Tender Bid Documents: IITB/Dean IPS/DC/Main Building Phase 1/INT
Tender Bid Documents: IITB/Dean IPS/DC/Main Building Phase 1/INT
“Proposed Interior & Renovation of Main Building Phase 1 consisting Civil, Interior,
Electrical & Furniture works for Indian Institute of Technology Bombay within IITB
campus Powai. Mumbai –400 076”
FOR
ELECTRICAL WORKS
TECHNICAL SPECIFICATIONS
1.0 SCOPE
Electrical installation work and supply of electrical equipment and accessories shall conform
to the relevant, latest Indian Standards (IS) specifications and shall also comply with the
requirements of the regulation or acts in force in the Loner together with other relevant
specifications with particular reference to the following.
Entire electrical installation, testing and commissioning shall be carried out in accordance with the
general specification and shall comply with the requirements of currently applicable statutory
regulations or acts in force including but not limited to the following
3.2 Nothing in this specification, and attached drawings shall be construed to relieve the contractor of
his responsibility to make the installation comply with the requirements of the above. It shall be
the responsibility of the contractor to obtain approval of competent Govt. authorities and satisfy
them regarding the compliance with relevant regulations, for his scope of work. Any inspection
required to get the electrical installation cleared by relevant authorities shall be to contractor's
account.
3.3 Test certificates for the installation shall be prepared in the form required by The Electrical
Inspector / Electricity Board. Any rework necessitated on Account of remarks by Electrical
Inspector / Electricity Board shall have to be carried out by the contractor at no extra cost.
a) The contractor shall be responsible for the supply, delivery, Unloading and transportation to
site, installation, testing and commissioning of all Electrical equipments / materials as
indicated in schedule of quantities, and all papers of documents to be filled and all relevant
certificates / TC etc.
c) The Contractor shall be responsible for the satisfactory operations of the equipment supplied
by him for the period of 12 months from the date of commissioning or 18 months from the
date of delivery whichever is earlier.
d) In case of custom-built items, Contractor shall obtain the approval of general arrangement
drawings from the engineer in charge at site.
e) The Contractor shall make available all the machines, tools, tackles, testing equipment, etc,
required for the period of installation work,
5.1 All installation materials covered under the ‘Schedule of Quantities and Rates’ including
necessary hardware such as clamps cleats nuts and bolts, brick, sand, coke and salt, solders,
fluxes & all accessories etc. including all consumables like electrodes, gases etc. shall be
supplied by the Contractor.
5.2 The Contractor shall not avail himself of any unintentional errors or omissions in the
descriptions gives in this specification and attached drawings.
5.3 Contractor shall also keep a check on the deliveries of the equipment / material covered in his
scope or erection and shall advise owner well in advance regarding possible holdups in his
work due to expected delays in delivery of equipment to enable owner to expedite the
deliveries.
5.4 All packing/ plates/ shims required for the alignment/ leveling of equipment should have to be
arranged by the contractor as per instructions of the owner or his representative, free of
change.
TENDER DOCUMENT – VOLUME 2 OF 3 3
TECHNICAL SPECIFICATION SIGNATURE & SEAL OF TENDERER
IITB/Dean IPS/DC/Main Building Phase 1/INT
5.5 Final touch up of electrical equipment, if required shall be carried out by the contractor. Paint
will be arranged by the contractor. Brushes shall be arranged by the Contractor.
5.6 Single line welding shall not be accepted. All joints shall be made by lap welding and all
jointing lines will be welded by qualified welder ( ITI )
6.1 All switchgears shall be handled with care and use of crane / fork lift and trailer shall be made
for Unloading / handling as well as for the purpose of installation.
6.2 All equipment and panels to be installed shall be transported from the storage are to the
location of installation by the Contractor. The panels shall preferably be kept inside the
packing cases till the foundations are ready. This packing shall be opened only at the place
where it is required to be installed.
6.3 Installation of switchgear also includes assembling the panels, aligning the same and fixing
on the foundation as per the manufacture’s / supplier’s instruction. All the components shall
be checked for tightness as well as for any visual damages. Visual damages shall be brought
to the notice of the owner. Busbars should be tightened to 35 KN-m to 50 KN-m by torque
wrench.
6.4 In the event of switchgear giving the low I.R. value, switchgear shall be dried-up/ treated with
air drying as per the manufacture’s recommendations to improve the I.R. value to the safe
value for commissioning.
6.5 Earthing of the switchgear shall be done using the proper size of conductors as per the
relevant engineering documents.( IS – given in front page No. 2 )
6.6 Main bus bars, bus risers shall be connected to fixed and outgoing terminals and bus
systems shall be totally enclosed by individually taping with not less then five half-layer
insulating tapes on all busbars. All joints shall be padded with plastic compound prior to
taping. Control wiring, AC & DC control supply connections shall be interconnected between
different shipping sections of the switchgear cubicles.
6.7 All switchgear shall be tested at site as per the manufacture’s recommendations and shall
include the minimum following tests.
a) Visual inspection for dimensional check-up, completeness of the equipments as per the
manufacturer’s documents, furnishing the list of missing components, if any, tightness of
all the terminals/ equipments, etc.
b) Measuring I.R. Value.
c) High voltage test.
d) Testing of protective relays with primary and secondary injection test, wherever
applicable.
e) Stimulation test for all the interlocks, annunciations and for the correct operations of the
switchgear.
f) Testing of oil for Di-electric strength, wherever applicable.
g) Any other tests as recommended by Site Engineers / Site-in-Charge.
6.8 All the switchgears shall be cleaned with vacuum cleaners before commissioning.
6.9 Plugging / sealing of all the unused cut outs for the cable glands in the equipment.
7.0 MAIN PCC/ DG PCC, CAPACITOR BANKING/ CAPACITOR PANEL & POWER & MOTOR
CONTROL CENTER
All testing & Commissioning shall be done by the contractor in presence of manufacturers
Engineer/ site engineer, before Testing SOP to be made.
7.1 Capacitor banks with PFIC panel shall be installed and commissioned after checking all
connections as per the Manufacturer’s detailed technical manuals.
7.2 UPS panel shall only be installed and UPS supplier shall carry out commissioning.
8.0 WALL MOUNTING PANELS (DB) / LOCAL STARTERS/ P.B. STATIONS, POWER AND
LIGHTING RECEPTABLES / LSB /etc.
8.1 Normally wall mounting panels including light distribution boards, power distribution boards,
push button stations, local starters, power and lighting receptacles are mounted on fabricated
steel mounting frames which are either grouted into the building walls using Anchor bolts of
10mm & 75 mm long or welded to building structural members or welded to separate
mounting channels on the floor.
8.2 The locations of items referred in the clause above and as shown in the drawings are
approximate. The electrical contractor shall check actual location of these devices in the field
with the Engineer-in- charge so that the locations are convenient from the operational point of
view and do not interfere with removal and maintenance of any equipment.
8.3 The mounting height of the wall mounting panels, P.B. Stations, local starters, switches and
receptacles shall be generally 1.2 m above ground level or mutually decided as per site
conditions.
8.4 The Contractor shall fabricate necessary frames, brackets, mounting channels, canopy if
located outdoor etc. for installation of these equipment from the structural steel. The
installation of this equipment shall include fabrication of necessary frames/ brackets, grouting
of these frames in RCC / Masonry walls using 10 mm & 75 mm long Anchor bolts, grouting of
mounting channels where applicable in the floors using 10 mm & 75mm long Anchor bolts,
welding of mounting frames / brackets to building structural columns or mounting channels.
Necessary civil works for the above shall be carried out by the electrical contractor. Painting:
after applying derusting primer, the two coats of Synthetic enamel paint to be applied.
9.0 CABLES
9.1 SCOPE:
This specification covers the requirements of Power Cables Upto 1.1KV, and Lighting Cables
with general purpose insulation and sheaths. Requirement of special sheaths with Fire
Survival (FS) and flame retardant low smoke (FRLS) characteristics are also covered in this
specification.
a. Transporting the cables from the store to various locations of installations in such a manner to
achieve maximum utilizations and avoiding cable jointing.
b. Drums under the Contractor’s custody shall be arranged properly in drum-yards and cable
shall be cut after measuring the exact length at site with respect to cable schedule / after
taking dimensions at the locations. The cut lengths of cables shall be properly sealed to
prevent ingress of moisture. And empty wooden drums to be shifted to scrap yard.
c. Before laying, the cables shall be tested for continuity and insulation value after it is cut.
d. Cables shall be laid in trenches, trays on walls, columns, structural steel as per requirements
shown in respective engineering documents.
e. All cables shall be dressed properly in aesthetically acceptable manner as approved by
Engineer-in-charge. Extra length in form of Loop shall be provided near termination for all
cables, wherever possible.
g. Cable termination shall be carried out using appropriate size of single/ double compression
weatherproof cable glands and suitable size of crimping type tinned copper cable lugs for
copper cables and aluminum cables. All glands shall be nickel plated brass. With de-oxidizing
one cable joint mili-volt loss to be logged for HT paste main cables.
h. Cable gland shall be of ‘COMET’ made and cable lugs shall be ‘DOWELL’s make (Brass)
i. Cable identification tags shall be provided on either end of the cable as well as at bends and
at an interval of 30 meters. The tags shall be made of 2 mm thick aluminum strip or 22 SWG
SS strip 20mm wide and embossed with cable number as per respective cable schedule. The
tags shall be fastened to cables by brass wires. Alternative new material / method to be
evaluated during execution.
k. All cables after terminations shall be provided with ferrules to identify the terminal number as
per the vendor/ engineering documents.
l. Cables installed in places where mechanical damages are likely to occur shall be protected
by G.I conduits / pipes Upto 2000 mm from the ground / floor level. If cable travels vertically.
m. Chasing in wall for embedding cable / conduits shall be done using electrically operated
Cutters. Contractor should engaged skilled labour to give satisfactory finish as acceptable to
client.
The design, construction, manufacture and performance of cables shall comply with all
currently applicable statues, regulations and safety codes in the locality where cables will be
installed. Nothing in this specification shall be construed to relieve the VENDOR of this
responsibility.
9.3 SPECIFICATIONS :
The following aspects are applicable for all the types of cables covered in this specification.
a) Construction and Performance of the Cable shall conform to the Standards indicated
herein.
b) Conductor :
Conductor shall be tinned when indicated under notes in relevant Data sheet.
Insulation for cables shall be as per requirement indicated herein and shall conform to
the properties covered in the following applicable standards.
d) Core Identification
Colour coding shall be acceptable for all cables upto 5 cores. Cables with more than 5 cores
shall have printed numerals on each core.
e) Inner sheath
Inner sheath when specified shall be extruded type and shall be compatible with the insulation
provided for the cables.
f) Armour
Armoring for the cables shall comprise galvanized steel or hard drawn aluminium, in the form
of round wires or strips. These are designated as below in Data Sheet.
Any other special requirement of armour shall be as per section – C of the specification or as
indicated under notes in Data Sheet.
g) Outer Sheath
The outer sheath shall be of an extruded layer of suitable synthetic material compatible with
the specified ambient and operating temperature of the cables. The sheath shall be resistant
to water, ultra violet radiation, fungus, termite and rodent attacks. The colour of the outer
sheath shall be black otherwise specified In Section – C or under notes in Data Sheet.
Elastomer and PE sheath shall meet the requirements of standards covered under 3.1.c
above.
Cables shall be subjected to routine and acceptance tests in accordance with standards
specified. Test methods shall conform to IS 10810 (Methods of Test for Cables). Type tests
and optional tests according to applicable standards shall be conducted on cables when
specified in Section – C or under notes in data sheet. BIDDER shall ensure use of calibrated
test equipment having valid calibration test certificates from standard laboratories traceable to
National standards.
i) Cable Drums
Cables shall be supplied in non – returnable wooden drums. The wood used for construction
of the drum shall be properly seasoned and free from defects and wood preservative shall be
applied to the entire drum. All ferrous parts shall be treated with a suitable rust preventive
coating to avoid rusting during transit or storage. Cables drums shall confirm to IS 10418
(Specification for drums of electric cables).
The BIDDER shall indicate in the offer, the maximum length for each size of cable, which can
be supplied on one drum. The actual length supplied on each drum shall be within tolerance
limit of + 5% with an overall ceiling of + 5% on total ordered quantity of each size of cable
unless otherwise indicated in Section – C/Data sheet. However, before winding the cables on
drums, VENDOR shall obtain PURCHASER’s approval for the drum lengths. Cable ends
shall be sealed by non-hygroscopic sealing caps.
Cable lengths specified in Data sheet are approximate only. Actual requirements will be
advised to the successful BIDDER at the time of placing the order.
Incremental cable lengths in meters shall be embossed on the outer sheath of every 1 meter
interval when specified in Section – C or under notes in Data sheet.
c) Twisting : The insulated conductors shall be twisted together to form twisted pairs or
quads, these shall be stranded in concentric layers to form the cable core. The cable thus
formed shall be tighty lapped with outer wrapping tapes.The interstices of insulate cable core
shall be completely filled with viscose compound.
d) Overall Width 0.05 mm aluminium tap or 0.013 mm Melinex screening tape, overlap not
less than 30%.
e) Other details: A suitable non – magnetic rip cord shall be laid details longitudinally under the
sheath. The armoring shall be of galvanized steel wires or galvanized single steel strip. The
inner PVC sheath shall be of type – A. The outer PVC sheath shall be of Type ST-1.
f) Voltage tests for: Dielectric withstand between conductors – 500 V for 1 minute (rms) and
between conductor and sheath – 2000 V rms/3000 VDC.
The construction, performance and testing of the cable shall comply generally with the following
standards:
i) IEC 189-1 (Low frequency cables wires with PVC insulation and sheath General tests and
measuring methods.
a. All cable trays shall be Perforated / ladder type, prefabricated fire retardant plutunded section
of various colors, light weight easy installation to be used. Galvanized MS or of perforated G.I.
Or type as specified in schedule of quantities / rates & shall comply with specifications of
National Electrical code. All bolts, nuts washers shall also be hot dip galvanized and shall
confirm to latest I.S. All bends in cable trays shall be smooth and curvature for bend shall be
suitable for the largest diameter of cable running in tray (Minimum bending radius for cables
12-15D) The width of the cable tray shall be decided on the No. of cables to be laid in such a
manner that minimum distance between two cables shall not be less than one cable diameter.
The straight sections of cable trays shall be supplied in 2.5 M length. The side angles have
three 10mm diameter holes at each end of the straight sections, elbows, crosses, tees etc. for
fixing the side couplers. All elbows, ts junction bend, shall be fabricated to suit site
requirements. To prevent entry of water through wall openings the cable trays shall be offset
at the building entry point that is the elevation inside the building shall be higher than the
outside. And opening to be closed with special material.
b. Perforated trays shall be of channel type of 50mm height & width as specified in drawings.
Ladder type shall be made of 40 x 20 slotted for the rungs & 100mm x 30mm channel for side
rails. The thickness of sheet steel for various types of trays is 2mm Upto & including 300mm
width
c. Cables in horizontal trays shall be tied using nylon tie wrap of suitable size at an interval of
one meter. Horizontal trays shall be clamped with the supports/ structure/ racks at an interval
of 500mm.
d. Cables in vertical trays shall be clamped at an interval of 50mm using strip fastener suitable
non-metallic material. (Vendor to specify)
e. Generally along with each cable routes separate two Nos. of bare earth wires/ strips shall run
in cable trays.
f. Cable trays shall be supplied with all accessories like 90 deg. Bends, coupler plates, Tees,
reducers, 4 way cross, Anchor fasteners for installation etc.
11.0 ALL CABLES SHALL BE TESTED AS UNDER BEFORE ENERGISING THE SAME:
a. Megger test using 1000 volt Megger for all L.T. cables. With calibration certificate
12.1 All equipment shall be earthed using appropriate size of hot dip galvanized (galvanizing
thickness not less than 100 microns) G.I. / COPPER Flats / G.I. wire as shown in respective
engineering documents/ drawings. ALCOMETER checking of Thickness of 100 microns to be
shown to consultant / client.
12.2 The resistance of the total earthing system shall be less than one ohm to ensure satisfactory
operating of protective devices.
12.3 The earth pit shall be plate type & as per the engineering standard documents to comply with
I.S. 3043 / other relevant specification / documents.
12.4 All main earthing grid shall be joined by full welding having over-lapped joints and shall be
protected with bitumen compound. Connections to the equipment shall be of hot dip
galvanized materials. Terminal joints shall be bolted type & total.
12.5 Earth pit installation and laying of main earthing grid shall include excavation, re-filling
hamming and leveling with soft soil of the earth and leveling the ground. Main earthing grid
shall be buried at minimum depth of 800mm below finished ground level. Plate electrode shall
be G.I & of dimension as specified in the drawing. The plate shall be buried vertically in
ground at a depth not less than 3 meters with its face vertical. Earth leads to the electrode
shall be connected to the plate with bolts, nuts, & washers. A.G. I. pipe for watering as
specified in drawings shall be clamped with bolts vertically to the plate & terminated to a wire
mesh funnel which shall be enclosed in a fine masonry chamber (RCC with 1:3:6 ratio). The
masonry chamber shall be provided with G.I frame & C.I. inspection cover with proper
painting & marking.
12.6 Wherever entry of water due to rains or any other reason is likely to occur during excavation,
Contractor shall make available necessary dewatering pumps
12.7 All earthing materials shall be hot dip galvanized as per I.S.
12.8 Earthing system shall be tested for individual resistance of earth pit as well as for the total
earthing grip.
12.9 The lightning arrestors roof & down coming conductors shall be connected to the earthing
system through separate earth pits.
12.10 Earth wire shall run throughout the conduits/ pipes/ trays. All clamping shall be done using
clamps.
13.1 The lighting fittings shall be installed on the ceiling / column/ wall or ceiling cutout as shown in
appropriate engineering documents. The supporting arrangements shall be approved by the
Engineer-in-charge. Location of lighting fittings, switches etc. shall be generally as shown on
the drawing.
13.2 All structural support/ lighting poles, wherever provided, shall be duly painted with 2 coats of
zinc phosphate/ zinc chromate primer and 2 coats of enamel paint after the installation of
fittings. (Vendor to quote for polyurethane quoting for structures & poles, alternatively) Heat
resistance
13.3 All cables shall be 1100 Volts grade, PVC insulated, copper/ Aluminum Conductor, as per IS
with appropriate colors
13.5 Lighting switches and panels shall be installed on walls/ column at a height of 1.2 Mtrs above
ground using suitable structural steel wall bracket / stand to ensure that the same are lifted
from the wall to the extent of 40mm. Thickness of the switchboard shall be 16 SWG.
13.6 Lighting panels /DB’s shall have cable entries from top by providing suitable gland plate/
knock-out plates. Lighting panels/ DB’s shall be fabricated only after obtaining the approval of
general arrangement drawings from the concerned site engineer. The lighting panels shall
have terminals for all incoming and outgoing cables.
13.7 Lighting fittings wherever applicable shall be provided with capacitors to improve power
factor. Installation of lighting fittings shall also include providing lamps and energizing the
same.
13.8 Flameproof fixtures shall be wired using armoured, copper cables & flameproof double
compression cable glands without junction boxes. All fittings shall be earthed by G.I wire and
tinned copper lugs for connections to fittings.
13.9 All lighting fittings shall be earthed using 8 SWG G.I wire and special lugs for connections to
fittings.
13.10 Installation of lighting fittings shall also include providing lamps and energizing the same.
13.11 Lighting poles shall be as per the relevant drawings & shall be of specified section with
swaged joints. The street lighting / floodlighting poles are normally supplied with one coat of
primer. The electrical contractor shall apply a coat of bituminous paint to the bottom portion of
each pole which is being embedded in the concrete foundation and an additional coat of
primer to the rest of the pole. The installation of the lighting pole shall include excavation of
the earth for the foundation and casting of the RCC concrete foundation as shown in the
drawing. G.I. pipe shall be embedded in the R.C.C concrete foundation as shown in the
drawing to route the supply cables to the control box on the lighting pole. After the installation,
the lighting pole shall be given two coats of epoxy paint of approved shade. (vendor to quote
alternatively for polyurethane coating)
14.0 MOTORS:
14.2 The Contractor shall check the cable entry provided on the motor cable box for fixing the
gland and inform the owner/ owner’s representative of requirement of reducers, if any
sufficiently in advance or procure necessary reducers.
14.3 Larger rated Motors/ Alternator etc., may require modification of cable box for cable
termination. The Contractor shall carry out the same as per requirement of site Engineer.
14.4 The motor shall be earthed at two different points. The earthing strip/ wire shall be neatly laid
and clamped. If earthing is of wire then, the said wire to be terminated through lugs, paint to
be scrapped where earthing is connected & continuity to be checked for motor.
14.5 In case of cable from trench/ ground, lower floor etc. G.I. pipes shall be provided to bring the
cable and the opening of the pipes shall be sealed with compound after commissioning the
motor
14.6 The motors shall be run on no-load for four hours, after checking the condition of grease and
bearings. Temp to be marked for future maintenance
14.7 The motors shall be tested for insulation value before commissioning. The insulation value of
individual motors shall be recorded properly and handed over to owner/ owner’s
representative. If required, the windings shall be dried with space heaters. A motor inspection
chart to be prepared in which insulation, No load current voltage, RPM etc. to be noted.
14.8 Decoupling and coupling of motors for checking the direction of rotation is part of contractor’s
scope. History card to be filled with all data like HP.--, RPM--, Frame size, -- etc. Format will
be given by consultant.
15.1 Structural steel required for the cable tray, equipment foundation, equipment supports etc.
shall be treated as separate item & accordingly payment shall be made as per rate quoted in
schedule of work. The rates quoted for installation work of various equipment shall not include
any major steel work. However minor steel material such as cable clamps etc. shall be
included in relevant item. Material take-off of structural steel for this purpose shall be
prepared by contractor & furnished in advance enabling client/consultant to decide for scope
of supply of steel. However fabrication and installation shall be carried out by contractor.
Quantities indicated in specification are approximate.
15.2 Installation are of structural steel shall include fabrication work also. All fabricated portions of
steel shall be painted with after de rusting, 2 coats of zinc phosphate/ zinc chromate primer
and 2 coats of enamel paint of approved shade to be decided by the site Engineer.
16.1 All equipment shall be tested in presence of Site Engineer as per the relevant IS/ as specified
in this specification/ as directed by the Engineers-in-charge and proforma test reports shall be
prepared for all the equipment and signature to be obtained on test report.
16.2 Installation rates as quoted in schedule of quantities/ rates shall include installation of
equipment, testing and commissioning of the same.
16.3 Contractor shall be required to provide their own, calibrated with calibration certificate with
valid date, for testing equipment and the same shall be available at site throughout the
execution of the work.
16.4 A brief schedule of the tests to be carried out on each type of electrical equipment is given
below.
All cores of cables shall be tested individually for continuity and Insulation Resistance before
connecting to the equipments.
Point wiring shall consist of all the materials right from distribution board together with a
switchboard, control switches with front plate & box of same make as switch, fan regulator,
plug sockets, industrial plug sockets as required including providing conduits & accessories,
the ceiling rose, lamp holders, connector, pendant holder or a swan holder, fan hook boxes,
junction boxes etc. with proper termination.
17.1 All lighting fixtures & ceiling fans, wiring shall be carried out using 3nos. 2.5 Sq. mm PVC
insulated FRLS stranded copper conductor 660/1100 V grade PVC insulated wires in 16
SWG black enameled MS conduit / PVC conduit . Wiring from D.B. to the switches & switch to
switch shall be done using 2.5 Sq. mm stranded copper wires. Separate wire shall be used for
earthing of all points. Individual junction/ Inspection boxes shall be provided for each lighting
fitting for the purpose of looping from fitting to fitting. The boxes shall be round / square with
Knockout holes suitable to terminate the conduits. The boxes shall have concealed screwed
sockets to fix the ceiling rose. Boxes shall be minimum 50 mm deep. Looping shall be done in
lighting fittings. Installations of ceiling fans shall be inclusive of embedding / grouting of
necessary suspension hooks in building RCC work and installation of fan regulator on the
building wall. The installation of exhaust fans shall include fabrication of necessary steel
framework, making the opening in the masonry wall and grouting of the steel frame work in
the opening. After installation of the frame work, the masonry work shall be made good to
original condition by the contractor.
17.2 All single phase plug sockets (Upto 16A) wiring shall be carried out using 3 core 3nos. 2.5
Sq. mm PVC insulated FRLS stranded copper conductor660/1100 V grade.
17.3 Point wiring shall include all necessary conduits with G.I pull wire, conduit fittings, conduit
accessories like saddles, spacers, bends, couplings, collars etc., junction/ pull/ inspection
boxes, wire, conduit supports, bushings, lamp holders, ceiling rose, flexible conduit/inspection
L bends, fan hooks wherever required & terminations using tinned copper lugs of crimping
type. A point wiring shall include in addition the earth continuity conductor / wire from the D.B.
to the earth pin / stud of the outlet/ switchbox & to the outlet point. In addition point writing
shall include provision of PVC sheathed flexible three core extension chords including flexible
conduit from light/outlet points to the light outlets.
17.4 The system of wiring will be as specified in the drawings. In case of lighting point wiring,
wiring form D.B. or Switch to common switch controlling more points will be measured
considering first point (From D.B. or switch to switch till First point) as full point and
subsequent point as half points. Maximum number of points in one circuit shall be limited to
7/8 or 1000 watts. Neutral wire size shall be same as the phase wire. All terminations shall be
done using copper lugs.
17.5 In case of power point wiring, maximum two power plugs shall be looped from one circuit. A/C
Industrial power plug point shall be fed from one circuit. They shall not be looped. Neutral wire
size shall be same as the phase wire. All terminations shall be done using tinned copper lugs.
17.6 All switches and plugs sockets shall be enclosed in 16 SWG sheet steel enclosures with top
plate both of same make as of switches/ sockets. Switchbox shall be concealed/ Flush
mounting/ surface type depending upon type of wiring.
17.7 The total load of lighting and power points have to be balanced after commissioning.
17.8 Point wiring for all areas shall be concealed in walls ceiling & under floors. Where ever false
ceiling is present point wiring shall be above false ceiling.
17.9 Telephone points shall be laid using 2 Pair 0.5 / 0.7 Sq. mm copper unarmored cable in
25mm conduits from the junction box / EPABX to the socket outlet. The sockets shall be RJ11
type (Anchor Roma /CPL/Equiv.)
Prior to laying & fixing of conduits, contractor shall carefully examine the layout drawing given
& prepare a detailed drawing showing conduit routing with sizes, No. of conduits per phase
(Min conduit size shall be 25mm.), no. of wires running in each Conduit Considering 25%
Spare space for future pulling, control switch location. The contractor shall take the approval
of all the drawings by the consultant prior to the installation of conduits.
For each lot of wire supply, contractor shall supply a certificate issued by the manufacturer
stating its Make (i.e. Finolex/Polycab, Date of manufacturer, insulation class & standards to
which it comply.)
Wiring shall be totally colour coded as per I.S. (Single phase- Red; Three phases-Red,
Yellow, Blue; Neutral- Black; Earth-Green.
IS 375- 1964 : Switchgear busbars, main connections and auxiliary wiring, making and
arrangement.
IS 2147 : Degrees of protection provided by enclosures for low voltage switchgear and
control gear.
IS 4237 : General requirements for switchgear and control gear for voltages not
exceeding 1000 V.
IS 8623 : Factory-built assemblies of switchgear and control gear for voltages upto
including 1000 V AC and 1200 V DC.
18.1 The DB’s shall be Pre fabricated, with 14 SWG CRCA sheet steel after 7 tanks pretreatment.
The frame of individual vertical panels shall be fabricated using pressed and shaped CRCA
sheet steel 14 SWG thickness or by using suitable mild steel structural sections. All load
bearing sections shall be of 14 SWG sheets. Doors shall be double door type of 14 SWG.
Only inside partitions shall be 16 SWG.
18.2 All hardware shall be corrosion resistant. All joints and connections of the panel members
shall be made by galvanized, zinc passivated or cadmium plated high quality steel bolts, nuts
and washers, secured against loosening.
18.3 DB’s shall be of front access type. All openings, covers & doors shall be provided with
neoprene gaskets round the perimeters to make the DB dust and vermin proof.
18.4 The cable entry shall be from top. DB’s shall be suitable for wall mounting. The degree of
protection shall be IP 52.
18.5 The DB’s shall be provided with 3 phase, 4 wire, and busbar system. Main busbars including
vertical droppers or risers of DB’s shall be electrical grade aluminum conforming to IS-5082.
The horizontal and vertical busbars in the switchgear shall be insulated with heat shrinkable
PVC Sleeves, Colour coded red, yellow, blue and black. The busbars in switchgear shall be
supported on SMC insulators. All hardware used in busbar connections shall be zinc
passivated. All busbar connections shall be provided with spring washers. Busbars should be
tightened to 35 KN/m2 to 50 KN / m2 by torque range.
18.6 For D.B’s with single & three phases outgoing there shall be separate Neutral links for all the
three phases.
18.7 In the event of switchgear giving the low I.R. value, switchgear shall be dried-up/ treated with
air drying as per the manufacturer’s recommendations to improve the I.R. value to the safe
value for commissioning. Earthing of the switchgear shall be done using the proper size of
conductors as per the relevant engineer’s documents.
18.8 Main busbars, bus risers shall be connected to fixed and outgoing terminals and bus systems
shall be totally enclosed by individually taping with not be less than five half-layer insulating
tapes on all busbars. The incomer, bus bar, O/G ways shall be completely segregated from
each other.
18.9 The DB’s shall be powder coated inside and outside. The shade shall be decided later. Total
thickness of painting shall be atleast 90-100 microns. The finished panels shall be dried in
staving ovens in dust free atmosphere. Panel finish shall be free of imperfections like
pinholes, orange peels, run off paint etc. All the side plates, front doors, internal plates shall
be powder coated.
18.10 Inside the DB, the wiring for power, control, signaling, protection and instrument circuits shall
be done with PVC insulated copper conductors. The insulation grade for these wires shall be
650/1100 volts. All control wiring shall be enclosed in plastic channels with the wires neatly
bunched together.
18.11 The LDB/ PDB incomers shall be with ELCB of rating & 100mamp sensitivity as mentioned in
BOQ. All O/G shall comprise ELCB for all the phases MCB’s shall be of 10 KA breaking
capacity with ‘G’ type characteristics. The MCB’s shall be TPN/ SPN, snap mounted on to the
DIN rail channel.
18.12 It shall be possible to replace any single MCB without disturbing the other MCB’s. There shall
be atleast 3 to 4 vacant spaces with DIN rail channel in the DB for mounting MCB’s in the
future. The rating & quantity of O/G ways shall be as specified in DB load schedule.
18.13 Name plate with necessary designation shall be fixed at the center of the DB. Engraved
nameplates giving feeder details shall be provided for each compartment. Nameplate shall be
of acrylic with white letters on black background.
18.14 All openings, covers & doors shall be provided with neoprene gaskets around the perimeters
to make the DB dust and vermin proof.
18.15 Tests shall be carried out on various equipment/ components mounted on the LDB/ PDB as
per relevant Indian Standard Specifications.
21.0 DEVIATIONS
Deviations from the specifications must be stated separately in writing at the quotation stage. In
the absence of such statement it will be assumed that the requirements of the specification are
met without exception.
All materials supplied by the Contractor shall be new and of approved quality manufactured by
approved vendors, conforming to Indian standards or to standards mentioned in the bill of
quantities. The materials shall have approved quality unless other wise approved by Consultants/
Engineer in charge prior to procurement and use. The Contractor shall furnish manufacturer’s
certificates for the materials supplied when asked for and shall get the materials tested, if asked
for, by the Engineer-in-charge. The cost of all tests and test certificates shall be borne by the
Contractor. No separate payment shall be made for testing.
All the liabilities of the contractor in terms of his payments of taxes, duties, salaries, wages etc.
Shall be contractors responsibility and contractors shall provide an affidavit, before final payment
is made to contractor,
25. MEASUREMENTS
Rates and measurements shall conform to the bill of quantities based on the detailed
specifications. Mode of measurements to be as specified under detailed specifications.
All measurements shall be computerized & of which soft & hard copy to be submitted to
Client and Consultants for each running bill. All bills will be accompanied by necessary
attachments and reconciliation statements. The bills, if not accompanied by necessary
attachments may be liable for rejection.
26. All statutory clearances like obtaining labor license, ESIC, P&F & Insurance are the sole
responsibility of Electrical contractor. All statutory approvals – photocopy to be submitted along
with 1st running bill. In absence of these documents1st running bill will not be cleared.
27. All material in contractor’s scope of supply will be inspected approved by Client / Consultant
before dispatch.
28 Contractors should quote for all items including rate only item. Some of these Rate only items may
be executed. The implication of cost of such items will be done by Consultants in techno –
commercial evaluation of bids. The discount to be passed on rate only items also at the time of
submission of price break up.
29. All bought out items will be covered under one year guarantee. We require guarantee certificate
from original manufacture as back-to-back arrangement. All defective parts will be replaced free
of cost within warranty period.
30. Contractor to arrange the scaffolding arrangement to erect the Electrical Fixtures up to 5.5 to 6.5
meter height. The scaffolding arrangement to have movable lockable wheel.
31. Good House keeping procedure has to be followed at site. All scrap & debris generated by
contactor to be cleaned regularly. If not done than the Penalty will be imposed by client.
32. Electrical Contractor to submit the As Built Drawing after the hand over the job. Final Bill will be
cleared after handing over AS BUILT Drawings.
33. The Cable wastage should not exceed 2.5%. Any short fall in cable issued to contractor & cable
Installed by contractor at site, after reconciliation of cable & other free issued items the excess qty
of wastage will be charged as per purchase rates of the Item & amount will be deducted from the
Contractors final Bill.
*******