plan according to
changes in the legislation or other requirements emerging
- Ensures the necessary training for BRUA PMU staff on
waste management is delivered;
- Centralizes the information regarding the generated waste
and waste management by the Contractors;
- Provides necessary support to the Contractors to enable
them to comply with the Waste Management Plan;
- Ensures this waste Management Plan is available to all
BRUA PMU staff and Contractor staff;
- Performs regular audits of the main Contractors’
performance against the requirements of this Plan;
- Reports all risks, non-compliances with this Plan and
incidents; and
- Prepares an annual environmental report that includes
waste management details.
Environmental responsible on Will verify the implementation of contractors’ obligations,
site of Transgaz from PMU including regular audits of:
BRUA - registration of the waste generated;
- the selection of waste manner;
- checking the waste deposit areas;
- visual inspections of soil and water in the work area;
- whether the required waste authorizations are held by the
contractors and their partners;
- Whether Contractors have appropriate Intervention Plans
in case of accidents.
2
Ecologic accident – an event resulting from an unforeseen and accidental spillage or emission of a hazardous or polluting
substance (whether liquid, solid, gasseous or vapour) that could result in detrimental impacts to the environment and/or local
communities (G.E.O. 195/2005 on environment protection, as further amended and supplemented)
Page 10 of 30 DOCUMENT No. 1062-BRUA-WsMP-0006 Rev 0
5.3 Contractor Roles & Responsibilities
Overarching Contractor HSSE requirements are defined in the relevant articles of their contracts and
associated mandatory Annexes. Each contractor must also implement all relevant requirements of the
CESMPs, including this Waste Management CESMP. Contractors are also responsible for ensuring that
any subcontracted work meets these requirements. In addition, within the Project, responsibility for waste
management activities lies with the Contractors according to the principle "polluter pays".
Contractors will therefore be required to present to the Beneficiary, represented in the Project by BRUA
PMU in accordance with the requirements, their proposed approaches to:
• Identification and quantification of the different types of waste produced on site;
• Collection of recyclable wastes and hazardous wastes, their collection and storage arrangements
inside the site;
• Waste transport (own resources or through outsourcing);
• Reusable waste recovery;
• Treatment and disposal of hazardous waste by presenting pre-contracts / contracts with licensed
companies; and
• Any other conditions outlined in this CESMP or its Appendices.
Further specific responsibilities of the Contractor/sub-contractors are outlined in the Appendix 1 and
Appendix 2 to this CESMP and in Table 5.3:
Table 5.3 Contractor Roles and Responsibilities
Role Responsibilities
- Manager responsible for - Ensures all activities are performed according to the
environmental matters requirements of the Waste Management Plan;
- Produces a Waste Management plans in line with this Plan
- Performs regular inspections at the working sites to ensure
all activities are being performed according to the
requirements of the Waste Management Plan;
- Assigned by way of Decision the person/persons
responsible for waste management;
- Keeps all necessary records and reports on waste
according to the requirements of relevant legislation;
- Ensures all staff receive the necessary training in relation
to waste management, including hazardous waste;
- Ensures contracts are in place with legally certified
companies for the collection, recovery and disposal of all
categories of waste;
Page 11 of 30 DOCUMENT No. 1062-BRUA-WsMP-0006 Rev 0
Role Responsibilities
- Identifies registered and appropriately managed disposal
facilities for waste and hazardous waste; and undertakes
a review of facilities as part of Project supplier
management processes;
- Ensures the transportation of waste is undertaken by
certified companies, according to the legal provisions.
- Ensures all subcontractor activities are conducted in line
with this Waste Management Plan;
- Produces monthly and an annual environmental reports
that include details on waste management that must be
sent to Transgaz;
- Reports on all risks, non-compliances with this Plan an
incidents;
- Ensures all necessary measures are taken to remedy any
non-compliances.
Objective Approach
1: Risk Based Monitoring programmes to address material issues base on the use of the
‘source-pathway-receptor’ approach in the Environmental Social Impact
Assessment. These are commensurate with:
the scale and nature of the activity,
the assessed potential level of impact (and uncertainty thereof), and
the sensitivity of the local environment within the activity area of influence
2: Compliance Addition monitoring programmes to meet specific regulatory needs.
Based
Following this approach the proposed monitoring plans should meet both Transgaz’s requirement to
understand and manage the Project’s potential impacts during each construction activity/location and any
specific requirements of the Romanian authorities. The specific monitoring requirements for this Waste
CESMP are presented in Appendix 2.
6.3 Management System Verification Monitoring
Management System verification monitoring requirements, as detailed in the F-CESMP Document, are
divided into three levels as shown in Table 6.3.
Table 6.3 Auditing Management System
In addition to the above, there are also expected to be regulatory audits and lender compliance
monitoring visits. The nature and structure of these will be confirmed with regulators and lenders.
GCR Ref
Requirement Verification
Ref. Topic Location Responsibility
Process
WsM Waste All requirements in the Environmental Agreement in relation to waste All
All Contractor Audit
001 Management management must be met
WsM Waste Any relevant requirements in the Pollution Prevention CESMP associated
All Contractor Audit
002 Management with waste management should be put in place
Contractors will produce their own Waste Management plans. These will 298
adopt the following ‘good practices’ to reduce the risk of impacts arising
from waste management activities:
• develop an inventory of likely wastes;
• identification of local licensed waste management facilities;
• waste generation will be minimized as far as possible;
• waste reuse/recycling opportunities will be maximised;
• waste segregation (liquid and solid/reusable and recyclable) will be
undertaken using appropriate storage and labelling; Review and
Waste
WsM • waste collection, storage and transfer in line with Good Industry approval of
Management All Contractor
003 Practice Contractor Waste
Plans
• specific disposal procedures will be produced for all waste streams Management Plan
identified including waste transfer notes if moved to a licensed offsite
facility;
• auditing and reporting procedures will be produced for Contractor waste
management and disposal.; and
•measures to be taken after construction works are completed, so as to
assure the disposal and turning into value of all waste from the
construction sites, including the waste resulted from the removal of
temporary structures.
83
*The transport of the waste for its permanent valorization / elimination Audit of relevant
WsM
Transport All should be made based on a documentation prepared for the transfer of Contractor paperwork for
004
waste, according to the Government Decision no. 1061/2008 waste transfer
Visual 300
Hazardous waste or hazardous materials will be managed separately at
inspections. Audit
all locations and will be collected by authorized third party operators.
WsM Waste of relevant
All There will be no incineration of hazardous waste on site. Containers of Contractor
005 Management paperwork for
hazardous waste will only be moved or transferred to the site by qualified
waste collection
personnel using appropriate equipment and vehicles.
and transfer.
301
Personnel involved in waste management will be given regular training,
WsM Audit of training
Training All specific to the range of wastes being generated and managed, and where Contractor
006 records.
relevant including requirements for hazardous waste management.
For each type of waste, the waste management solution will be 293
WsM Waste assessed, and contracts with licensed waste management contractors for Review of
All Contractor
007 Management each type of waste will be obtained. contracts
Operators will keep track of the waste.
All areas, 114
*Waste from the work fronts will be stored in bins within trash bags and
but
will be transferred daily to the construction site, where there will be
WsM Waste especially
dedicated collection points with different containers provided for each Contractor Visual inspections
008 Storage areas with
type of waste. For household and all food waste, a metal container with a
large
tightly fitted lid will be provided.
mammals
81
*Contractors will record and report on the different types and quantities of
waste generated and how they are disposed of on a monthly basis by Audit of monthly
WsM completing the waste management data sheets as per the requirements reports and waste
Reporting All Contractor
009 of HG 856/2002 (Government Decisions) on waste management record management data
keeping and according to the template set out in Appendix 5 of this sheets.
CESMP.
Site *To reduce the volume of waste that needs to be stored and transported 77
WsM Waste
organizatio metal can and plastic container (PET) presses and paper shredders will Contractor Visual inspections
010 Reduction
n be provided on site.
WsM Waste No waste material should be spilled/disposed of/abandoned in forested 220
All Contractor Visual inspections
011 Disposal areas.
WsM Waste
All Waste will not be stored in the proximity of watercourses or protected areas Contractor Visual inspections
012 Storage
WsM Waste *Clearly defined areas for the safe storage of all types of waste will be 80
All Contractor Visual inspections
013 Storage established at the construction sites and work fronts.
Waste *The selective collection of waste, temporary storage and final disposal 89
WsM Periodic
Storage and All of waste under safety conditions and full recycling of recyclable waste will Contractor
014 inspections
Disposal be undertaken
Waste 34
WsM *Waste will be temporarily stored in dedicated storage areas, by waste
Storage and All Contractor Visual inspections
015 stream, before collection and transport to authorised disposal facilities.
Disposal
Audit of waste
WsM Inert waste from excavations will be recycled for covering the pipe or will
Re-cycling All Contractor management data
017 be used for temporary road works, platforms, etc.
sheets
Visual
inspections. Audit
WsM Waste Any metallic wastes will be stored in specially designated areas and of relevant
All Contractor
018 Storage periodically recovered in specialized units based upon a contract; paperwork for
waste collection
and transfer
WsM Waste Waste management will be performed in strict compliance with Law No
All Contractor Visual inspections
019 Management 211/2011 on waste regime.
WsM Waste 79
All *The storage of any waste within any water course is prohibited. Contractor Visual inspections
020 Storage
Visual
inspections. Audit
The transport / handling of waste generated and dangerous materials will
WsM Waste of relevant
All be undertaken in such a manner as not to cause pollution of soil, surface Contractor
021 Transport paperwork for
waters or groundwater
waste collection
and transfer
Audit of relevant
Waste paperwork for
WsM Contracts for the collection and disposal of household waste will be set
Transport All Contractor waste collection,
022 up with a local municipal waste collection and disposal company.
and Disposal transfer and
disposal.
According
WsM Waste The contractor will be required to dislodge and break rocks to a size that
to tender Contractor Visual inspections
023 Transport allows them to be transported effectively and safely.
documents
Waste All Waste tyres will be collected separately from other waste streams and Audit of relevant 219
Disposal will be turned into value via licensed transporters in accordance with paperwork for
WsM
relevant regulations. Contractor waste collection,
024
transfer and
disposal
WsM Waste *Packaging waste will be managed in accordance with the provisions of 82
All Contractor Visual inspections
025 Management Law no. 249/2015
Law no. 249/2015 on packaging and packaging waste Transposes the provisions of Directive 94/62/CE of the
management; European Parliament and Council of December 20, 1994 on
packaging and packaging waste, published in the Official
Journal of European Community series L, no. 365 of
December 31, 1994, amended by Directive 2004/12/CE of
the European Parliament and Council of February 11, 2004,
published in the Official Journal of UE , series L, no. 47 of
February 18, 2004, by Directive 2013/2/UE of the European
Commission, of February 7, 2013 on the amendment of
Annex I to Directive 94/62/CE of the European Parliament
and Council of on packaging and packaging waste,
published in the Official Journal of UE series L, no. 37 of
February 8, 2013, Decision 97/129/CE of the European
Commission of January 28, 1997 establishing the
identification system for packaging materials pursuant to
European Parliament and Council Directive 94/62/CE on
packaging and packaging waste, published in the Official
Journal of European Community series L, no. 50 of
February 20, 1997, Commission Decision 2005/270/CE of
March 22, 2005 establishing the formats relating to the
database system pursuant to Directive 94/62/EC on
packaging and packaging waste [notified under number C
(2005) 854, published in the Official Journal of UE series L,
no. 86 of April 5, 2005.
DECISION (Template)
The institution management, based on the company's statute and contract of the company
DECIDE:
Article 1. Mr. / Ms. ........................... in charge of waste management in ......... ... ... as required by Law
211/2011 republished in 2014, with the subsequent changes and additions
Article 2. In this capability, Mr. / Ms. ....................... ensures fulfillment of the obligations stipulated by:
- Law 211 of 2011 on waste regime republished in 2014, with the subsequent modifications and
completions
- Order no. 794/2012 on the procedure for reporting data on packaging and packaging waste
- Decision 856 of 2002 on waste management records and approving the list of wastes, including
hazardous wastes and other applicable environmental requirements.
and for the other regulations applicable to the company's Environmental Management.
Article 3. All employees have a duty to grant any assistance requested, while ensuring favorable
conditions for waste management.
Manager,
Waste
0 1 2 3 4 7
Electrical and
4. Headquarters 20 01 35 -
electronic equipment
16 06 01*
8. Headquarters Auto batteries -
16 06 06*
Note:
- Hazardous wastes are marked with an asterisk (*)
- The waste in the table is indicative and list will be supplemented with specific categories of
generated waste.
Drawn-up by,
Checked by,
Approved by
Date:..................
NOTES:
*1) Type of storage: *3) Scope of treatment:
RM – metallic recipient V – to be turned into value
RP – plastic recipient E – to be disposed of
BZ – receiving tank *4) Means of transportation:
CT – transportable container AS – transportation truck
CF – immovable container AN - vehicle
S - bags H – hydraulic transport
PD - dehydration platform CF - railway
VN – in bulk, not covered A - others
VA - in bulk, enclosure not covered *5) Destination:
RL – wooden recipient DO – town/village waste storage
A - others HP – own waste dump
*2) Means of treatment: HC – common industrial waste dump
TM – mechanical treatment I – incineration for disposal
TC – chemical treatment Vr – turning into value by authorised agents
TMC – chemical-mechanical treatment P – material or energy use in own undertaking
TB – biochemical treatment Ve – turning into energy value by authorised
D – dehydration economic agents
TT – thermal treatment A - others
A - others