SECTION 7
ELECTRICAL
SECTION 7 ELECTRICAL
Index Page
Appendix 1 : Isolation and Livening Permits for Use During Initial Livening of Electrical
             facilities
Section 7
ELECTRICAL
7.1. General
              Deviations from this specification shall be specified separately and the reasons
              for the deviations shall be explained. Their influence on the price shall be stated.
              The installation and equipment shall comply with the laws and stipulations
              currently in force in Indonesia.
              The equipment shall comply with relevant IEC recommendations and local
              standards; any exceptions shall be mentioned in the tender.
7.3.1 General:
7.3.2 Installation:
              The Contractor is invited to propose to the Purchaser any deviations from the
              drawings and documents which he thinks might be an improvement or of
              Before starting the work, the Contractor shall examine the site conditions
              with other contractors so that cables, cable trays etc. can be installed properly
              and appropriately, taking into consideration installation of other equipment.
              If complete installation 'differs from the contract, the Contractor shall make the
              necessary rectification without delay, at no charge to the Purchaser.
              The Contractor shall use skilled staff for the installation work. It is expected
              that foremen will have detailed information about the installation work included
              in this inquiry specification.
              The Contractor shall participate in meetings at the mill site which concern
              electrical installation. The minutes of installation meetings shall form part of
              the contract so that the changes agreed in these meetings shall be accepted by
              the Purchaser and Contractor as being included in the contract.
7.3.2 Materials:
              The Contractor shall measure installed cable lengths and mark them on the
              cable list supplied by the Purchaser.
              This record shall indicate for each item the amount of material already
              installed and the amount required completing the installation. This record shall
              be updated weekly.
              The material lists, the cable lists and the lists of additional and extra work
              shall be handled in installation meetings. Any unclear matters shall be clarified
              as soon as possible.
7.3.3 Completion:
              When the installation work is complete the Purchaser and the Contractor will
              compile a list for each installation package of the work done. These lists shall be
              based on the material lists enclosed with this specification, with quantities
              adjusted appropriately.
              The basis for the above-mentioned lists shall be the following documents (all
              documents must be approved between the Purchaser and the Contractor):
              - cable lists
              - material lists
               The basis for cable tray installation shall be the direct cable ladder lengths
               including necessary angles, T-pieces and cross-pieces. Only direct tray length
               shall be counted as installed. This includes all necessary supports etc.
               The basis for cable installation shall be the cable length from terminal to
               terminal including installation and fastening materials.
               After the installation work is finished a percentage of the cables and cable
               ladder racks will be measured. The result will be compared to the Contractor's
               corresponding length data and the total lengths will be adjusted accordingly.
               The basis for the various material quantities in the electrical installation shall
               be the quantities of equipment installed including all necessary additional material
               (fixing materials, accessories, name plates, etc.) needed for such installation as
               specified in this inquiry specification.
               Any work carried out by the Contractor which is not covered by the unit prices
               shall be agreed in writing between the Purchaser and Contractor before the work
               is commenced and shall be the subject of a separate order.
                   The switch gear will be air insulated, metal clad with withdrawal vacuum
                   circuit breakers or contactors, Siemens type 8 BK 20.
                   The power transformers will be 3-phase oil immersed outdoor type of the
                   following ratings:
                   12.5 MV A                          20/6.9 kV
                   6.3 MV A                           30/6.9 kV
                   3150 kV A                          20/0.693 kV
                   2000 kV A                          20/0.4 kV
                   1000 kV A                          20/0.4 kV
                   630 kV A                           20/0.4 kV
                   630 kV A                           660/400 kV
                 The Contractor’s scope of work shall include the mounting of the loose
                 transformers components and filling of the transformer with oil under
                 controlled full vacuum conditions as specified by the transformer
                 manufacturer (Siemens). The Contractor shall provide a suitable and
                 approved vacuum filling and oil treatment plant.
                 The bus duct consists of three insulated phase bars made of electrolytic
                 copper. The insulation consists of polyamide filled polyester resin.
                 Ratings are as follows:
6.6kV 1250A
        7.4.4.1 Resistors are provided to earth the neutral of the transformers of the 6.6kV
                systems.
                 They will be of iron frame, sheet steel covered, floor standing, IP23.
                 Ratings arc as follows:
        7.4.4.2 The 660 V system neutrals are earthed by resistors housed, together with
                associated control components, in individual IP 23 panels for mounting on
                top of the MCC incomers. Ratings are kV 2 A continuous.
           Low voltage MCC's will be Siemens metal clad with withdrawal circuit breakers,
           fuse combination starters and fuse feeders. They will be of modular construction,
           floor standing.
           The 660V MCC's are connected to the transformers by means of bus duct
           consisting of insulated phase conductors enclosed in a cast epoxy resin outer
          The bus duct will be provided in Sections which shall be connected together and
          installed by the Contractor.
          These are ABB SAMI GS and SAMI STAR frequency converters, enclosed
          type, for wall or floor mounting as indicated.
          Cubicles, panels and racks will be supplied for various applications, mounted in
          the electrical rooms or in the field. They will be of modular sheet steel
          construction, floor standing, either individual or forming a suite.
          These will be of sheet steel construction and shall be installed by the Contractor
          in the field as indicated in the drawings.
          Cable trays will be aluminum prefabricated ladder or Hat tray type consisting of
          straights, bends, tees and other pieces as indicated in the cable tray drawings.
          The Purchaser will supply the material for the supporting brackets, consisting of
          mild steel channel or angle in standard lengths. The Contractor shall fabricate
          the required supporting brackets from this material and shall paint same after
          fabrication.
          Where cable trays enter cable rooms they shall be installed with a slight
          downward slope (approximately 5%) to the outside.
7.4.11 Cables:
            The Purchaser will supply all cable glands, lugs, terminating materials, clamps,
            and marker ties and fixing materials. The Contractor shall supply only
            consumable items.
a)     The cable trays shall be supported at intervals not exceeding the maximum distance
       specified by the manufacturer.
b)     The location of cable tray droppers and field mounted items will not be shown on
       the installation drawings. The Contractor shall observe that when locating these, he
       shall not restrict future maintenance and operation of the equipment nor block transport
       or walkways. He shall also try to utilize the same droppers for the requirements of the
       instrument installation.
c)     The Contractor shall cooperate with other trades regarding the location of cable tray
       supports and droppers in order to avoid any interference.
d)     The Purchaser reserves the right to request the Contractor to relocate any drop-out
       which, in his opinion, does not comply with the general practice of the trade without
       extra cost to the Purchaser. No horizontal sections of the drop-outs shall be located
       lower than 2.1 meters above walking floor level.
e)     Where cable trays pass under or over steam lines, heat proof barriers shall be
       installed between the tray and the steam lines. A minimum of 150 mm clear space
       between cable and the surface of pipes or pipe insulation shall be allowed.
f)     Cables shall run on the trays to which they are assigned in the power layouts and cable
       lists.
g)     The estimated length of each cable will be shown on the cable schedules provided by
       the Purchaser. The Contractor shall immediately inform the Purchaser if there is a
       difference between the estimated and installed length.
j)     Where there is only one tray for both power and control cables, they shall be clearly
       separated.
ii)     larger cables shall be spaced and shall be tied at intervals that will ensure maintenance of
        the spacing called for in the standards;
iii)    on horizontal runs, spaced cables only shall be tied. On vertical runs however, all cables
        shall be tied. Maximum distance between ties shall be 60 cm;
1)      All cables and wires shall be installed in continuous lengths from one end of the circuit to
        the other if not otherwise specified.
m)      Power cables shall be installed in one layer only without spacing. Control cables shall be
        installed in layers.
n)      All cables shall be numbered at both ends in accordance with Crapp-m10, "Numbering
        Procedure for Electrical Parts and Equipment".
o)      The Contractor shall drill all gland plates as necessary to accept the correct size cable
        gland.
q)      Where non-armored cables leave ladders outside electrical rooms, they shall be run in
        galvanized welded steel conduit or otherwise mechanically protected.
r)      All cables passing less than 1.5 meters above ground shall be protected from mechanical
        damage.
s)      It must be possible to energize part of MCC and control rack and take starters and modules
        into operation while the cabling work for the remaining starters and modules goes on.
t)      Induction motors will be supplied by the Purchaser. The motors will have a connection
        box and terminals for cable connecting.
7.5.2 Earthing
Earthing wire for the main cable routes shall be 120 mm2 PVC insulated copper.
           All earth conductors above ground shall be so located as to be readily visible for
           inspection.
          All earth conductors and armoring in cables shall be terminated at both ends
          unless otherwise specified by using approved connectors.
          All earth connections shall be made only after the surface is thoroughly
          cleaned of pain and dirt. Earth wires shall not run parallel to single core cables.
The joints of the main earthing loop shall be of the thermal type.
7.6. Testing
7.6.1 General:
          The Contractor shall carry out testing and all other services necessary to put
          the electrical system in condition ready for service.
          The Contractor shall provide all two-way radios, instruments, equipment and
          personnel necessary for testing the electrical installation and shall make sure
          that such personnel are available during final testing of the process system as
          considered necessary by the Purchaser to make immediate adjustments.
The costs of all testing activities shall be included in the total price.
          All cabling and wiring shall be tested for continuity, short circuits and earth
          faults.
          6.6kV cables shall be submitted to pressure testing after installation in the presence
          of the Purchaser.
          Before energizing, the Contractor shall carry out the following cable tests:
          -    tightening up the joints
          -    checking of the power cable connections
          -    checking of the control cable connections
          Connections shall be checked by using a tester. "OK" sign shall be marked in pen
          on the corresponding wiring diagrams. These marked copies shall be given to the
          Purchaser's supervisors.
Megger tests shall be made on all motors prior to connection of power leads.
            Immediately prior to energizing a motor for the first time, the Contractor shall
            request the Purchaser to check out the motor for proper and adequate lubrication.
            The Contractor shall submit the test result on a test report form supplied by the
            Purchaser.
            The electrical installation work will take place simultaneously with civil
            construction and pipe and machine installation. Therefore the Contractor should not
            expect free and uninterrupted access at all times in all areas. The Contractor
            shall take into consideration these other installation activities.
            The Contractor shall ensure that lack of material or labor will not prevent the
            installation from being done according to the time schedule.
The Purchaser will supply the following drawings and documents for electrical
installation:
          All other drawings and documents needed by the Contractor shall be provided by
          him and approved by the Purchaser and a copy shall be given to the Purchaser.
          All drawings used for electrical installation shall be approved by the Purchaser and
          stamped accordingly.
          Drawings accompany this specification to describe the work and to supplement the
          information contained in this specification. It shall be known and understood that
          addition detail drawings may be prepared and issued during the course of the work to
          modify or clarify this specification. Such drawings shall thereupon become part of
          this specification.
          Below is the time schedule concerning the delivery of the final installation
          documents (documents for various installation areas; the time is weeks before the
          corresponding part of the work starts):
          The power cable lists and the control cable lists may be delivered at different times.
          Non-receipt of the power cable lists shall not prevent lying of control cables and vice-
versa.
7.8.4 As-Built:
          When the installation work is finished the Contractor shall deliver two sets of
          working drawings on which all "as-built" modifications are marked with red pen.
          The installation will be accepted only after the above drawings have been handed
          over.
7.9.1     The Contractor shall quote a lump sum price for the complete installation in
          accordance with this specification and accompanying Schedule of Equipment.
          This lump sum price shall be valid for changes to the final quantity of
          plus/minus 15%.
7.9.2     To cater for changes to the final scope in excess of the plus/minus 15%, the
          Contractor shall quote take-out/take-in unit prices for each and every type of item
          listed in Appendix I.
7.9.3 The Contractor shall also quote hourly labor rates for:
7.10.1    All electrical material, equipment, cables and all work during the installation and
          acceptance periods shall at all times have adequate weather, moisture and
          mechanical protection.
7.10.2    All Electrical Rooms and work areas must be kept in a clean, neat and tidy
          condition at all times.
7.10.3    Care of the motors in storage shall conform to the Mechanical Equipment
          Installation Specifications Section 10, #2.
7.11.1    The general location of local and remote control stations and other wiring
          devices shall be mounted in such a manner as to afford the maximum
          protection from mechanical damage, moisture, chemicals and dirt.
7.12.1    Fastenings for attaching electrical cables, conduit, ducts and other electrical
          equipment, if not cast-in-place with the concrete, shall be an expansion type as per
          the Design standards.
7.12.2    All openings into Electrical Rooms, control consoles and other electrical
          equipment shall be sealed to prevent moisture and foreign matter from entering.
7.12.3    All openings into exterior walls or roofs of buildings shall be flashed and
          sealed in a manner consistent with their construction and, in the case of roofs,
          shall be flashed and sealed to the approval of the contractor who installed it
          and is guaranteeing the installation of the roofs.
 7.13.1   Each cable shall be identified at each connection with the proper code number as
          shown on the drawings or design standards; likewise each conductor shall also
          be identified at each connection.
7.14.2    The "Electrical Tag" on a MCC for a piece of electrical equipment shall relate
          to that piece of equipment and to all cable supplying power to the equipment
          including the connection of the cable to the preceding piece of equipment.
7.14.3    Each portion of the installation shall then be tested and "checked out" in the
          sequence and in the manner described in Chapter 7.
7.14.4    On completion of each stage of the testing and checkout, the contractor's
          Superintendent shall satisfy himself that the stage is complete and shall date and
          sign the tag. He shall then advise the Area Electrical Engineer of the completion
          of the stage, and request the Engineer's approval before going on to the next
          stage.
7.14.5 In the case of motors, there will be an "Equipment Tag" mounted on the piece of
       equipment to be driven by the motor. The installation of the motor shall be tested
       and checked out as set out in the appropriate stages of the Equipment Installation
       Check out Procedure. The Contractor's Superintendent, when satisfied that each
         stage has been properly completed, shall date and sign the Equipment Tag and
         shall advise the other Contractor who is responsible for the installation of the
         driven equipment that the installation of the motor has been properly completed.
         When the other Contractor is satisfied that the motor installation is completed and
         does not interfere with the alignment of the equipment, he will sign the
         Electrical Tag in the space provided.
7.15.1    Stage 1
          Installation ready for Testing and Check out (Visual check to see if the following is
          completed)
           7.15.1.1      The whole assembly is clean inside and outside. No loose cables
                         hanging free. Ground wires clear of bus work and properly
                         grounded.
           7.15.1.5      Each starter is identified with correct drive number, drive title and
                         power rating.
           7.15.1.6      Feeder cables, if single conductors are used, that the load end of the
                         cables are insulated from the enclosure and from one another, the
                         connecting gland or clamp should also be insulated with plastic
                         electrical tape. This is to prevent shock from sheath voltage.
           7.15.1.7      All cables leaving Electrical Equipment have proper cable clamps
                         or glands.
           7.15.1.9      All openings are sealed to prevent steam and other foreign matter
                         from entering.
           7.15.1.12      Motors and connected units have been properly fastened down to
                          the base, and aligned. (Signatures affixed by others to the
                          alignment stage of Mechanical Check-out Tag, 2S-20.01).
7.15.2 Stage 2-
       Insulation Resistance Test
          7.15.2.1       Take megger test and record for all control circuits, motor leads,
                         feeders, etc. on equipment up to and including 5000 volts. Do not
                         megger static devices, tachometer or pulse generators, check with
                         ohm meter.
          7.15.2.4       Stress cones must be completed and be in accordance with the design
                         standards, prior to the DC Hi-pot test. Pig-tails are not to be added or
                         connected to stress cones at load and if length is less than 130m.
          7.15.2.6       When cables are re-connected they are to be in the proper phase
                         sequence.
7.15.3 Stage 3-
       For each type of equipment, check as noted.
                         4.        Batteries are suitably stored, and all connections are well made
                                  with no chance of loose connections. Vaseline has been applied
                                  over all terminals and connection points.
                         6.         Stress cones are adequate and all pig-tails are connected with
                                  the ground lead and must be returned back through the ground
                                  fault current transformer and then grounded.
                         8.         All relays and protection devises are wired correctly and are
                                  tested, such testing procedure will be available from the
                                  Engineer.
10. All instruments and relays are identified for their use.
                         11.      All cells are clean including the whole electrical room. Concrete
                                  floors should be painted if possible before the units are
                                  energized. This is to prevent concrete dust from entering the
                                  cells.
                         12.      The top of cells are sealed with silicone rubber caulking
                                  compound or the equivalent to prevent water, etc., from entering
                                  the cells if switch gear is not located in an air conditioned room.
                                  This is particularly important between 'cells and extension
                                  sections added to the rear for extra cable, etc.
                         13.      A single line diagram of the primary supply and feeder system
                                  shall be wall mounted as close to the cells as possible.
                         21.      Each breaker, including the main, should be operated three times
                                  to prove operating condition of the breaker and also that the
                                  protection devices are ready for operation.
                         12.      Static exciter and regulator are correctly connected and properly
                                  grounded.
                         16.      Assist to check relays, meters and other devices forming part of
                                  this generator system as shown on the drawings.
                         17.      Check all remote controls, meters and other devices forming
                                  part of this generator system as shown on the drawings.
                         6.       Sudden pressure switch and relay and other alarm points are
                                  working properly. See manufacturer's instructions for details.
                         2.       Contacts are clean, with proper tension, and all moving parts are
                                  free and properly aligned.
                         2.       Contacts are clean, with proper tension, and all moving parts are
                                  free and properly aligned.
                         2.       Contacts are clean with proper tension, and all moving parts are
                                  free and properly aligned.
                         7.       All devices, other than starters are identified and will operate as
                                  the drawings indicate.
7.15.3.7 AC Motors
          7.15.4.2       If breaker trips or fuse blows, re-megger motor leads and check
                         amperes reading and voltage at motor terminal box.
          7.15.4.3       Motor runs hot or trips from overload heater, check amperes reading,
                         and voltage at motor terminal box.
          7.15.5.1       Each piece of equipment shall, upon completion of all the required
                         check-out stages the Electrical and Mechanical Check-out Tags, secure
                         the approval of the Area Engineer on the installation completion.
          7.15.5.2       Any field changes made to original plans shall be recorded on a set
                         of 'as built drawings' and forwarded to Owner Plant Superintendent
                         upon completion of the installation.
7.15.5.4 All damaged equipment and material has been repaired or replaced.
          The grounding conductor of the wiring system shall be No. 4/0 AWG bare
          copper conductor. Except where conductor may be in direct contact with
          aluminum, conductor shall have a green insulated jacket.
          The 4/0 grounding conductor will run around the perimeter of each building to
          form a ground grid. The conductor shall be outside the foundation wall.
          Loops shall be provided at each electrical room and transformer slab location and
          provision shall be made to run ground conductor to each piece of electrical
          equipment as detailed on the electrical room and transformer slab layout drawings.
Contents:
1. Introduction
2. Responsible Persons
         3.1     Permit
         3.2     Procedure
         3.3     Principles Incorporated into the Procedure
         3.4     Actions Covered by Procedure
7. Switching Requests
1. Introduction
       This document addresses the livening of electrical facilities during the initial
       energization program.
1.1 Definitions:
       Energizing refers to making a system "Live" or electricity being put on to a system after
       that system has been commissioned and is approved.
       Livening refers to electricity being put on to a system for the "First Time" only.
2. Responsible Persons
       To exercise direction and control over energization and carry out all necessary
       switching operations under permit control, four officials are required. Their
       responsibilities and duties are defined in detail in the permit procedure, Appendices 2 and
       3.
       The following gives a summary of the responsibilities and duties of the respective
       officials.
       There are a number of defined construction areas within the project, each having
       its own electrical supervisor who is in charge of electrical construction work or in
       charge of subcontractors doing the work. The electrical supervisors will be the
       Construction Representatives (CR) for the livening of electrical facilities in their
       respective areas. The Construction Representative will advise the Energizing
       Coordinator which facilities are ready for livening, having confirmed the completion of
       checkout of the facilities, the category 1 punch items and the withdrawal of all
       construction personnel from the facilities. In the case of electrical facilities within sub-
       stations, he will hand over control of entry into the building premises to the
       Responsible Commissioning Engineer, Electrical, subject to the issue of an Interim
       Acceptance Certificate for the sub-station building and on the signing of a "Ready
       for Commissioning" (RFC) Certificate for the substation.
construction in progress.
       The Responsible Commissioning Engineer, Electrical (RCEE) will take over control of
       facilities to be livened, lock up facilities to prevent unauthorized access or accidental
       contact with live conductors and take all necessary steps to ensure safety of personnel
       and plant equipment.
       He will review and approve all switching requests before sanctioning these and passing
       them on to the Energizing Controller for execution. The Responsible Commissioning
       Engineer, Electrical will be the senior Operations Electrical Engineer carrying legal
       appointment as fee official in overall charge of the permanent power distribution
       network.
The permit and procedure are to secure permission to proceed with livening.
3.1 Permit:
3.2 Procedure:
       The procedure for the initial livening of electrical facilities is detailed in Appendix 2.
       It is consistent with Riau's practice and incorporates the minimum requirements to ensure
       effective control for safe and orderly livening.
       For clarity of how the procedure is structured and applied the following describes
       the main principles and terminology incorporated into the procedure.
a)     The facility (Circuit) to be livened must be identified. Following checkout of all items of
       equipment making up the facility and completion of Category 1 punch items, livening
       of any section of a power distribution network or facility may only proceed after the
       Construction Representative has notified the ECR that the electrical construction is
       complete and the facility is ready to liven.
b)     To make a circuit safe it must be electrically isolated from the source of supply. This
       is accomplished by opening the feeder circuit breaker and isolating the switch.
d)     A circuit under permit control is referred to as "permitted out". The permit holder
       puts his own lock on the circuit breaker for the period of time he holds the permit,
       to prevent anyone from inadvertently closing the circuit breaker and livening the
       feeder.
       The official responsible for switching (Energizing Controller) also places his lock on
       the circuit breaker to prevent unauthorized closure of the circuit breaker. A copy of the
       isolation permit is fixed to the circuit breaker and the circuit is then referred to as
       "locked out, permitted and tagged".
       No circuit may be made live unless the permit, against which it was isolated and
       taken out of service, has been cleared.
       The permit release thus becomes the main safeguard to control safe livening of
       circuits as the permit release can only be affected by the holder's endorsement of the
       Energizing Coordinator's master copy. The Energizing Coordinator will not issue a
       switching request for the livening of a circuit until he is in possession of the cleared
       permit.
f)     The closing of any circuit breaker may only be done against a switching request issued
       by the Energizing Coordinator and approved by the Responsible Commissioning
       Engineer and this is the second safeguard to controlling safe livening.
There are only four different actions allowed for in the procedure, these being:
a)     The issue of a switching request to isolate a circuit, together with the permit to cover
       the isolation of a circuit to be locked out, prior to being energized for the first time.
b)     The issue of a switching request to isolate a circuit, together with the permit to cover
       the isolation of a circuit to be taken out of service after it has been energized and placed
       into service.
a)     bump testing and uncouple test running a motor where its feeder circuit is isolated
       and locked out under an initial isolation permit; and
       For the purpose of locking out feeders, three sets of locks will be necessary (one
       set for each of the officials designated in paragraphs 2.1, 2.3 and 2.4). A
       combination of only two locks applied simultaneously to a feeder circuit breaker
       by two of the designated officials will be necessary to secure lockout in
       accordance with the procedure.
       Each official will retain control over the keys for his own set of
       locks and it is proposed that the key combination for the locks be
       arranged as follows: '
       The Construction Representative will have a set of locks for his own area. Ideally,
       each lock will have the same key (for different areas the locks must have different
       key combinations).
       These locks should be keyed alike to obviate the need to carry around large
       bunches of keys.
       These locks should be keyed alike but with a different key combination to those
       of the Responsible Commissioning Engineer set.
a)     Procedure No 1: To ensure that all feeder breakers (incoming and outgoing) and all
       bus-section (tie) circuit breakers are isolated and locked out and to initiate permit
       control over livening of facilities (prior to livening the facility under consideration for
       the first time). Compliance with this procedure is essential to set up and place the permit
       system in operation.
f)     Procedure No. 6: To liven a feeder temporarily for construction testing and to isolate it
       again on completion of the tests.
g)     Procedure No. 7: To temporarily remove locks from motor starter cubicles, which are
       isolated and locked out to allow access for completion of construction work?
7. Switching Requests
       Switching requests will be prepared by the Energizing Coordinator and issued to the
       Responsible Commissioning Engineer, Electrical, for review and approval to cover each
       and every livening or isolating operation which is necessary to execute. Appendix 4 is
       a typical example of a switching request.
SECTION 7
APPENDIX 1
                                                                                    Section 7
                                                                                  Appendix 1
                                                                                  Page 1 of 8
Circuit/Service                : ____________________
Located in Sub-Station No.     : ______________________
Switch gear Location - Tag No.: ________         Cubical No.: __________
______________________
We, the undersigned, certify that the circuit has been isolated and locked out. We have each
applied our own lock and mutually agree that the circuit may be safely worked on to complete
the specified work.
                                                                           Section 7
                                                                         Appendix 1
                                                                         Page 2 of 8
I, the undersigned permit holder, release the permit and notify completion of construction
work. All construction workmen have been withdrawn from the workplace.
Approved by:
Responsible Commissioning Engineer:          ______________            _________
                                               Signature                Date
We the undersigned certify that the feeder circuit breaker has been correctly identified
and confirm removal of the Construction Representatives lock and permit from the
circuit isolator.
                                                                                 Section 7
                                                                               Appendix 1
                                                                               Page 3 of 8
Section 3 - Permit to Liven
Initiated by:
Energizing Coordinator: _____________             _______             ______
                        Signature                 Date                Time
                                                                                Section 7
                                                                              Appendix 1
                                                                              Page 4 of 8
                                  Temporary Permit Release
I, the permit holder, request that the feeder be released to allow access to the equipment.
Approved by:
I certify that all necessary steps have been taken to cover any exposed live conductors
and accept full responsibility for supervision of all work on the equipment. Only qualified
electricians will be assigned to do this work and they have been instructed not to operate the
circuit isolator under any circumstances.
Locks removed and switch in open position as per above referenced switching request.
                                                                                Section 7
                                                                               Appendix 1
                                                                              Page 5 of 8
Release to Bump Test Motor Plant Equipment No.:
I, the permit holder, request that the feeder be made temporarily live to allow test running.
Switching Request No.: ________ issued (with copy routed via Area Process
Superintendent for information and approval).
Approved by:
Responsible Commissioning Engineer: _____________                __________
                                        Signature                   Date
I certify that all necessary steps have been taken to ensure safety of persons and plant and
accept full responsibility for supervision of the live circuit, the tests and isolation of the
circuit on completion of the tests. I have confirmed correct identification of the circuit and
witnessed completion of the megger and trip tests and switching as requested.
Construction
Representative: ____________               _______               ______
                  Signature                 Date                 Time
Locks removed and switching completed as per above referenced switching request, the
circuit having been megger tested and motor protection trip tested before livening.
                                                                                    Section 7
                                                                                  Appendix 1
                                                                                  Page 6 of 8
                      Notification of Completion of Work/Test Run
I herewith request that the circuit be re-isolated and locked out. Construction
Representative: _________________
                Signature
                                                                           Section 7
                                                                        Appendix 1
                                                                       Attachment 2
Section 7
                                                                                        Section 7
                                                                                      Appendix 2
                                                                                     Page 1 of 10
1. Introduction
        The electrical system energizing procedure and permit system is structured to achieve
        two goals, namely:
        -     to provide maximum safety for all personnel during the energization of the
              electrical system; and
        The procedure was developed from proven permit systems. From these proven permit
        systems the basic safety elements have been incorporated and the administrative parts have
        been simplified to satisfy the Riau situation.
        The procedure is designed to function quickly and efficiently, as the steps involved
        have been simplified and condensed to a minimum required while maintaining complete
        safety.
        Administration has been simplified to two operational documents and two database
        records of those documents.
2. Documentation
-     Electrical Isolation/Livening Permit: This document serves two functions. In the first
        instance, it provides a method to allow personnel to work safely on a portion of the
        system which could be energized. Secondly, it provides a method to ensure agreement
        that a portion of a system is ready and safe to energize and will be switched with the
        required checks and in the proper sequence.
-     Switching Request: This document provides a method to ensure that required safety
       checks, equipment checks and switching operations are completed in the correct
       sequence. The document provides a check to the switching operation and eliminates a one
       man judgment condition.
                                                                                       Section 7
                                                                                     Appendix 2
                                                                                    Page 2 of 10
2.2    Database Records
-      System Status Record: This record provides a current complete picture of the electrical
       system status as it is progressively energized. At any time it can be determined what
       parts of the system are energized, de-energized and under permit or de-energized but
       available for service. The information source for this record is the completed switching
       request.
-      Permit Status Record: This record provides a quick source of information to determine
       at any time that has the permit for any one circuit or what circuits are permitted out to
       any one individual. The information source for this record is the permits.
       For the Riau Project, the Construction Representative is either the Electrical
       Supervisor in charge of the construction work or the Senior Electrical Supervisor of
       the subcontractors doing the work within a defined construction area on the project. It is
       the responsibility of the Construction Representative to ensure that any work to be
       done on the electrical installation which could become energized, is done under
       PERMIT control.
       The Construction Representative in each construction area will have to appoint a backup
       representative who can perform these duties in his absence.
       The Construction Representative in each construction area will ensure that the project
       safety standards are enforced for any work on the electrical installation.
       -      Initiate the requests to release PERMITS when the work is completed and the
              circuit may be energized.
                                                                                Section 7
                                                                              Appendix 2
                                                                             Page 3 of 10
       -      Install a lock on any FEEDER circuit breaker of circuits where the work is
              to be performed.
       -      Remove the lock on any FEEDER circuit breaker of the circuit where the
              work has been completed.
       -      Place a lock on all FEEDER breakers which he has taken out under permit
              and retain the keys.
       -      Confirm that the correct feeder circuits have been taken out of service and
              certify the PERMITS accordingly.
       -      Confirm that the correct feeder circuits have been released for service and
              approve the PERMIT RELEASE.
       -      Confirm that the correct circuits have been energized when the circuits are
              placed into service.
       The Energizing Coordinator will have to appoint a backup representative who can
       perform these duties in his absence.
       -    Prepare all requests and releases of PERMITS and initiate isolation, lockout
            and permitting out of all circuits comprising any defined section of the power
            distribution network scheduled for livening.
                                                                                        Section 7
                                                                                      Appendix 2
                                                                                     Page 4 of 10
       -    Keep a record of what the total system energized condition is.
       -    Keep a record of what circuits are permitted out and who the permit was
            issued to.
- Be the only party allowed "up-date" capability access to the data base. 3.3
       He will cause all facilities to be locked up to prevent unauthorized access and all
       circuits to be electrically isolated to prevent accidental contact of persons with live
       conductors. He will take all necessary steps to ensure safety of personnel and plant
       equipment prior to allowing livening of facilities to commence.
       -      Place a lock on all incoming breakers and tie breakers which have been taken
              out under permit. (Blue Locks)
       -      Confirm that the correct incoming/tie breakers have been taken out of service
              and signs for the PERMITS as the recipient (permit holder) of these.
       -      Confirm that the incoming/tie breakers have been released for service and
              approves the PERMIT RELEASES.
       -      Confirm that the correct circuits have been energized when the circuits are placed
              into service.
                                                                                          Section 7
                                                                                        Appendix 2
                                                                                       Page 5 of 10
       The Energizing Controller will have to appoint a backup representative who can
       perform these duties in his absence.
       -      Make entries in sub-station log books to reflect intended switching (prior to actual
              switching), completion of successful switching and date and time of each entry.
       -      Place a lock on all incoming breakers, tie (Bus coupler) breakers and feeder
              breakers which have been taken out under permit. (Gold Locks)
       -      Post copies of initial isolation permits on feeders which have been permitted out
              and ensure that each circuit is tagged to reflect full details of the permit holder's
              name, location of his base office, supervisor's name and telephone number.
- Place an ENERGIZED (In Service) tag on each breaker placed into service.
       -      Confirm that the correct incoming/tie breaker and feeder breaker circuits have
              been taken out of service and certify the PERMITS accordingly.
       -      Confirm that the incoming/tie breaker and feeder breaker circuits have been
              released for service and certify the PERMIT RELEASES accordingly.
       -      Confirm that the correct circuits and loads have been energized when the
              circuits are placed into service.
                                                                                      Section 7
                                                                                    Appendix 2
                                                                                   Page 6 of 10
4. Permit Procedures
4.1    Permit to Request that a Circuit he Taken Out of Service Prior to the Circuit Being
       Energized for the First Time
       Initially, upon construction completion of each sub-station, all circuit breakers will
       be OPENED, TAGGED (with a copy of the isolation permit) and LOCKED OUT.
a) Feeder Breakers
                                                                                        Section 7
                                                                                      Appendix 2
                                                                                     Page 7 of 10
4.2    Permit to Request that a Circuit be Taken Out of Service After a Circuit Has Been
       Energized and Placed in Service
a) Feeder Breakers
                                                                                          Section 7
                                                                                        Appendix 2
                                                                                       Page 8 of 10
              -      The Energizing Controller will place a copy of the PERMIT on the incoming
                     or tie breaker which has been taken out of service and locked out.
4.3    Release of a Permit and Return of a Circuit to a "Ready for Service Condition" (Not
       Energized)
a) Feeder Breakers
              -      The Construction Representative will remove his locks on the feeder circuit
                     breaker released for return to service.
              -      The Energizing Controller will leave his lock in place until such time as he
                     receives an energizing request and switching instructions from the
                     Responsible Commissioning Engineer, Electrical.
                                                                                     Section 7
                                                                                   Appendix 2
                                                                                  Page 9 of 10
         - The Energizing Controller will remove the copy of the PERMIT on the feeder
           breaker which has been released for service.
a) Feeder Breakers
         - The Energizing Coordinator prepares and submits a release note and switching
           request to the Responsible Commissioning Engineer, Electrical for review and
           approval.
         - The Energizing Controller will switch the feeder breaker circuit into service
           according to the switching request issued by the Responsible Commissioning
           Engineer, Electrical.
         - The Energizing Controller and the Construction Representative will each sign the
           PERMIT for the feeder circuit returned to service and return the PERMIT to the
           Energizing Coordinator for the records.
         - The Energizing Controller will remove the copy of the PERMIT on the feeder
           breaker which has been released for service.
                                                                                 Section 7
                                                                               Appendix 2
                                                                             Page 10 of 10
         - The Energizing Controller will switch the feeder breaker circuit into service
           according to tile’s switching request given by the Responsible Commissioning
           Engineer, Electrical.
         - The Energizing Controller will remove the copy of the PERMIT on the feeder
           breaker which has been released for service.
Section 7
                                                                                                                                   Section 7
                                                                                                                                 Appendix 3
                                                                                                                                 Page 1 of 1
   5     With the Energizing Controller,                                          With the Energizing Controller,          With the Construction Representative
         confirms that the feeder circuits to                                     confirms that the incoming/lie           and Responsible Commissioning
         be switched out of service are                                           breakers to be switched out of service   Engineer to witness the switching
         correctly identified.                                                    are correctly identified.
   6     Approves the PERMITS and                                                 Approves the PERMITS                     Switches the circuits out of service
         keeps a copy of each PERMIT.                                                                                      and signs each Permit to certify that
         Witnesses switching and signs                                                                                     circuit has been isolated.
         each permit to certify circuit
         isolation.
   7     Puts construction locks on all the                                       Puts Responsible Commissioning           Puts Energizing Controller locks on all
         feeder breakers of the circuits                                          Engineer, Electrical locks on all of the of the breakers of the circuits taken out
         taken out of service. The CR                                             incoming and tie breakers taken out of of service. The EC keeps his keys.
         keeps his keys and signs                                                 service. The RCEE keeps his keys
         acceptance of and keeps a copy                                           and signs for acceptance of the
         of, each permit                                                          relevant permit as the permit holder.
   8                                                                                                                       Attaches a copy of the relevant
                                                                                                                           PERMITS to each breaker of the
                                                                                                                           circuits taken out of service
Section 7
APPENDIX 4
       Page 1 of 1
                              CONSTRUCTION RELATED ACTIVITIES                                                                                         OPEARATIONS RELATED ACTIVATES
STEP      CONSTRUCTION REPRESENTATIVE (CR)                 ENERGISING CO-ORDINATOR (ECR)                                    RESPONSIBLE COMMISSIONING                               ENERGISING CONTROLLER (EC)
                                                                                                                           ENGINEER, ELECTRICAL (RCEE)
 1                                              Determines that a circuit needs to be taken out of service to support Determines that a circuit needs to be taken
                                                the construction programmed.                                          out of service to support system operating
                                                                                                                      conditions.
 2                                              Confirms circuit to be switched out of service and prepares Requests The Energizing coordinator to take a
                                                the SWITCHING REQUEST for that circuit.                               circuit out of service.
 3                                              Initiates a PERMIT to take the circuit out of service. Sends the      Reviews and approves the SWITCHING
                                                PERMIT with SWITCHING REQUEST to the Responsible                      REQUEST. Instructs the Energizing
                                                Commissioning Engineer, Electrical.                                   Controller to proceed.
 4                                                                                                                                                                   Contacts the Responsible Commissioning Engineer, Electrical,
                                                                                                                                                                     to witness and confirm the switching.
 5                                                                                                                With the Energizing Controller, confirms that the With the Responsible Commissioning Engineer, Electrical
                                                                                                                  circuit to be switched out of service is correctly confirms that the circuit to be switched out of service is correctly
                                                                                                                  identified.                                        identified.
 6                                                                                                                Approves the PERMIT. Witnesses switching           Switches the circuit out of service and signs PERMIT to certify
                                                                                                                  and certifies isolation of the circuit and signs that circuit has been isolated.
                                                                                                                  for acceptance of the permit as the permit
                                                                                                                  holder.
 7                                                                                                                Puts a Responsible Commissioning                     Puts an Energizing Controller lock on the breaker of the circuit
                                                                                                                  Engineer, Electrical, and lock on the breaker of     taken out of service. The EC keeps the key in his possession.
                                                                                                                  the circuit taken out of service. The RCEE
                                                                                                                  keeps the key in his possession.
       Page 1 of 1
                               CONSTRUCTION RELATED ACTIVITIES                                                                                        OPEARATIONS RELATED ACTIVITIES
STEP      CONSTRUCTION REPRESENT ATIVE (CR)                 ENERGISING CO-ORDINATOR (ECR)                              RESPONSIBLE COMMISSIONING                                   ENERGISING CONTROLLER (EC)
                                                                                                                       ENGINEER, ELECTRICAL (RCEE)
 1                                                                                                               Requests the Energizing coordinator to release a
                                                                                                                 circuit to Operations.
 2                                               Confirms that the circuit is available and ready to energies.
 3                                               Prepares the SWITCHING REQUEST for the circuit. Sends the       Reviews and approves the SWITCHING
                                                 SWITCHING REQUEST to the Responsible Commissioning              REQUEST. Obtains an approval to energies
                                                 Engineer, Electrical.                                           from the process area superintendent.
                                                                                                                 Instructs the Energizing Controller to proceed.
 4                                                                                                               With the Energizing Controller, confirms that the     With the Responsible Commissioning Engineer, Electrical,
                                                                                                                 circuit to be energized is correctly identified and   confirms that the circuit to be energized is correctlyidentified.
                                                                                                                 clear of personnel.
 5                                                                                                                                                                     Places ENERGISED (in service) tags on the equipment tobe
                                                                                                                                                                       energized.
 6                                                                                                                                                                     Remove the Energizing Controller lock on the breaker of the
                                                                                                                                                                       circuit to be energized.
 7                                                                                                                                                                     SWITCHES THE BREAKER "ON", Energizing the circuit.
 8                                                                                                               With the Energizing Controller, confirms that the     With the Responsible Commissioning Engineer, Electrical,
                                                                                                                 load placed into service is energized and             confirms that the load placed into service is energized and
                                                                                                                 operational.                                          operational.
 9                                                                                                               Places the circuit under the normal Operations        Returns the original SWITCHING REQUEST to the Energizing
                                                                                                                 permit control.                                       Coordinator.
 3                                                                Sends the TEMPORARY PERMIT RELEASE and the                        Approves the TEMPORARY PERMIT
                                                                  SWITCHING REQUEST to the Responsible                              RELEASE. Obtains approval to energies from
                                                                  Commissioning Engineer, Electrical.                               the process area superintendent.
 4                                                                                                                                  Reviews and approves the SWITCHING
                                                                                                                                    REQUEST. Instructs the Energizing
                                                                                                                                    Controller to proceed.
 5                                                                                                                                                                               Contacts the Construction Representative to remove locks
                                                                                                                                                                                 and to witness and confirm the switching.
 6     With the Energizing Controller, confirms that the                                                                                                                         With the Construction Representative, confirms that the
       circuit to be released and clear of personnel.                                                                                                                            circuit to be released and energized is correctly identified.
 7     Signs the TEMPORARY PERMIT RELEASE                                                                                                                                        Places ENERGISED (In Service) tags on the
       accepting responsibility for supervision of the live                                                                                                                      equipment to be energized.
       circuit and keeps a copy of the TEMPORARY
       PERMIT RELEASE.
 8                                                                                                                                                                               Attaches a copy of the TEMPORARY PERMIT
                                                                                                                                                                                 RELEASE to the breaker of the circuit to be energized.
 9     Removes the Construction Representative lock on the                                                                                                                       Removes the Energizing Controller lock on the circuit
       circuit breaker of the circuit to be energized.                                                                                                                           breaker of the circuit to be energized.
 10                                                                                                                                                                              Megger tests circuit, trip tests electrical protection and
                                                                                                                                                                                 SWITCHES THE BREAKER "ON", ENERGISING THE
                                                                                                                                                                                 CIRCUIT.
 10                                                                                                  With the Energizing Controller, confirms that With the Responsible Commissioning Engineer,
                                                                                                     the circuit placed into service is energized and Electrical, confirms that the circuit placed into service is
                                                                                                     operational.                                     energized and operational.
 11                                                Records the switching action on the SYSTEM STATUS                                                  Returns the original PERMIT RELEASE and
                                                   RECORD. Records the PERMIT RELEASE information on                                                  "Completed" SWITCHING REQUEST to the
                                                   the PERMIT STATUS RECORD.                                                                          Energizing Coordinator.