GENERAL QUALITY ASSURANCE PLAN FOR SUBSTATION
VENDORS / CONTRACTOR       AIL           CLIENT           TPI
ACTIVITY POINT / INSPECTION POINT                                                            P     A/RD    W      P   RD    W   P   A/RD     W   P   A/RD     W
DESIGN & ENGINEERING
- Site Study, Collection of Detailed Site Data / Soil Investigation                          √                    √         √         √      √
- Project / Equipment Design                                                                 √                    √   √               √
- Structural Design                                                                                               √                   √
- Foundation Design                                                                          √                    √   √               √
- Design of other Auxiliary Civil Works                                                      √                    √   √               √
VENDOR/ MANUFACTURER APPROVAL                                                                                     √                   √
PLACEMENT OF ORDERS                                                                                               √
INSPECTION OF RAW MATERIAL USED FOR EQUIPMENTS                                               √      √      √          √               √
INSPECTION OF MAJOR EQUIPMENTS / MATERIAL
- Power Transformer                                                                          √                        √     √         √      √        √       √
GIS                                                                                          √                        √     √         √      √        √       √
- Circuit Breaker                                                                            √                        √     √         √      √        √       √
- Instrument Transformer                                                                     √                        √     √         √      √        √       √
                                                                                                                                                      Page 1 of 5
                                              GENERAL QUALITY ASSURANCE PLAN FOR SUBSTATION
                                                                   VENDORS / CONTRACTOR       AIL           CLIENT           TPI
ACTIVITY POINT / INSPECTION POINT                                    P     A/RD    W      P   RD    W   P   A/RD     W   P   A/RD     W
- Disconnectors / Earth Switch                                       √                        √     √         √      √        √       √
- 33 kV Indoor Switchgear                                            √                        √     √         √      √        √       √
- Surge Arresters                                                    √                        √     √         √      √        √       √
- Control & Protection Panel                                         √                        √     √         √      √        √       √
- Substation SCADA                                                   √                        √     √         √      √        √       √
- Battery & Battery Charger                                          √                        √     √         √               √       √
- DCDB                                                               √                        √     √         √               √       √
- Earthing/Auxiliary Transformer                                     √                        √     √         √               √       √
- Substation Structures                                              √                        √     √         √               √       √
- Earthing Material                                                  √                        √     √         √               √       √
- LT Power, Control & Instrumentation Cable                          √                        √     √         √               √       √
- HT Power Cable                                                     √                        √     √         √               √       √
- Other Accessories                                                  √                        √     √         √               √       √
SEAWORTHY PACKING CHECK                                              √                              √                                 √
                                                                                                                              Page 2 of 5
                                                                   GENERAL QUALITY ASSURANCE PLAN FOR SUBSTATION
                                                                                                         VENDORS / CONTRACTOR       AIL           CLIENT           TPI
ACTIVITY POINT / INSPECTION POINT                                                                          P     A/RD    W      P   RD    W   P   A/RD     W   P   A/RD     W
MATERIAL TRANSIT INSURANCE                                                                                                      √                   √
SITE SAFETY MEASURES                                                                                                            √                          √
CIVIL WORKS
- Check that cement, sand and aggregate to be used is of mutually agreed quality                                                √                   √      √
 - Check and ensure that test of design mix for concrete has been got done from a reputed
                                                                                                                                √                   √      √
laboratory
- Check that ratio of ingredients during mixing in the motorized mixer is maintained at site and water
                                                                                                           √                    √         √                √
used is potable
 - Check that form box and stub setting template are correct to be used & are relating to the
Structure for which foundation is to be casted. The adjustment of template may be got made as per          √                    √         √                √
normal tower or normal tower with extension.
- Check the levels of stubs, back to back distance & distance between diagonals                            √                    √         √                √
- Check that form boxes are thoroughly cleaned and sprayed with fine sand or treated with black /
                                                                                                           √                    √         √                √
waste before use , every time
- Check that reinforcement steel is properly placed as per drawing. The steel bars to be tied with
                                                                                                           √                    √         √                √
binding wire at every crossing point
 - Check that the pouring of concrete is done without jerks or sudden fall and concrete aggregate
                                                                                                           √                    √         √                √
vibrated to avoid air bubbles
- Check that pouring of concrete is stopped , if the temperature goes considerably down say Zero
                                                                                                           √                    √         √                √
Degree C
                                                                                                                                                                    Page 3 of 5
                                                                     GENERAL QUALITY ASSURANCE PLAN FOR SUBSTATION
                                                                                                          VENDORS / CONTRACTOR       AIL           CLIENT           TPI
ACTIVITY POINT / INSPECTION POINT                                                                           P     A/RD    W      P   RD    W   P   A/RD     W   P   A/RD     W
 - Check that poured concrete aggregate is periodically vibrated to take out the air bubbles or air
                                                                                                            √                    √         √                √
voids
 - Check that form boxes are stripped /removed only after sufficient time( 24 hours with average
                                                                                                            √                    √         √                √
temperature of 20 0C or 48 hours in case of rainy season/ low temperature) after pouring of concrete
 - Check that any part of the civil structure is not damaged during stripping. If damage is minor ,it
                                                                                                            √                    √         √                √
should be got rectified / attended. The tolerances of concrete dimensions may also be checked
- Check that foundation pit is back- filled up with soil excavated only in layers ( not more the 300mm)
                                                                                                            √                    √         √                √
&water added in sufficient quantity for proper compacting
 - Check that the level of stubs , back to back distance and distance between diagonals are within
                                                                                                            √                    √         √                √
the permissible tolerances.
ERECTION WORKS
- Installation of Substation Structures                                                                     √                    √         √                √
- Installation of Power Transformer                                                                         √                    √         √                √
- Installation of GIS                                                                                       √                    √         √                √
- Installation of Substation outdoor Switchgear                                                             √                    √         √                √
- Laying of Cables                                                                                          √                    √         √                √
- Installation of Indoor Switchgear Panels                                                                  √                    √         √                √
                                                                                                                                                                     Page 4 of 5
                                                                 GENERAL QUALITY ASSURANCE PLAN FOR SUBSTATION
                                                                                                    VENDORS / CONTRACTOR       AIL           CLIENT           TPI
ACTIVITY POINT / INSPECTION POINT                                                                        P     A/RD   W    P   RD    W   P   A/RD     W   P   A/RD     W
- Installation of Control & Protection Panels                                                            √                 √         √                √
- Installation of Battery & Battery Charger                                                              √                 √         √                √
- Laying of Substation Earthing                                                                          √                 √         √                √
- Other Accessories                                                                                      √                 √         √                √
PRE TESTING & COMMISSIONING WORK                                                                                           √                          √
HANDING / PART HANDING OVER                                                                                                √                   √
NOTE:-
P        PERFORM
A/RD APPROVE / REVIEW DOCUMENTS
W        WITNESS
TPI   THIRD PARTY INSPECTION
1. All the equipments/workmanship shall be conforming to internationally recognized norms & standards.
2. This QAP is general purpose however the detailed equipment QAP shall be submitted during execution stage.
                                                                                                                                                               Page 5 of 5